Glaciers Edge Wind Project
808 450th St., Cleghorn, IA 51035Plant Summary Information
Glaciers Edge Wind Project is ranked #23 out of 279 power plants in Iowa in terms of total annual net electricity generation.
Glaciers Edge Wind Project generated 158.8 GWh during the 3-month period between April 2025 to July 2025.
Plant Name | Glaciers Edge Wind Project |
---|---|
Utility Name | EDF Renewable Asset Holdings, Inc. |
Location | Cherokee County, IA |
Initial Operation Date | December 2019 |
Last Update | Jul 2025 |
Annual Generation | 857.0 GWh |
Annual Consumption | 3.0 M MMBtu |
Ranked #839 out of 12,530 Power Plants Nationwide | |
Ranked #109 out of 1,360 Wind Power Plants Nationwide | |
Ranked #23 out of 279 Iowa Power Plants | |
Ranked #13 out of 123 Iowa Wind Power Plants | |
Fuel Types | Wind |
Previous Operator |
Glaciers Edge Wind Project LLC (2018 to 2018) EDF Renewable Asset Holdings, Inc. (2019 to 2024) |
Map of Glaciers Edge Wind Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Glaciers Edge Wind Project.
Monthly Net Generation for Glaciers Edge Wind Project
Glaciers Edge Wind Project Details
Summary Information | |
---|---|
Plant Name | Glaciers Edge Wind Project (62035) |
Plant Address | 808 450th St., Cleghorn, IA 51035 |
Utility | EDF Renewable Asset Holdings, Inc. (57170) |
Latitude, Longitude | 42.862, -95.772 |
Generation Dates on File | Dec 2019 to Jul 2025 |
Initial Operation Date | December 2019 |
Annual Generation | 857.0 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | EG19-69 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | MidAmerican Energy Co (12341) IA |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator GEW Details Operating December 2019
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 211.7 MW |
Summer Capacity | 200 MW |
Winter Capacity | 200 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2019 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 82 |
Turbine Details | |
Number Of Turbines | 82 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 2.5-127 |
Design Wind Speed | 18.6 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 292 |
Glaciers Edge Wind Project Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#99 | Thunder Ranch Wind Project | Marland, OK | 881.7 GWh |
#100 | Maverick Wind Project, LLC | Meno, OK | 879.8 GWh |
#101 | Dermott Wind | Snyder, TX | 876.2 GWh |
#102 | O'Brien Wind | Primghar, IA | 875.9 GWh |
#103 | Prevailing Wind Park | Lesterville, SD | 869.3 GWh |
#104 | Tecolote Wind LLC | Duran, NM | 868.6 GWh |
#105 | Willow Springs Wind Farm | Weinert, TX | 863.3 GWh |
#106 | Grandview Wind Farm, LLC | Panhandle, TX | 861.5 GWh |
#107 | Crowned Ridge Wind II Energy Center | Watertown, SD | 861.5 GWh |
#108 | Buffalo Dunes Wind Project | Satanta, KS | 858.3 GWh |
#110 | Las Majadas Wind Farm | Santa Monica, TX | 855.7 GWh |
#111 | Clearwater Wind East | Miles City, MT | 855.2 GWh |
#112 | Diamond Trail Wind Farm | Ladora, IA | 854.4 GWh |
#113 | Blazing Star Wind Farm 1 | Hendricks, MN | 853.9 GWh |
#114 | Blazing Star 2 Wind Farm | Hendricks, MN | 851.7 GWh |
#115 | White Cloud Wind Project, LLC | Tarkio, MO | 851.6 GWh |
#116 | Southern Hills Wind Farm | Creston, IA | 849.3 GWh |
#117 | Skeleton Creek Energy Center Hybrid | Carrier, OK | 844.9 GWh |
#118 | Plum Creek Wind Project (NE) | Winside, NE | 841.6 GWh |
#119 | Eclipse Wind Farm | Adair, IA | 840.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Glaciers Edge Wind Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alta Municipal Utilities | Alta, IA | 70.0 MWh | 27.1 mi |
Earl F Wisdom | Spencer, IA | 7.1 GWh | 33.2 mi |
Flying Cloud Power Partners LLC | Lake Park, IA | 81.0 GWh | 43.6 mi |
Highland Wind Project (IA) | Primghar, IA | 1.7 TWh | 16.2 mi |
Ida Grove II | Ida Grove, IA | 725.6 GWh | 40.3 mi |
Ida Grove Wind | Ida Grove, IA | 1.1 TWh | 39.3 mi |
Intrepid | Schaller, IA | 549.4 GWh | 31 mi |
Lost Lakes Wind Farm LLC | Lake Park, IA | 243.7 GWh | 40.4 mi |
O'Brien Wind | Primghar, IA | 875.9 GWh | 24.5 mi |
Osceola Windpower II | Harris, IA | 203.1 GWh | 43.2 mi |
Osceola Windpower LLC | Harris, IA | 401.0 GWh | 43.2 mi |
Otter Creek Ethanol Poet - Ashton | Ashton, IA | 43.2 GWh | 28.6 mi |
Plymouth Wind | Remsen, IA | 801.3 GWh | 8.7 mi |
POET Biorefining - Hudson | Hudson, SD | 17.0 GWh | 39.2 mi |
Sibley No Two | Sibley, IA | 38.0 MWh | 37 mi |
Sibley One | Sibley, IA | 42.0 MWh | 37.6 mi |
Spencer Gas Turbine | Spencer, IA | 651.0 MWh | 37.2 mi |
Storm Lake 1 | Alta, IA | 84.7 GWh | 22.2 mi |
Storm Lake II | Alta, IA | 114.2 GWh | 18.6 mi |
Upland Prairie | Spencer, IA | 1.1 TWh | 32 mi |