431 Premier Drive, Clyde, OH 43410Plant Summary Information
Clyde Peaking Engine is ranked #15 out of 56 distillate fuel oil power plants in Ohio in terms of total annual net electricity generation.
Clyde Peaking Engine is comprised of 1 generator and generated 164.7 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Clyde Peaking Engine |
---|---|
Utility Name | AEP Onsite Partners, LLC |
Location | Sandusky County, OH |
Initial Operation Date | November 2020 |
Last Update | Dec 2023 |
Annual Generation | 540.0 MWh |
Annual Consumption | 14.3 k MMBtu |
Ranked #11,001 out of 11,825 Power Plants Nationwide | |
Ranked #509 out of 1,263 Distillate Fuel Oil Power Plants Nationwide | |
Ranked #144 out of 182 Ohio Power Plants | |
Ranked #15 out of 56 Ohio Distillate Fuel Oil Power Plants | |
Fuel Types | Distillate Fuel Oil |
Map of Clyde Peaking Engine
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Clyde Peaking Engine.
Monthly Net Generation for Clyde Peaking Engine
Clyde Peaking Engine Details
Summary Information | |
---|---|
Plant Name | Clyde Peaking Engine (64157) |
Plant Address | 431 Premier Drive, Clyde, OH 43410 |
Utility | AEP Onsite Partners, LLC (60571) |
Latitude, Longitude | 41.29329, -82.96526 |
Generation Dates on File | Nov 2020 to Dec 2023 |
Initial Operation Date | November 2020 |
Annual Generation | 540.0 MWh |
Fuel Types | Distillate Fuel Oil |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Clyde Light & Power (3824) OH |
Grid Voltage | 12.48 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | COLUMBIA GAS OF OHIO |
Natural Gas Storage | No |
Generator CPG Details Operating November 2020
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 10 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 10 MW |
Winter Capacity | 10 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | November 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Clyde Peaking Engine Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#499 | Cascade Creek | Rochester, MN | 38.7 GWh |
#500 | Diesel Generators | Madison, WI | 569.0 MWh |
#501 | Glenwood | Glenwood Landing, NY | 568.0 MWh |
#502 | Edward L. Addison Generating Plant | Thomaston, GA | 200.2 GWh |
#503 | Bridge Street 1 & 2 | Groton, CT | 562.0 MWh |
#504 | Industrial Park | Rock Falls, IL | 561.0 MWh |
#505 | Montville Station | Uncasville, CT | 36.2 GWh |
#506 | Castleton Energy Center | Castleton, NY | 89.9 GWh |
#507 | J K Smith | Winchester, KY | 619.4 GWh |
#508 | Covanta Babylon Inc | West Babylon, NY | 121.7 GWh |
#510 | York Energy Center | Delta, PA | 8.8 TWh |
#511 | Montpelier Electric Generating Station | Poneto, IN | 142.8 GWh |
#512 | Cape Gas Turbine | Portland, ME | 532.0 MWh |
#513 | Nottoway Diesel Generating Facility | Courtland, VA | 525.0 MWh |
#514 | PSEG Sewaren Generating Station | Sewaren, NJ | 2.8 TWh |
#515 | Naval Submarine Base Kings Bay | Kings Bay, GA | 517.1 MWh |
#516 | False Island | Thorne Bay, AK | 513.0 MWh |
#517 | Packaging Corp. of America Jackson Mill | Jackson, AL | 158.4 GWh |
#518 | Seward (AK) | Seward, AK | 507.0 MWh |
#519 | Indiana University of Pennsylvania | Indiana, PA | 18.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Clyde Peaking Engine.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bowling Green Generating Station | Bowling Green, OH | 2.1 GWh | 35.8 mi |
Bowling Green Peaking | Bowling Green, OH | 1.5 GWh | 35.6 mi |
Buckeye Power Inc. | Marion, OH | 3.9 GWh | 34.6 mi |
Clyde Solar Array | Clyde, OH | 3.9 GWh | 2.1 mi |
Davis Besse | Oak Harbor, OH | 7.4 TWh | 21.9 mi |
DG AMP Solar Bowling Green | Bowling Green, OH | 39.4 GWh | 32.8 mi |
Energy Developments, Hancock | Findlay, OH | 21.4 GWh | 27.9 mi |
Fremont Energy Center | Fremont, OH | 3.6 TWh | 11.7 mi |
Genoa Diesel Generating Station | Genoa, OH | 130.0 MWh | 25.3 mi |
Monroeville RTO BTM | Monroeville, OH | 83.0 MWh | 13.7 mi |
Monroeville Solar | Monroeville, OH | 4.0 GWh | 13.9 mi |
Oregon Clean Energy Center | Oregon, OH | 6.5 TWh | 35.8 mi |
POET Biorefining - Fostoria | Fostoria, OH | 21.5 GWh | 23 mi |
Renewable Energy Services of Ohio | Milan, OH | 11.1 GWh | 19.1 mi |
Shelby North | Shelby, OH | 23.0 MWh | 31.6 mi |
Shelby Solar Array | Shelby, OH | 2.5 GWh | 31.4 mi |
Shelby South | Shelby, OH | 37.0 MWh | 31.1 mi |
Troy Energy LLC | Luckey, OH | 821.7 GWh | 28.6 mi |
Woodville RTO BTM | Woodville, OH | 75.0 MWh | 23.8 mi |
Wyandot Solar Farm | Upper Sandusky, OH | 10.7 GWh | 34 mi |