Carson Ice-Gen Project
Franklin Blvd, Sacramento, CA 95758Plant Summary Information
Carson Ice-Gen Project is ranked #71 out of 346 natural gas power plants in California in terms of total annual net electricity generation.
Carson Ice-Gen Project is comprised of 3 generators and generated 29.8 GWh during the 3-month period between November 2024 to February 2025.
Plant Name | Carson Ice-Gen Project |
---|---|
Utility Name | Sacramento Municipal Util Dist |
Location | Sacramento County, CA |
Initial Operation Date | October 1995 |
Last Update | Feb 2025 |
Annual Generation | 116.5 GWh |
Annual Consumption | 1.1 M MMBtu |
Ranked #3,083 out of 11,993 Power Plants Nationwide | |
Ranked #871 out of 2,253 Natural Gas Power Plants Nationwide | |
Ranked #343 out of 1,579 California Power Plants | |
Ranked #71 out of 346 California Natural Gas Power Plants | |
Fuel Types | Natural Gas : 99.9% |
Map of Carson Ice-Gen Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Carson Ice-Gen Project.
Monthly Net Generation for Carson Ice-Gen Project
Carson Ice-Gen Project Details
Summary Information | |
---|---|
Plant Name | Carson Ice-Gen Project (7527) |
Plant Address | Franklin Blvd, Sacramento, CA 95758 |
Utility | Sacramento Municipal Util Dist (16534) |
Latitude, Longitude | 38.44568, -121.46239 |
Generation Dates on File | Jan 2001 to Feb 2025 |
Initial Operation Date | October 1995 |
Annual Generation | 116.5 GWh |
Fuel Types | Natural Gas : 99.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Balancing Authority of Northern California (BANC) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Sacramento County Water |
Ash Impoundment | No |
Transmission / Distribution Owner | Sacramento Municipal Util Dist (16534) CA |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | PACIFIC GAS |
Natural Gas Storage | No |
Generator 1 Details Operating October 1995
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 54 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 41.2 MW |
Winter Capacity | 41.2 MW |
Minimum Load | 20 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1995 |
---|---|
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 2 Details Operating October 1995
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Wholly Owned by Other Entity |
Duct Burners | Yes |
Nameplate Capacity | 17.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 16.6 MW |
Winter Capacity | 16.6 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1995 |
Combined Heat & Power | Yes |
Sector Name | Electric Utility (1) |
Topping Or Bottoming | T |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator CCCT Details Operating October 1995
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Wholly Owned by Other Entity |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 54 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 51.2 MW |
Winter Capacity | 51.2 MW |
Minimum Load | 21 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 1995 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Other Biomass Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | NG / OBG |
---|
Carson Ice-Gen Project Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Central Valley Financing Auth | PO Box 15830, Sacramento, CA 95852 | Generator 1 | 100.00% |
Central Valley Financing Auth | PO Box 15830, Sacramento, CA 95852 | Generator 2 | 100.00% |
Central Valley Financing Auth | PO Box 15830, Sacramento, CA 95852 | Generator CCCT | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#861 | Algonquin Windsor Locks | Windsor Locks, CT | 120.3 GWh |
#862 | Sumpter | Belleville, MI | 120.0 GWh |
#863 | Concord | Watertown, WI | 119.8 GWh |
#864 | Energy Center Dover | Dover, DE | 119.9 GWh |
#865 | Purdue University | West Lafayette, IN | 129.8 GWh |
#866 | Millcreek Power Generation | St. George, UT | 118.6 GWh |
#867 | Pittsburgh Airport Gas Plant | Coraopolis, PA | 118.4 GWh |
#868 | Marion | Marion, IL | 755.0 GWh |
#869 | D G Hunter | Alexandria, LA | 117.8 GWh |
#870 | Ray Olinger | Navada, TX | 117.4 GWh |
#872 | Marsh Landing Generating Station | Antioch, CA | 116.4 GWh |
#873 | Chamon Power LLC | Houston, TX | 116.3 GWh |
#874 | WFEC GenCo LLC | Anadarko, OK | 115.4 GWh |
#875 | Mid-Georgia Cogeneration Facility | Kathleen, GA | 125.0 GWh |
#876 | San Jacinto County Peaking Facility | Shepherd, TX | 115.1 GWh |
#877 | Victoria Port Power II LLC | Victoria, TX | 114.7 GWh |
#878 | Kansas Ethanol, LLC | Lyons, KS | 113.4 GWh |
#879 | Lordsburg Generating | Lordsburg, NM | 113.3 GWh |
#880 | AL Sandersville LLC | Warthen, GA | 112.9 GWh |
#881 | Decker Creek | Austin, TX | 112.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Carson Ice-Gen Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Department of Justice | Sacramento, CA | 4.1 GWh | 7.1 mi |
Depot Park Solar System | Sacramento, CA | 2.4 GWh | 5.9 mi |
Dept of General Services -FTB | Sacramento, CA | 5.3 GWh | 10.5 mi |
FRV SI Transport Solar LP | Sacramento, CA | 1.3 GWh | 4.8 mi |
RE Bruceville 1 LLC | Elk Grove, CA | 10.8 GWh | 7.3 mi |
RE Bruceville 2 LLC | Elk Grove, CA | 10.7 GWh | 7.3 mi |
RE Bruceville 3 LLC | Elk Grove, CA | 11.1 GWh | 7.3 mi |
RE Kammerer 1 LLC | Elk Grove, CA | 11.3 GWh | 7.1 mi |
RE Kammerer 2 LLC | Elk Grove, CA | 11.3 GWh | 7.1 mi |
RE Kammerer 3 LLC | Elk Grove, CA | 11.3 GWh | 7.1 mi |
Renew Solar ABC Sacramento LLC | Sacramento, CA | 2.9 GWh | 9.7 mi |
Sacramento (SMUD) | Sacramento, CA | 2.1 GWh | 9.8 mi |
Sacramento Fairbain Water Treatment Plant | Sacramento, CA | 1.1 GWh | 7.9 mi |
Sacramento Point West Medical Offices | Sacramento, CA | 2.2 GWh | 10.6 mi |
Sacramento Regional County Sanitation PV | Elk Grove, CA | 7.4 GWh | 0.2 mi |
SCA Cogen 2 | Sacramento, CA | 607.1 GWh | 6.8 mi |
SMUD at Grundman | Elk Grove, CA | 24.2 GWh | 6.2 mi |
SMUD at Lawrence | Elk Grove, CA | 4.2 GWh | 7.6 mi |
Solar Star California II LLC | Sacramento, CA | 3.5 GWh | 4.9 mi |
SPA Cogen 3 | Sacramento, CA | 632.7 GWh | 4.6 mi |