Fort Churchill
1000 Sierra Way, Yerington, NV 89447Plant Summary Information
Fort Churchill is ranked #22 out of 110 power plants in Nevada in terms of total annual net electricity generation.
Fort Churchill is comprised of 2 generators and generated 134.0 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Fort Churchill |
|---|---|
| Utility Name | Sierra Pacific Power Co |
| Location | Lyon County, NV |
| Initial Operation Date | September 1968 |
| Last Update | Dec 2025 |
| Annual Generation | 468.8 GWh |
| Annual Consumption | 6.2 M MMBtu |
| Ranked #1,419 out of 12,613 Power Plants Nationwide | |
| Ranked #573 out of 2,246 Natural Gas Power Plants Nationwide | |
| Ranked #22 out of 110 Nevada Power Plants | |
| Ranked #9 out of 18 Nevada Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of Fort Churchill
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fort Churchill.
Monthly Net Generation for Fort Churchill
Monthly Plant Fuel Consumption for Fort Churchill
Fort Churchill Details
| Summary Information | |
|---|---|
| Plant Name | Fort Churchill (2330) |
| Plant Address | 1000 Sierra Way, Yerington, NV 89447 |
| Utility | Sierra Pacific Power Co (17166) |
| Latitude, Longitude | 39.1281, -119.1322 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | September 1968 |
| Annual Generation | 468.8 GWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | Nevada Power Company (NEVP) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Wells |
| Ash Impoundment | |
| Transmission / Distribution Owner | Sierra Pacific Power Co (17166) NV |
| Grid Voltage | 120.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | SOUTHWEST GAS CORPORATION |
| Natural Gas Storage | No |
Generator 1 Details Operating September 1968
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 115 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 113 MW |
| Winter Capacity | 113 MW |
| Minimum Load | 18 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | September 1968 |
| Planned Retirement | September 2028 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating September 1971
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 115 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 113 MW |
| Winter Capacity | 113 MW |
| Minimum Load | 18 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | September 1971 |
| Planned Retirement | September 2028 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Fort Churchill Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #563 | Oleander Power Project LP | Cocoa, FL | 488.9 GWh |
| #564 | Mustang | Oklahoma City, OK | 491.4 GWh |
| #565 | Thomas Fitzhugh | Ozark, AR | 484.4 GWh |
| #566 | Oxnard | Oxnard, CA | 482.0 GWh |
| #567 | Mountain Creek | Dallas, TX | 479.5 GWh |
| #568 | SABIC Innovative Plastics Mt. Vernon | Mount Vernon, IN | 478.4 GWh |
| #569 | Masspower | Indian Orchard, MA | 475.7 GWh |
| #570 | Shady Hills Generating Station | Shady Hills, FL | 481.2 GWh |
| #571 | Victoria Texas Plant | Victoria, TX | 472.4 GWh |
| #572 | South Belridge Cogeneration Facility | McKittrick, CA | 469.3 GWh |
| #574 | Richard M Flynn | Holtsville, NY | 469.0 GWh |
| #575 | Georgetown | Indianapolis, IN | 466.1 GWh |
| #576 | Mansfield Mill | Mansfield, LA | 859.4 GWh |
| #577 | Roseville Energy Park | Roseville, CA | 461.9 GWh |
| #578 | Permian Basin | Monahans, TX | 464.5 GWh |
| #579 | Afton Generating Station | La Mesa, NM | 460.1 GWh |
| #580 | Astoria Station | Astoria, SD | 455.4 GWh |
| #581 | International Paper Riverdale Mill | Selma, AL | 562.2 GWh |
| #582 | Gary Works | Gary, IN | 950.4 GWh |
| #583 | Ocotillo | Tempe, AZ | 443.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Fort Churchill.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Fleish | Fleish, NV | 21.2 GWh | 27 mi |
| Ft. Churchill PV | Yerington, NV | 22.2 GWh | 0.4 mi |
| Galena 2 Geothermal Power Plant | Reno, NV | 36.7 GWh | 37.8 mi |
| Galena 3 Geothermal Power Plant | Reno, NV | 82.6 GWh | 37.6 mi |
| Lahontan | Fallon, NV | 10.0 GWh | 23.4 mi |
| New Lahontan | Fallon, NV | 10.5 GWh | 23.5 mi |
| Patua Acquisition Project, LLC | Hazen, NV | 133.5 GWh | 31.8 mi |
| Salt Wells | Fallon, NV | 70.0 GWh | 32.1 mi |
| Soda Lake 3 | Fallon, NV | 118.1 GWh | 33.1 mi |
| Steamboat Hills LP | Reno, NV | 231.7 GWh | 37.9 mi |
| Steamboat II | Reno, NV | 62.7 GWh | 37.7 mi |
| Steamboat III | Reno, NV | 69.4 GWh | 37.7 mi |
| Tesla Reno GigaFactory | Sparks, NV | 8.7 GWh | 32.8 mi |
| Tracy | Sparks, NV | 4.0 TWh | 36.6 mi |
| Turquoise Nevada, LLC | Sparks, NV | 108.7 GWh | 37.3 mi |
| Verdi | Verdi, NV | 19.0 GWh | 27.4 mi |
| Washoe | Verdi, NV | 14.4 GWh | 25.9 mi |
| Waste Management Lockwood LFGTE | Sparks, NV | 25.8 GWh | 36.3 mi |
| Western 102 Power Plant | McCarran, NV | 406.2 GWh | 36.1 mi |
| Whitegrass No. 1 | Yerington, NV | 17.7 GWh | 3.5 mi |