Point Beach Nuclear Plant
6610 Nuclear Road, Two Rivers, WI 54241Plant Summary Information
Point Beach Nuclear Plant is ranked #35 out of 54 nuclear power plants nationwide in terms of total annual net electricity generation.
Point Beach Nuclear Plant is comprised of 3 generators and generated 2.2 TWh during the 3-month period between February 2026 to May 2026.
| Plant Name | Point Beach Nuclear Plant |
|---|---|
| Utility Name | NextEra Energy Point Beach LLC |
| Location | Manitowoc County, WI |
| Initial Operation Date | June 1969 |
| Last Update | May 2026 |
| Annual Generation | 10.0 TWh |
| Annual Consumption | 114.2 M MMBtu |
| Ranked #61 out of 13,081 Power Plants Nationwide | |
| Ranked #35 out of 54 Nuclear Power Plants Nationwide | |
| Ranked #1 out of 260 Wisconsin Power Plants | |
| Ranked #1 out of 1 Wisconsin Nuclear Power Plants | |
| Fuel Types | Nuclear |
Map of Point Beach Nuclear Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Point Beach Nuclear Plant.
Monthly Net Generation for Point Beach Nuclear Plant
Monthly Plant Fuel Consumption for Point Beach Nuclear Plant
Point Beach Nuclear Plant Details
| Summary Information | |
|---|---|
| Plant Name | Point Beach Nuclear Plant (4046) |
| Plant Address | 6610 Nuclear Road, Two Rivers, WI 54241 |
| Utility | NextEra Energy Point Beach LLC (55906) |
| Latitude, Longitude | 44.2806, -87.5369 |
| Generation Dates on File | Jan 2001 to May 2026 |
| Initial Operation Date | June 1969 |
| Annual Generation | 10.0 TWh |
| Fuel Types | Nuclear |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | RFC |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Lake Michigan |
| Ash Impoundment | No |
| Transmission / Distribution Owner | American Transmission Co (659) WI |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator 5 Details Operating June 1969
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | WEC.PTBEACB5 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | WEC.PTBEACB5 |
| Nameplate Capacity | 25 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 15 MW |
| Winter Capacity | 18 MW |
| Minimum Load | 4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | June 1969 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
Generator 1 Details Operating December 1970
| Technology | Nuclear |
|---|---|
| Prime Mover | Steam Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | WEC.PTBHGB1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | WEC.PTBHGB1 |
| Nameplate Capacity | 643 MW |
| Nameplate Power Factor | 0.94 |
| Summer Capacity | 591.3 MW |
| Winter Capacity | 597.7 MW |
| Minimum Load | 150 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 1970 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Nuclear |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | OVER |
| Other Planned Modifications | No |
| Multiple Fuels | No |
Generator 2 Details Operating October 1972
| Technology | Nuclear |
|---|---|
| Prime Mover | Steam Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | WEC.PTBHGB2 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | WEC.PTBHGB2 |
| Nameplate Capacity | 643 MW |
| Nameplate Power Factor | 0.94 |
| Summer Capacity | 598.2 MW |
| Winter Capacity | 605.7 MW |
| Minimum Load | 150 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | October 1972 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Nuclear |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | OVER |
| Other Planned Modifications | No |
| Multiple Fuels | No |
Point Beach Nuclear Plant Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Nuclear.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #25 | Quad Cities Generating Station | Cordova, IL | 15.2 TWh |
| #26 | Dresden Generating Station | Morris, IL | 15.1 TWh |
| #27 | Calvert Cliffs Nuclear Power Plant | Lusby, MD | 14.9 TWh |
| #28 | Joseph M Farley | Columbia, AL | 14.7 TWh |
| #29 | Beaver Valley | Shippingport, PA | 14.5 TWh |
| #30 | Arkansas Nuclear One | Russellville, AR | 14.1 TWh |
| #31 | Edwin I Hatch | Baxley, GA | 13.9 TWh |
| #32 | Turkey Point | Homestead, FL | 19.8 TWh |
| #33 | Surry | Surry, VA | 12.2 TWh |
| #34 | Perry | Perry, OH | 11.0 TWh |
| #36 | Grand Gulf | Port Gibson, MS | 10.0 TWh |
| #37 | Seabrook | Seabrook, NH | 9.9 TWh |
| #38 | Waterford 3 | Killona, LA | 9.5 TWh |
| #39 | Wolf Creek Generating Station | Burlington, KS | 9.3 TWh |
| #40 | Columbia Generating Station | Richland, WA | 9.1 TWh |
| #41 | Callaway | Fulton, MO | 9.0 TWh |
| #42 | Prairie Island | Welch, MN | 8.8 TWh |
| #43 | PSEG Hope Creek Generating Station | Hancocks Bridge, NJ | 8.8 TWh |
| #44 | Clinton Power Station | Clinton, IL | 8.3 TWh |
| #45 | River Bend | St. Francisville, LA | 8.3 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Point Beach Nuclear Plant.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Combined Locks | Combined Locks, WI | 42.6 GWh | 37.8 mi |
| Combined Locks Energy Center | Combined Locks, WI | 301.6 GWh | 37.8 mi |
| Consumer Operations LLC | Green Bay, WI | 239.2 GWh | 28.5 mi |
| Custer Energy Center | Manitowoc, WI | 4.1 GWh | 16.4 mi |
| De Pere Energy Center | De Pere, WI | 180.2 GWh | 28.9 mi |
| Fox Energy Center | Wrightstown, WI | 4.2 TWh | 33.3 mi |
| Island Street Peaking Plant | Kaukauna, WI | 20.2 GWh | 36.1 mi |
| Kaukauna Gas Turbine | Kaukauna, WI | 2.3 GWh | 36 mi |
| Kaukauna Paper Mill | Kaukauna, WI | 90.0 GWh | 35.4 mi |
| Kohler Solar | Kohler, WI | 2.9 GWh | 38.6 mi |
| Little Chute | Combined Locks, WI | 22.1 GWh | 35.6 mi |
| Manitowoc | Manitowoc, WI | 178.4 GWh | 14.9 mi |
| New Badger | Kaukauna, WI | 43.8 GWh | 36.2 mi |
| Point Beach Solar | Two Creeks, WI | 197.8 GWh | 0.9 mi |
| Pulliam | Green Bay, WI | 103.2 GWh | 29.4 mi |
| Rapide Croche | Kaukana, WI | 16.5 GWh | 38.5 mi |
| Ridgeview | Whitelaw, WI | 37.3 GWh | 16.2 mi |
| Shirley Wind | Denmark, WI | 57.0 GWh | 19.9 mi |
| Two Creeks Solar | Two Rivers, WI | 185.0 GWh | 2.2 mi |
| Wind Turbine | Casco, WI | 12.0 GWh | 27.3 mi |