Lenox
205 South Main, Lenox, IA 50851Plant Summary Information
Lenox is ranked #47 out of 89 distillate fuel oil power plants in Iowa in terms of total annual net electricity generation.
Lenox is comprised of 5 generators and generated 9.0 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Lenox |
|---|---|
| Utility Name | City of Lenox - (IA) |
| Location | Taylor County, IA |
| Initial Operation Date | September 1948 |
| Last Update | Dec 2024 |
| Annual Generation | 39.0 MWh |
| Annual Consumption | 551 MMBtu |
| Ranked #12,280 out of 12,539 Power Plants Nationwide | |
| Ranked #959 out of 1,236 Distillate Fuel Oil Power Plants Nationwide | |
| Ranked #240 out of 279 Iowa Power Plants | |
| Ranked #47 out of 89 Iowa Distillate Fuel Oil Power Plants | |
| Fuel Types | Distillate Fuel Oil |
Map of Lenox
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lenox.
Monthly Net Generation for Lenox
Lenox Details
| Summary Information | |
|---|---|
| Plant Name | Lenox (1158) |
| Plant Address | 205 South Main, Lenox, IA 50851 |
| Utility | City of Lenox - (IA) (10908) |
| Latitude, Longitude | 40.88, -94.5589 |
| Generation Dates on File | Jan 2002 to Dec 2024 |
| Initial Operation Date | September 1948 |
| Annual Generation | 39.0 MWh |
| Fuel Types | Distillate Fuel Oil |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Municipality |
| Ash Impoundment | No |
| Transmission / Distribution Owner | City of Lenox - (IA) (10908) IA |
| Grid Voltage | 34.50 kV |
| Energy Storage | No |
Generator 1 Details Standby September 1948
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.ALTW |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.ALTW |
| Nameplate Capacity | 0.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.3 MW |
| Winter Capacity | 0.3 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
|---|---|
| First Operation Date | September 1948 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 2 Details Standby March 1965
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.ALTW |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.ALTW |
| Nameplate Capacity | 1.1 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.1 MW |
| Winter Capacity | 1.1 MW |
| Minimum Load | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
|---|---|
| First Operation Date | March 1965 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 3 Details Standby March 1966
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.ALTW |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.ALTW |
| Nameplate Capacity | 0.9 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.9 MW |
| Winter Capacity | 0.9 MW |
| Minimum Load | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
|---|---|
| First Operation Date | March 1966 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 4 Details Standby October 2001
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.ALTW |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.ALTW |
| Nameplate Capacity | 1.8 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.7 MW |
| Winter Capacity | 1.8 MW |
| Minimum Load | 1.3 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
|---|---|
| First Operation Date | October 2001 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 5 Details Standby February 2016
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.ALTW |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.ALTW |
| Nameplate Capacity | 2 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.8 MW |
| Winter Capacity | 1.8 MW |
| Minimum Load | 1.3 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
|---|---|
| First Operation Date | February 2016 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Lenox Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #949 | Wayne IC | Wayne, NE | 43.0 MWh |
| #950 | Powell Valley | Kyles Ford, TN | 43.0 MWh |
| #951 | Encogen | Bellingham, WA | 593.2 GWh |
| #952 | South Hampton | Southampton, NY | 42.0 MWh |
| #953 | Anadarko | Woodsfield, OH | 42.0 MWh |
| #954 | West Point (PA) | West Point, PA | 272.0 GWh |
| #955 | Red Cloud | Red Cloud, NE | 41.0 MWh |
| #956 | Thomson Reuters Data Center Bldg H | Eagan, MN | 41.0 MWh |
| #957 | Walnut | Turlock, CA | 429.0 MWh |
| #958 | Alliant SBD 9201 Norplex | Postville, IA | 40.2 MWh |
| #960 | Truman | Truman, MN | 39.0 MWh |
| #961 | Knoxville Industrial | Knoxville, IA | 39.0 MWh |
| #962 | Winston | Lakeland, FL | 39.0 MWh |
| #963 | Shelby, NC | Shelby, NC | 39.0 MWh |
| #964 | University of Michigan | Ann Arbor, MI | 208.5 GWh |
| #965 | MNDOT Standby Generation | St. Paul, MN | 38.0 MWh |
| #966 | St Johns Riverside Hospital | Yonkers, NY | 38.0 MWh |
| #967 | Lake Mills | Lake Mills, IA | 38.0 MWh |
| #968 | West Liberty | West Liberty, IA | 38.0 MWh |
| #969 | Waterloo Lundquist | Waterloo, IA | 38.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lenox.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Adams Wind | Lenox, IA | 474.5 GWh | 6.5 mi |
| August Wind Farm | Clearfield, IA | 6.5 GWh | 9.1 mi |
| Birch | Clearfield, IA | 6.9 GWh | 8.9 mi |
| Bulldog | Orient, IA | 4.1 GWh | 24.7 mi |
| Contrail Wind Farm | Bedford, IA | 309.8 GWh | 20.5 mi |
| Corning | Corning, IA | 51.0 MWh | 11.8 mi |
| Creston Solar (50 MW) | Creston, IA | 96.1 GWh | 18.2 mi |
| Cumberland Rose | Orient, IA | 5.2 GWh | 24.8 mi |
| Downtown Generation Plant | Greenfield, IA | 58.0 MWh | 29.7 mi |
| Fontanelle | Fontanelle, IA | 5.7 GWh | 31.7 mi |
| Greenfield Wind | Greenfield, IA | 5.3 GWh | 28.6 mi |
| North Generation Plant | Greenfield, IA | 105.0 MWh | 30.6 mi |
| Orient Wind Farm | Orient, IA | 1.8 TWh | 23.5 mi |
| POET Biorefining LLC - Corning | Corning, IA | 14.0 GWh | 13.7 mi |
| Prescott Wind Farm | Prescott, IA | 144.0 GWh | 16.8 mi |
| Rolling Hills Wind Farm | Massena, IA | 1.6 TWh | 24.6 mi |
| Sky Volt | Greenfield, IA | 5.1 GWh | 28.6 mi |
| Southern Hills Wind Farm | Creston, IA | 827.8 GWh | 16.7 mi |
| Summit Lake | Creston, IA | 70.0 GWh | 19.6 mi |
| Villisca Municipal Power Plant | Villisca, IA | 7.0 MWh | 22.6 mi |