Waste Management Naples LFGTE Project

3750 White Lake Blvd, Naples, FL 34117

Plant Summary Information

Waste Management Naples LFGTE Project is ranked #6 out of 13 landfill gas power plants in Florida in terms of total annual net electricity generation.

Waste Management Naples LFGTE Project is comprised of 5 generators and generated 6.1 GWh during the 3-month period between September 2025 to December 2025.

Plant NameWaste Management Naples LFGTE Project
Utility NameWM Renewable Energy LLC
LocationCollier County, FL
Initial Operation DateMay 2011
Last Update Dec 2025
Annual Generation 24.0 GWh
Annual Consumption 329.2 k MMBtu
Ranked #5,208 out of 13,301 Power Plants Nationwide
Ranked #109 out of 282 Landfill Gas Power Plants Nationwide
Ranked #275 out of 334 Florida Power Plants
Ranked #6 out of 13 Florida Landfill Gas Power Plants
Fuel Types Landfill Gas

Map of Waste Management Naples LFGTE Project

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Waste Management Naples LFGTE Project.

Create Your Account Today

Monthly Net Generation for Waste Management Naples LFGTE Project

Monthly Plant Fuel Consumption for Waste Management Naples LFGTE Project

Waste Management Naples LFGTE Project Details

Summary Information
Plant NameWaste Management Naples LFGTE Project (57168)
Plant Address3750 White Lake Blvd, Naples, FL 34117
UtilityWM Renewable Energy LLC (54842)
Latitude, Longitude26.15583, -81.65806
Generation Dates on FileMay 2011 to Dec 2025
Initial Operation DateMay 2011
Annual Generation 24.0 GWh
Fuel Types Landfill Gas
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionSERC
Balancing AuthorityFlorida Power & Light Company (FPL)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerDairyland Power Coop (4716)
Grid Voltage 12.00 kV
Energy StorageNo

Generator GEN1 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationFP&L
RTO ISO Location Designation For Reporting Wholesale Sales DataFP&L
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN2 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationFP&L
RTO ISO Location Designation For Reporting Wholesale Sales DataFP&L
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN3 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationFP&L
RTO ISO Location Designation For Reporting Wholesale Sales DataFP&L
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN4 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationFP&L
RTO ISO Location Designation For Reporting Wholesale Sales DataFP&L
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN5 Details Operating May 2011

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node DesignationFP&L
RTO ISO Location Designation For Reporting Wholesale Sales DataFP&L
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2011
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Waste Management Naples LFGTE Project Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Landfill Gas.

RankPlant NamePlant LocationAnnual Generation
#99DANC LFGTE FacilityRodman, NY25.5 GWh
#100Peoples Generating StationAnn Arbor, MI25.5 GWh
#101Waste Management Lockwood LFGTESparks, NV25.2 GWh
#102Mountain ViewGreencastle, PA26.4 GWh
#103Short MountainEugene, OR25.0 GWh
#104BMW Manufacturing CoGreer, SC30.4 GWh
#105Ameresco San JoaquinLinden, CA24.8 GWh
#106Ameresco Dallas LLCDallas, TX24.8 GWh
#107Spruce Ridge Gas RecoveryGlencoe, MN24.7 GWh
#108Oneida HerkimerBoonville, NY24.3 GWh
#110Pendleton County LFGTEButler, KY24.0 GWh
#111Mesquite Creek LFGTE ProjectNew Braunfels, TX24.0 GWh
#112Five Oaks Gas RecoveryTaylorville, IL23.7 GWh
#113Terry Bundy Generating StationLincoln, NE148.4 GWh
#114Riverbend LandfillMcMinnville, OR23.5 GWh
#115Sycamore Energy LLCSantee, CA23.3 GWh
#116Cumberland County Solid Waste ComplexMillville, NJ23.3 GWh
#117Gaston County Renewable Energy CenterDallas, NC23.1 GWh
#118Eagle Valley (MI)Orion, MI23.0 GWh
#119Oak Ridge LFGTELogansport, IN23.0 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Waste Management Naples LFGTE Project.

Plant NamePlant LocationAnnual GenerationDistance
Babcock PreservePunta Gorda, FL163.3 GWh48.9 mi
Babcock Solar Energy Center HybridPunta Gorda, FL136.1 GWh49.1 mi
BeautyberryClewiston, FL167.0 GWh41.6 mi
Blue Heron SolarClewiston, FL151.0 GWh49.9 mi
BoardwalkTBD, FL136.6 GWh25.5 mi
CaloosahatcheeClewiston, FL161.5 GWh50.6 mi
Clewiston Sugar HouseClewiston, FL243.4 GWh59.9 mi
Fort MyersFt. Myers, FL9.3 TWh38.2 mi
Ghost Orchid Solar Energy CenterClewiston, FL146.0 GWh42.6 mi
GoldenrodImmokalee, FL133.8 GWh24.7 mi
Green PastureTBD, FL185.4 GWh60.4 mi
Hammock SolarLabelle, FL144.7 GWh42.4 mi
Hendry IslesTBD, FL176.7 GWh50.1 mi
ImmokaleeImmokalee, FL157.8 GWh26 mi
Lee County Solid Waste EnergyFort Myers, FL314.6 GWh33.5 mi
Okeelanta CogenerationSouth Bay, FL53.2 GWh63.5 mi
Port Charlotte Energy LLCPunta Gorda, FL626.0 MWh47.8 mi
Sawgrass Solar Energy CenterClewiston, FL145.1 GWh40.6 mi
Swamp CabbageLaBelle, FL109.8 GWh48.8 mi
WoodyardClewiston, FL174.4 GWh41.6 mi