Sterling Power Plant
110 East Seneca Street, Sherrill, NY 13461Plant Summary Information
Sterling Power Plant is ranked #96 out of 115 natural gas power plants in New York in terms of total annual net electricity generation.
Sterling Power Plant is comprised of 3 generators and generated 245.4 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Sterling Power Plant |
|---|---|
| Utility Name | Sterling Power Partners LP |
| Location | Oneida County, NY |
| Initial Operation Date | June 1991 |
| Last Update | Dec 2024 |
| Annual Generation | 3.7 GWh |
| Annual Consumption | 31.3 k MMBtu |
| Ranked #8,790 out of 12,539 Power Plants Nationwide | |
| Ranked #1,767 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #568 out of 944 New York Power Plants | |
| Ranked #96 out of 115 New York Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 99.7% |
Map of Sterling Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Sterling Power Plant.
Monthly Net Generation for Sterling Power Plant
Sterling Power Plant Details
| Summary Information | |
|---|---|
| Plant Name | Sterling Power Plant (50744) |
| Plant Address | 110 East Seneca Street, Sherrill, NY 13461 |
| Utility | Sterling Power Partners LP (14182) |
| Latitude, Longitude | 43.08034, -75.60096 |
| Generation Dates on File | Apr 2001 to Dec 2024 |
| Initial Operation Date | June 1991 |
| Annual Generation | 3.7 GWh |
| Fuel Types | Natural Gas : 99.7% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | New York Independent System Operator (NYIS) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Municipality |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Niagara Mohawk Power Corp. (13573) NY |
| Grid Voltage | 115.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | NIAGARA MOHAWK DBA NATIONAL GRID |
| Natural Gas Storage | No |
Generator GEN1 Details Operating June 1991
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | No |
| RTO ISO LMP Node Designation | 23777 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | 23777 |
| Nameplate Capacity | 47.7 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 38.8 MW |
| Winter Capacity | 47.6 MW |
| Minimum Load | 35 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | June 1991 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN3 Details Operating June 1991
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | 23777 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | 23777 |
| Nameplate Capacity | 1.1 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 1.1 MW |
| Winter Capacity | 1.1 MW |
| Minimum Load | 0.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1991 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Startup Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN2 Details Operating July 1991
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Duct Burners | No |
| RTO ISO LMP Node Designation | 23777 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | 23777 |
| Nameplate Capacity | 16.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 16 MW |
| Winter Capacity | 16.5 MW |
| Minimum Load | 12 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | July 1991 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Sterling Power Plant Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1757 | Greenleaf 1 | Yuba City, CA | 4.1 GWh |
| #1758 | Rothschild Biomass Cogen Facility | Rothschild, WI | 152.8 GWh |
| #1759 | Marshfield Utilities Gas Plant | Marshfield, WI | 4.0 GWh |
| #1760 | C W Burdick | Grand Island, NE | 4.8 GWh |
| #1761 | University of Washington Power Plant | Seattle, WA | 4.1 GWh |
| #1762 | Juniper Networks Sunnyvale | Sunnyvale, CA | 3.9 GWh |
| #1763 | Grapeland Hybrid | Rancho Cucamonga, CA | 3.9 GWh |
| #1764 | Waters River | Peabody, MA | 4.8 GWh |
| #1765 | Chalk Cliff Limited | Bakersfield, CA | 3.8 GWh |
| #1766 | Williams | Goose Creek, SC | 2.3 TWh |
| #1768 | Ty Cooke | Lubbock, TX | 3.7 GWh |
| #1769 | AT&T San Diego | San Diego, CA | 3.5 GWh |
| #1770 | CalPeak Power Vaca Dixon Peaker Plant | Vacaville, CA | 3.5 GWh |
| #1771 | Carthage Energy LLC | Carthage, NY | 3.5 GWh |
| #1772 | Batavia Power Plant | Batavia, NY | 3.4 GWh |
| #1773 | Forked River | Forked River, NJ | 3.8 GWh |
| #1774 | McClellan (CA) | Sacramento, CA | 3.4 GWh |
| #1775 | Wellhead Power Panoche | Firebaugh, CA | 3.3 GWh |
| #1776 | NCAH Central Utility Plant | Ames, IA | 3.3 GWh |
| #1777 | Dallman | Springfield, IL | 809.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Sterling Power Plant.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Fenner Wind | Cazenovia, NY | 64.4 GWh | 10.3 mi |
| Judd Road Solar | Oriskany, NY | 8.6 GWh | 13.5 mi |
| Lenox Renewables | Canastota, NY | 5.4 GWh | 9.1 mi |
| Madison County | Canastota, NY | 2.1 GWh | 6.2 mi |
| Marathon Solar Farm II LLC North | Canastota, NY | 4.7 GWh | 6.8 mi |
| Marathon Solar Farm LLC South | Canastota, NY | 6.4 GWh | 6.8 mi |
| Munnsville Wind Farm LLC | Madison, NY | 82.0 GWh | 12 mi |
| NY USLE Rome-Oriskany | Rome, NY | 5.0 GWh | 11.7 mi |
| Oneida - South | Whitestown, NY | 2.5 GWh | 12.3 mi |
| Oneida - West | Whitestown, NY | 2.5 GWh | 11.7 mi |
| Oneida County- DPW | Oriskany, NY | 1.8 GWh | 12.6 mi |
| Onyx - Lamphear Road CSG | Rome, NY | 2.7 GWh | 9.5 mi |
| Owlville Creek Solar 2, LLC | Canastota, NY | 7.8 GWh | 8.6 mi |
| Owlville Creek Solar, LLC | Canastota, NY | 8.4 GWh | 9 mi |
| Peterboro (CSG) | Vernon, NY | 2.7 GWh | 2.9 mi |
| Pivot Solar NY 4 | Verona, NY | 208.0 MWh | 4.7 mi |
| Reid Solar | Rome, NY | 7.1 GWh | 14 mi |
| State Route 5 | Vernon, NY | 6.6 GWh | 5.4 mi |
| Tannery Road Landfill | Rome, NY | 2.7 GWh | 11.5 mi |
| Time Warner Cable Enterprises - Martino | Rome, NY | 2.2 GWh | 11.2 mi |