Montezuma Wind II
6700 Birds Landing Road, Birds Landing, CA 94512Plant Summary Information
Montezuma Wind II is ranked #39 out of 110 wind farms in California in terms of total annual net electricity generation.
Montezuma Wind II generated 25.7 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Montezuma Wind II |
|---|---|
| Utility Name | NextEra Energy Montezuma Wind II, LLC |
| Location | Solano County, CA |
| Initial Operation Date | January 2012 |
| Last Update | Dec 2024 |
| Annual Generation | 195.7 GWh |
| Annual Consumption | 682.4 k MMBtu |
| Ranked #2,491 out of 12,539 Power Plants Nationwide | |
| Ranked #747 out of 1,362 Wind Power Plants Nationwide | |
| Ranked #262 out of 1,600 California Power Plants | |
| Ranked #39 out of 110 California Wind Power Plants | |
| Fuel Types | Wind |
Map of Montezuma Wind II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Montezuma Wind II.
Monthly Net Generation for Montezuma Wind II
Montezuma Wind II Details
| Summary Information | |
|---|---|
| Plant Name | Montezuma Wind II (57701) |
| Plant Address | 6700 Birds Landing Road, Birds Landing, CA 94512 |
| Utility | NextEra Energy Montezuma Wind II, LLC (57026) |
| Latitude, Longitude | 38.11667, -121.82194 |
| Generation Dates on File | Jan 2012 to Dec 2024 |
| Initial Operation Date | January 2012 |
| Annual Generation | 195.7 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 1 Details Operating January 2012
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 78.2 MW |
| Summer Capacity | 78.2 MW |
| Winter Capacity | 78.2 MW |
| Minimum Load | 3.9 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 2012 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 34 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 34 |
|---|---|
| Predominant Turbine Manufacturer | Siemens |
| Predominant Turbine Model Number | SWT-2.3-93 |
| Design Wind Speed | 19 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 262.4 |
Montezuma Wind II Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #737 | Meadow Lake Wind Farm IV | Lafayette, IN | 200.1 GWh |
| #738 | Allegheny Ridge Wind Farm | Portage, PA | 200.1 GWh |
| #739 | Wilton Wind II LLC | Wilton, ND | 199.6 GWh |
| #740 | Summit Winds | Livermore, CA | 199.5 GWh |
| #741 | Laredo Ridge Wind LLC | Petersburg, NE | 199.5 GWh |
| #742 | Hog Creek Wind Project | Ada, OH | 198.1 GWh |
| #743 | Wheat Field Wind Power Project | Arlington, OR | 198.0 GWh |
| #744 | Milo Wind Project LLC | Portales, NM | 197.6 GWh |
| #745 | Flat Ridge Wind Energy LLC | Isabel, KS | 197.5 GWh |
| #746 | Osceola Windpower II | Harris, IA | 196.9 GWh |
| #748 | Jeffers Wind 20 LLC | Jeffers, MN | 195.4 GWh |
| #749 | Granite Reliable Power | Dummer, NH | 194.7 GWh |
| #750 | Milford Wind Corridor Stage II LLC | Milford, UT | 193.5 GWh |
| #751 | Alta Wind Energy Center IV | Mojave, CA | 193.4 GWh |
| #752 | Franklin County Wind Farm | Iowa Falls, IA | 190.7 GWh |
| #753 | Peak View Wind Farm | Walsenburg, CO | 190.1 GWh |
| #754 | FPL Energy Burleigh County Wind | Wilton, ND | 189.7 GWh |
| #755 | Taloga Wind LLC | Putnam, OK | 189.1 GWh |
| #756 | Alexander Wind Farm LLC | Alexander, KS | 188.8 GWh |
| #757 | Pinnacle Wind Force LLC | Keyser, WV | 188.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Montezuma Wind II.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Ameresco Keller Canyon | Bay Point, CA | 19.1 GWh | 9.9 mi |
| California PV Energy at ISD WWTP | Oakley, CA | 2.0 GWh | 10.2 mi |
| Columbia Solar Energy, LLC | Pittsburg, CA | 18.7 GWh | 7.1 mi |
| Creed Energy Center | Suisun, CA | 6.3 GWh | 8.9 mi |
| Delta Energy Center | Pittsburg, CA | 3.3 TWh | 7 mi |
| EDF Renewable Windfarm V Inc | Birds Landing, CA | 20.2 GWh | 0.6 mi |
| FPL Energy Montezuma Winds LLC | Birds Landing, CA | 85.4 GWh | 3.5 mi |
| Gateway Generating Station | Antioch, CA | 3.0 TWh | 7.7 mi |
| Goose Haven Energy Center | Suisun, CA | 13.0 GWh | 7.7 mi |
| High Winds LLC | Birds Landing, CA | 233.3 GWh | 1.7 mi |
| Lambie Energy Center | Suisun, CA | 9.7 GWh | 7.7 mi |
| Los Medanos Energy Center | Pittsburg, CA | 2.5 TWh | 6.6 mi |
| Marsh Landing Generating Station | Antioch, CA | 41.8 GWh | 7.6 mi |
| Oakley Solar Project | Oakley, CA | 1.9 GWh | 8.9 mi |
| Riverview Energy Center | Antioch, CA | 21.9 GWh | 7.3 mi |
| Shiloh I Wind Project | Rio Vista, CA | 389.6 GWh | 1.5 mi |
| Shiloh III Wind Project LLC | Birds Landing, CA | 265.2 GWh | 3.9 mi |
| Shiloh IV Wind Project LLC | Birds Landing, CA | 278.3 GWh | 2.3 mi |
| Shiloh Wind Project 2 LLC | Birds Landing, CA | 393.1 GWh | 4 mi |
| Solano Wind | Rio Vista, CA | 802.2 GWh | 2.9 mi |