Pixelle Specialty Solutions LLC - Chillicothe Facility
232 East 8th Street, Chillicothe, OH 45601Plant Summary Information
Pixelle Specialty Solutions LLC - Chillicothe Facility is ranked #47 out of 185 power plants in Ohio in terms of total annual net electricity generation.
Pixelle Specialty Solutions LLC - Chillicothe Facility is comprised of 4 generators and generated 48.5 GWh during the 3-month period between November 2024 to February 2025.
Plant Name | Pixelle Specialty Solutions LLC - Chillicothe Facility |
---|---|
Utility Name | Pixelle Specialty Solution, LLC |
Location | Ross County, OH |
Initial Operation Date | February 1952 |
Last Update | Feb 2025 |
Annual Generation | 203.9 GWh |
Annual Consumption | 11.2 M MMBtu |
Ranked #2,324 out of 11,623 Power Plants Nationwide | |
Ranked #66 out of 78 Black Liquor Power Plants Nationwide | |
Ranked #47 out of 185 Ohio Power Plants | |
Ranked #1 out of 1 Ohio Black Liquor Power Plants | |
Fuel Types | Black Liquor : 42.3% Natural Gas : 39.9% Wood/Wood Waste Solids : 14.5% Tire-derived Fuels : 2.1% Distillate Fuel Oil : 1.2% |
Previous Operators |
P H Glatfelter Company (2013 to 2015) P H Glatfelter Company (2016 to 2017) Pixelle Specialty Solutions LLC - (OH) (2018 to 2019) Pixelle Specialty Solutions (2020 to 2020) Pixelle Specialty Solution, LLC (2021 to 2023) |
Map of Pixelle Specialty Solutions LLC - Chillicothe Facility
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Pixelle Specialty Solutions LLC - Chillicothe Facility.
Monthly Net Generation for Pixelle Specialty Solutions LLC - Chillicothe Facility
Pixelle Specialty Solutions LLC - Chillicothe Facility Details
Summary Information | |
---|---|
Plant Name | Pixelle Specialty Solutions LLC - Chillicothe Facility (10244) |
Plant Address | 232 East 8th Street, Chillicothe, OH 45601 |
Utility | Pixelle Specialty Solution, LLC (61723) |
Latitude, Longitude | 39.32461, -82.97404 |
Generation Dates on File | Jan 2001 to Feb 2025 |
Initial Operation Date | February 1952 |
Annual Generation | 203.9 GWh |
Fuel Types | Black Liquor : 42.3% Natural Gas : 39.9% Wood/Wood Waste Solids : 14.5% Tire-derived Fuels : 2.1% Distillate Fuel Oil : 1.2% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 84-483-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | (322122) |
Sector | Industrial CHP (7) |
Water Source | Wells and Surface Water |
Ash Impoundment | No |
Transmission / Distribution Owner | Ohio Power Co (14006) OH |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | COLUMBIA GAS OF OHIO |
Natural Gas Storage | No |
Generator T-10 Details Out of Service February 1952
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 10.6 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 7.3 MW |
Winter Capacity | 4.5 MW |
Minimum Load | 5 MW |
Uprate/Derate Completed | No |
Status | Out of Service |
First Operation Date | February 1952 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Black Liquor / Natural Gas / Wood/Wood Waste Solids / Tire-derived Fuels / Distillate Fuel Oil |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | WDS / TDF |
---|
Generator T-11 Details Operating February 1958
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 24 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 10.2 MW |
Winter Capacity | 10.8 MW |
Minimum Load | 8 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 1958 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Black Liquor / Natural Gas / Wood/Wood Waste Solids / Tire-derived Fuels / Distillate Fuel Oil |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | WDS / TDF |
---|
Generator T-12 Details Operating February 1967
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 31 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 15.8 MW |
Winter Capacity | 19.5 MW |
Minimum Load | 10 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 1967 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Black Liquor / Natural Gas / Wood/Wood Waste Solids / Tire-derived Fuels / Distillate Fuel Oil |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | WDS / TDF |
---|
Generator T-13 Details Operating July 1978
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 27.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 10.6 MW |
Winter Capacity | 13.3 MW |
Minimum Load | 7 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 1978 |
Combined Heat & Power | Yes |
---|---|
Sector Name | Industrial CHP (7) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Black Liquor / Wood/Wood Waste Solids / Tire-derived Fuels / Distillate Fuel Oil |
Startup Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | No |
Multifuel Details | |
Cofire Energy Source | WDS / TDF |
---|
Pixelle Specialty Solutions LLC - Chillicothe Facility Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Black Liquor.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#56 | Hopewell Mill | Hopewell, VA | 280.9 GWh |
#57 | KapStone Kraft Paper Corp | Roanoke Rapids, NC | 189.7 GWh |
#58 | Georgia-Pacific Wauna Mill | Clatskanie, OR | 201.8 GWh |
#59 | Brunswick Cellulose | Brunswick, GA | 326.9 GWh |
#60 | International Paper Vicksburg Mill | Vicksburg, MS | 203.6 GWh |
#61 | WestRock (WA) | Tacoma, WA | 196.3 GWh |
#62 | Longview Fibre | Longview, WA | 170.9 GWh |
#63 | U S Alliance Coosa Pines | Coosa Pines, AL | 139.3 GWh |
#64 | Packaging Corp. of America Jackson Mill | Jackson, AL | 158.4 GWh |
#65 | International Paper Riverdale Mill | Selma, AL | 462.7 GWh |
#67 | Georgia-Pacific Corp - Nekoosa Mill | Nekoosa, WI | 195.3 GWh |
#68 | Clearwater Paper APP CB | Arkansas City, AR | 110.7 GWh |
#69 | IP Springfield Oregon | Springfield, OR | 91.2 GWh |
#70 | Ticonderoga Mill | Ticonderoga, NY | 193.3 GWh |
#71 | St Francisville Mill | St. Francisville, LA | 116.0 GWh |
#72 | Kaukauna Paper Mill | Kaukauna, WI | 116.4 GWh |
#73 | Interstate Paper LLC Riceboro | Riceboro, GA | 103.9 GWh |
#74 | Mosinee Mill | Mosinee, WI | 124.1 GWh |
#75 | Georgia-Pacific Toledo Mill | Toledo, OR | 59.6 GWh |
#76 | Port Townsend Paper | Port Townsend, WA | 35.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Pixelle Specialty Solutions LLC - Chillicothe Facility.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Atlanta Farms Solar | Williamsport, OH | 68.9 GWh | 19.5 mi |
Big Plain Solar, LLC | London, OH | 408.4 GWh | 41.3 mi |
Darby Power, LLC | Mt Sterling, OH | 557.3 GWh | 29 mi |
Fayette Solar | Greenfield, OH | 16.6 GWh | 23.1 mi |
Fox Squirrel Solar | Mt Sterling, OH | 782.7 GWh | 37.7 mi |
Greenup Hydro | Franklin Furnace, OH | 262.2 GWh | 47.2 mi |
Hanging Rock Energy Facility | Ironton, OH | 8.0 TWh | 52.9 mi |
Haverhill North Cogeneration Facility | Franklin Furnace, OH | 353.4 GWh | 50.9 mi |
Hecate Energy Highland LLC | Buford, OH | 470.0 GWh | 47.7 mi |
Hillcrest Solar | Mt. Orab, OH | 386.0 GWh | 52.8 mi |
IGS CMH4, LLC | Madison, OH | 2.6 GWh | 46.5 mi |
New Market Solar | Sardinia, OH | 69.1 GWh | 47.4 mi |
PS ST-8 Engine No 1 | Columbus, OH | 3.0 MWh | 44.2 mi |
Renick Run Pumping Station 03-04 | Columbus, OH | 1.0 MWh | 41.8 mi |
Rolling Hills Generating | Wilkesville, OH | 2.3 TWh | 38.1 mi |
Ross County Solar, LLC | Greenfield, OH | 40.4 GWh | 20.2 mi |
Salt City Solar Project - Hybrid | Circleville, OH | 105.0 GWh | 6.3 mi |
ST-1/1A Engine No 1 | Columbus, OH | 2.0 MWh | 43.3 mi |
Willowbrook Solar I, LLC | Morystown, OH | 144.7 GWh | 44.4 mi |
Yellowbud Solar, LLC | Williamsport, OH | 516.7 GWh | 13.2 mi |