Cosumnes Power Plant
Twin Cities Rd., Herald, CA 95638Plant Summary Information
Cosumnes Power Plant is ranked #6 out of 1,607 power plants in California in terms of total annual net electricity generation.
Cosumnes Power Plant is comprised of 3 generators and generated 451.7 GWh during the 3-month period between March 2026 to June 2026.
| Plant Name | Cosumnes Power Plant |
|---|---|
| Utility Name | Sacramento Municipal Util Dist |
| Location | Sacramento County, CA |
| Initial Operation Date | February 2006 |
| Last Update | Jun 2026 |
| Annual Generation | 3.1 TWh |
| Annual Consumption | 23.6 M MMBtu |
| Ranked #380 out of 13,094 Power Plants Nationwide | |
| Ranked #222 out of 2,208 Natural Gas Power Plants Nationwide | |
| Ranked #6 out of 1,607 California Power Plants | |
| Ranked #4 out of 316 California Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 99.0% Other Biomass Gas : 1.0% |
Map of Cosumnes Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cosumnes Power Plant.
Monthly Net Generation for Cosumnes Power Plant
Monthly Plant Fuel Consumption for Cosumnes Power Plant
Cosumnes Power Plant Details
| Summary Information | |
|---|---|
| Plant Name | Cosumnes Power Plant (55970) |
| Plant Address | Twin Cities Rd., Herald, CA 95638 |
| Utility | Sacramento Municipal Util Dist (16534) |
| Latitude, Longitude | 38.33848, -121.12398 |
| Generation Dates on File | Mar 2006 to Jun 2026 |
| Initial Operation Date | February 2006 |
| Annual Generation | 3.1 TWh |
| Fuel Types | Natural Gas : 99.0% Other Biomass Gas : 1.0% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | Balancing Authority of Northern California (BANC) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Folsom South |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Sacramento Municipal Util Dist (16534) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | PACIFIC GAS |
| Natural Gas Storage | No |
Generator 1 Details Operating February 2006
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | CCC1 |
| Ownership | Single Owner |
| Duct Burners | No |
| Nameplate Capacity | 190 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 171 MW |
| Winter Capacity | 178.6 MW |
| Minimum Load | 160 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2006 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating February 2006
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CCC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | Yes |
| Nameplate Capacity | 196.8 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 185 MW |
| Winter Capacity | 202 MW |
| Minimum Load | 160 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2006 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Other Biomass Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | No |
| Multifuel Details | |
| Cofire Energy Source | NG / OBG |
|---|---|
Generator 3 Details Operating February 2006
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CCC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | Yes |
| Nameplate Capacity | 170 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 189 MW |
| Winter Capacity | 201 MW |
| Minimum Load | 160 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2006 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Cosumnes Power Plant Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #212 | High Bridge | St. Paul, MN | 3.2 TWh |
| #213 | Rhode Island State Energy Center | Johnston, RI | 3.1 TWh |
| #214 | Pastoria Energy Facility, LLC | Lebec, CA | 3.1 TWh |
| #215 | Harquahala Generating Project | Tonopah, AZ | 3.1 TWh |
| #216 | Gila River Power Block 3 | Gila Bend, AZ | 3.1 TWh |
| #217 | Marshall (NC) | Terrell, NC | 7.7 TWh |
| #218 | R D Morrow | Purvis, MS | 3.1 TWh |
| #219 | Birdsboro Power | Birdsboro, PA | 3.1 TWh |
| #220 | Wolf Hollow I LP | Granbury, TX | 3.1 TWh |
| #221 | Quail Run Energy Center | Odessa, TX | 3.1 TWh |
| #223 | Northeastern | Oologah, OK | 4.0 TWh |
| #224 | Ingleside Cogeneration | Houston, TX | 3.1 TWh |
| #225 | Harry Allen | Las Vegas, NV | 3.0 TWh |
| #226 | Marshalltown Generating Station | Marshalltown, IA | 3.0 TWh |
| #227 | Nelson Energy Center | Rock Falls, IL | 3.0 TWh |
| #228 | Decatur Energy Center | Decatur, AL | 3.0 TWh |
| #229 | Attala | Sallis, MS | 3.0 TWh |
| #230 | Mesquite Generating Station Block 1 | Arlington, AZ | 3.0 TWh |
| #231 | Harrison County Power Project | Marshall, TX | 3.0 TWh |
| #232 | ANP Bellingham Energy Project | Bellingham, MA | 2.9 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cosumnes Power Plant.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bear Creek Solar (Lodi) | Lodi, CA | 3.9 GWh | 14 mi |
| Camanche | Clements & Wallace, CA | 17.1 GWh | 9.4 mi |
| Kiefer Landfill | Sloughhouse, CA | 34.6 GWh | 12.7 mi |
| Kiefer Landfill Generating Phase II | Sloughhouse, CA | 30.2 GWh | 12.7 mi |
| Oaks HOA | Ione, CA | 1.7 GWh | 11.6 mi |
| Rancho Seco Solar II, LLC | Twin Cities, CA | 268.6 GWh | 0.6 mi |
| Rancho Seco Solar, LLC | Herald, CA | 18.0 GWh | 0.5 mi |
| RE Dillard 1 LLC | Sloughhouse, CA | 4.9 GWh | 9.5 mi |
| RE Dillard 2 LLC | Sloughhouse, CA | 5.9 GWh | 9.3 mi |
| RE Dillard 3 LLC | Sloughhouse, CA | 5.9 GWh | 9.1 mi |
| RE McKenzie 1 LLC | Galt, CA | 11.6 GWh | 9.6 mi |
| RE McKenzie 2 LLC | Galt, CA | 11.6 GWh | 9.6 mi |
| RE McKenzie 3 LLC | Galt, CA | 11.6 GWh | 9.6 mi |
| RE McKenzie 4 LLC | Galt, CA | 11.6 GWh | 9.6 mi |
| RE McKenzie 5 LLC | Galt, CA | 11.6 GWh | 9.6 mi |
| RE McKenzie 6 LLC | Galt, CA | 11.6 GWh | 9.6 mi |
| Renew Solar ABC Sacramento LLC | Sacramento, CA | 2.7 GWh | 10.1 mi |
| SloughHouse Solar, LLC | SloughHouse, CA | 113.3 GWh | 9.5 mi |
| SMUD at Fleshman | Galt, CA | 3.9 GWh | 13.5 mi |
| SMUD at Van Conett | Galt, CA | 5.0 GWh | 10.3 mi |