Cokato CSG
4628 Quimby Ave SW, Cokato, MN 55321Plant Summary Information
Cokato CSG is ranked #77 out of 504 solar farms in Minnesota in terms of total annual net electricity generation.
Cokato CSG generated 1.1 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Cokato CSG |
|---|---|
| Utility Name | Cokato Holdco LLC |
| Location | Wright County, MN |
| Initial Operation Date | August 2021 |
| Last Update | Dec 2024 |
| Annual Generation | 8.0 GWh |
| Annual Consumption | 29.3 k MMBtu |
| Ranked #6,870 out of 12,529 Power Plants Nationwide | |
| Ranked #2,359 out of 6,390 Solar Power Plants Nationwide | |
| Ranked #205 out of 758 Minnesota Power Plants | |
| Ranked #77 out of 504 Minnesota Solar Power Plants | |
| Fuel Types | Solar |
Map of Cokato CSG
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cokato CSG.
Monthly Net Generation for Cokato CSG
Cokato CSG Details
| Summary Information | |
|---|---|
| Plant Name | Cokato CSG (64506) |
| Plant Address | 4628 Quimby Ave SW, Cokato, MN 55321 |
| Utility | Cokato Holdco LLC (64148) |
| Latitude, Longitude | 45.08723, -94.21561 |
| Generation Dates on File | Aug 2021 to Dec 2024 |
| Initial Operation Date | August 2021 |
| Annual Generation | 8.0 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | QF21-683 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Northern States Power Co - Minnesota (13781) MN |
| Grid Voltage | 0.48 kV |
| Energy Storage | No |
Generator COK Details Operating August 2021
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 4 MW |
| Summer Capacity | 4 MW |
| Winter Capacity | 4 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | August 2021 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 25 |
| DC Net Capacity | 5 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | Yes |
| Virtual Net Metering DC Capacity | 5 MW |
Cokato CSG Plant Owners
| Owner Name | Address | Ownership | |
|---|---|---|---|
| We couldn't locate any owners for this plant | |||
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #2349 | Walt Disney World Solar Facility | Orlando, FL | 8.0 GWh |
| #2350 | OYA Wayside Drive | Watertown, NY | 8.0 GWh |
| #2351 | Jacob Solar | Reidsville, NC | 8.0 GWh |
| #2352 | Randall Solar Project Hybrid | Berlin, MA | 7.9 GWh |
| #2353 | Held Solar Project | Waite Park, MN | 8.0 GWh |
| #2354 | ELP Claverack Solar | Claverack, NY | 8.0 GWh |
| #2355 | SunE Feely 1 CSG, LLC | Farmington, MN | 8.0 GWh |
| #2356 | Niagara Bottling - Seguin | Seguin, TX | 8.0 GWh |
| #2357 | Farmington Holdco Solar | Farmington, MN | 8.0 GWh |
| #2358 | Owen Solar | Lincolnton, NC | 8.0 GWh |
| #2360 | Taylors Falls CSG | Taylor Falls, MN | 8.0 GWh |
| #2361 | Gliden (Op Zone) | Tyner, NC | 8.0 GWh |
| #2362 | Northumberland Solar | Milton, PA | 8.0 GWh |
| #2363 | CalCity Solar 1 | California City, CA | 7.9 GWh |
| #2364 | Market Farm | Reidsville, NC | 7.9 GWh |
| #2365 | CBEP Solar 4, LLC | Milliken, CO | 7.9 GWh |
| #2366 | Saratoga Solar LLC | Milton, NY | 7.9 GWh |
| #2367 | Sangerfield Solar CSG | Waterville, NY | 7.9 GWh |
| #2368 | Cortlandville III Solar CSG | Cortland, NY | 7.9 GWh |
| #2369 | Canal Energy S23, LLC | Hanford, CA | 7.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cokato CSG.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Andromeda Community Solar | Lester Prairie, MN | 8.3 GWh | 15.6 mi |
| Annandale Solar | Annandale, MN | 12.2 GWh | 12.2 mi |
| Barone CSG | Winstead, MN | 1.9 GWh | 12 mi |
| Crane Garden | Lester Prairie, MN | 2.2 GWh | 15.2 mi |
| FastSun 1 CSG | Dassel, MN | 1.8 GWh | 4.6 mi |
| Honeysuckle Solar, LLC | Lester Prairie, MN | 2.0 GWh | 15.5 mi |
| Hutchinson Plant #1 | Hutchinson, MN | 35.7 GWh | 15.2 mi |
| Hutchinson Plant #2 | Hutchinson, MN | 1.4 GWh | 15.2 mi |
| Laurel Village (CSG) | Cokato, MN | 1.6 GWh | 1.8 mi |
| Litchfield | Litchfield, MN | 143.0 MWh | 15.8 mi |
| Maple Lake | Maple Lake, MN | 176.0 MWh | 14 mi |
| Meeker Community Solar One LLC CSG | Dassel, MN | 1.8 GWh | 4.6 mi |
| Montgomery Winsted CSG | Winsted, MN | 5.1 GWh | 12.2 mi |
| Montrose Solar | Montrose, MN | 6.6 GWh | 14.5 mi |
| MontSun Community Solar | Montrose, MN | 8.7 GWh | 15.3 mi |
| Nautilus Winsted Solar (CSG) | Winsted, MN | 5.6 GWh | 11.5 mi |
| Novel Martin Solar One LLC (McLeod) CSG | Lester Prairie, MN | 1.6 GWh | 15.7 mi |
| South Garden | Winstead, MN | 2.2 GWh | 11.7 mi |
| USS Water Fowl Solar LLC CSG | Silver Lake, MN | 908.0 MWh | 12.8 mi |
| WaveSun Community Solar | Waverly, MN | 7.7 GWh | 11.6 mi |