Phelps Dodge Refining
850 HAWKINS, El Paso, TX 79915Plant Summary Information
Phelps Dodge Refining is ranked #149 out of 314 natural gas power plants in Texas in terms of total annual net electricity generation.
Phelps Dodge Refining is comprised of 5 generators and generated 12.6 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Phelps Dodge Refining |
|---|---|
| Utility Name | Phelps Dodge Refining Corp |
| Location | El Paso County, TX |
| Initial Operation Date | October 1986 |
| Last Update | Dec 2024 |
| Annual Generation | 56.1 GWh |
| Annual Consumption | 946.4 k MMBtu |
| Ranked #3,950 out of 12,539 Power Plants Nationwide | |
| Ranked #1,048 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #518 out of 799 Texas Power Plants | |
| Ranked #149 out of 314 Texas Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of Phelps Dodge Refining
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Phelps Dodge Refining.
Monthly Net Generation for Phelps Dodge Refining
Phelps Dodge Refining Details
| Summary Information | |
|---|---|
| Plant Name | Phelps Dodge Refining (54628) |
| Plant Address | 850 HAWKINS, El Paso, TX 79915 |
| Utility | Phelps Dodge Refining Corp (14925) |
| Latitude, Longitude | 31.76446, -106.39131 |
| Generation Dates on File | Jan 2001 to Dec 2024 |
| Initial Operation Date | October 1986 |
| Annual Generation | 56.1 GWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | Yes |
| FERC Cogeneration Docket Number | 86-652-000; '93-57-000 |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | El Paso Electric Company (EPE) |
| NAICS Code | Metal Ore Mining (2122) |
| Sector | Industrial CHP (7) |
| Water Source | Wells |
| Ash Impoundment | No |
| Transmission / Distribution Owner | El Paso Electric Co (5701) TX |
| Grid Voltage | 13.80 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | TEXAS GAS SERVICE |
| Natural Gas Storage | No |
| Liquefied Natural Gas Storage | No |
Generator 2607 Details Out of Service October 1986
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 3.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.6 MW |
| Winter Capacity | 3 MW |
| Minimum Load | 2.6 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
| First Operation Date | October 1986 |
| Combined Heat & Power | Yes |
|---|---|
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 2608 Details Out of Service October 1986
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 3.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.6 MW |
| Winter Capacity | 3 MW |
| Minimum Load | 2.6 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
| First Operation Date | October 1986 |
| Combined Heat & Power | Yes |
|---|---|
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 3001 Details Operating June 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 4.2 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 3.2 MW |
| Winter Capacity | 3.8 MW |
| Minimum Load | 3.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1992 |
| Combined Heat & Power | Yes |
|---|---|
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 3002 Details Operating June 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 4.2 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 3.2 MW |
| Winter Capacity | 3.8 MW |
| Minimum Load | 3.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1992 |
| Combined Heat & Power | Yes |
|---|---|
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 3003 Details Operating June 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 4.2 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 3.2 MW |
| Winter Capacity | 3.8 MW |
| Minimum Load | 3.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1992 |
| Combined Heat & Power | Yes |
|---|---|
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Phelps Dodge Refining Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1038 | Osawatomie | Miami, KS | 58.8 GWh |
| #1039 | Little Dixie | Centrahoma, OK | 58.3 GWh |
| #1040 | Kaukauna Paper Mill | Kaukauna, WI | 106.5 GWh |
| #1041 | Cimarron River | Liberal, KS | 57.7 GWh |
| #1042 | Pine Bluff Mill | Pine Bluff, AR | 289.0 GWh |
| #1043 | R M Heskett | Mandan, ND | 57.4 GWh |
| #1044 | Newington | Newington, NH | 95.2 GWh |
| #1045 | Bristol Myers Squibb New Brunswick | New Brunswick, NJ | 56.8 GWh |
| #1046 | Saint Marys Hospital Power Plant | Rochester, MN | 56.8 GWh |
| #1047 | Crete Energy Venture LLC | Crete, IL | 56.5 GWh |
| #1049 | Niland Gas Turbine Plant | Niland, CA | 55.7 GWh |
| #1050 | SWM Fuel Cell | Yaphank, NY | 55.6 GWh |
| #1051 | Domino Sugar Baltimore | Baltimore, MD | 55.5 GWh |
| #1052 | F B Culley | Newburgh, IN | 1.4 TWh |
| #1053 | Gillette SBMC | Boston, MA | 54.9 GWh |
| #1054 | Gilbert | Milford, NJ | 54.8 GWh |
| #1055 | W&T Onshore Treating Facility (OTF) | Theodore, AL | 54.6 GWh |
| #1056 | Corpus Christi | Corpus Christi, TX | 54.6 GWh |
| #1057 | Georgia-Pacific Taylorsville Plywood | Taylorsville, MS | 54.6 GWh |
| #1058 | Coolidge Generation Station | Coolidge, AZ | 54.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Phelps Dodge Refining.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Afton Generating Station | La Mesa, NM | 349.1 GWh | 36 mi |
| Alamogordo Solar Energy Center | Alamogordo, NM | 11.2 GWh | 79.4 mi |
| Buena Vista Energy Center | Chaparral, NM | 386.8 GWh | 21.8 mi |
| Columbus Solar Project | Columbus, NM | 5.4 GWh | 70.6 mi |
| Copper | El Paso, TX | 51.9 GWh | 1.1 mi |
| Fort Bliss (DEA EPIC) | El Paso, TX | 4.5 GWh | 4.7 mi |
| Hatch Solar Energy Center I, LLC | Hatch, NM | 11.7 GWh | 78.4 mi |
| Holloman Solar Facility | Holloman Air Force Ba, NM | 3.3 GWh | 82.1 mi |
| Milagro Solar I | Santa Teresa, NM | 22.0 GWh | 14.9 mi |
| Montana Power Station | El Paso, TX | 1.2 TWh | 11.3 mi |
| Montana Solar Facility | El Paso, TX | 4.9 GWh | 10.7 mi |
| New Mexico State University | Las Cruces, NM | 32.4 GWh | 27.9 mi |
| Newman | El Paso, TX | 4.2 TWh | 15.3 mi |
| Newman Solar | El Paso, TX | 13.2 GWh | 14.9 mi |
| NMSU Solar and Storage | Las Cruces, NM | 7.8 GWh | 41.6 mi |
| Nodal Power | Sunland Park, NM | 11.8 GWh | 12.3 mi |
| Rio Grande | SunLand Park, NM | 920.0 GWh | 9.6 mi |
| Roadrunner Solar | Santa Teresa, NM | 46.5 GWh | 16.7 mi |
| SunE EPE1 LLC | Chaparral, NM | 27.0 GWh | 18.9 mi |
| SunE EPE2 LLC | Las Cruces, NM | 29.2 GWh | 45.5 mi |