Meadow Lake Wind Farm VI LLC
10296 E 600 N, Remington, IN 47997Plant Summary Information
Meadow Lake Wind Farm VI LLC is ranked #30 out of 210 power plants in Indiana in terms of total annual net electricity generation.
Meadow Lake Wind Farm VI LLC generated 143.0 GWh during the 3-month period between August 2025 to November 2025.
| Plant Name | Meadow Lake Wind Farm VI LLC |
|---|---|
| Utility Name | Meadow Lake Wind Farm VI LLC |
| Location | Benton County, IN |
| Initial Operation Date | November 2018 |
| Last Update | Nov 2025 |
| Annual Generation | 642.0 GWh |
| Annual Consumption | 2.4 M MMBtu |
| Ranked #1,071 out of 12,574 Power Plants Nationwide | |
| Ranked #236 out of 1,370 Wind Power Plants Nationwide | |
| Ranked #30 out of 210 Indiana Power Plants | |
| Ranked #5 out of 19 Indiana Wind Power Plants | |
| Fuel Types | Wind |
Map of Meadow Lake Wind Farm VI LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Meadow Lake Wind Farm VI LLC.
Monthly Net Generation for Meadow Lake Wind Farm VI LLC
Meadow Lake Wind Farm VI LLC Details
| Summary Information | |
|---|---|
| Plant Name | Meadow Lake Wind Farm VI LLC (61756) |
| Plant Address | 10296 E 600 N, Remington, IN 47997 |
| Utility | Meadow Lake Wind Farm VI LLC (61381) |
| Latitude, Longitude | 40.69255, -87.12701 |
| Generation Dates on File | Nov 2018 to Nov 2025 |
| Initial Operation Date | November 2018 |
| Annual Generation | 642.0 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | RFC |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Indiana Michigan Power Co (9324) IN |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator MWLVI Details Operating November 2018
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 200.4 MW |
| Summer Capacity | 200.4 MW |
| Winter Capacity | 200.4 MW |
| Minimum Load | 4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 2018 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 61 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 61 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V136-3.45 |
| Design Wind Speed | 17 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 105 |
Meadow Lake Wind Farm VI LLC Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #226 | Seiling Wind I | Seiling, OK | 669.0 GWh |
| #227 | Osborn Wind Energy | Stewartsville, MO | 664.9 GWh |
| #228 | Brazos Wind Farm | Fluvanna, TX | 658.7 GWh |
| #229 | Bronco Plains Wind II, LLC | Kit Carson, CO | 656.3 GWh |
| #230 | California Ridge Wind Energy LLC | Fithian, IL | 653.9 GWh |
| #231 | Rio Bravo Windpower, LLC | Roma, TX | 651.4 GWh |
| #232 | Minonk Wind Farm | Minonk, IL | 651.1 GWh |
| #233 | Wildcat Ranch Wind Project | Morton, TX | 645.0 GWh |
| #234 | White Rock East Wind Project | Anadarko, OK | 644.7 GWh |
| #235 | Bearkat | St. Lawrence, TX | 643.6 GWh |
| #237 | Limon III Wind LLC | Limon, CO | 639.8 GWh |
| #238 | Brady II Wind Energy Center | Dickinson, ND | 638.6 GWh |
| #239 | Chickasaw Wind Farm | New Hampton, IA | 637.3 GWh |
| #240 | Brady Wind Energy Center | Dickinson, ND | 632.3 GWh |
| #241 | Heart of Texas Wind Project | Brady, TX | 631.9 GWh |
| #242 | Glacier Sands Wind Power, LLC | Mason City, IL | 631.0 GWh |
| #243 | Cedar Springs II | Douglas, WY | 630.1 GWh |
| #244 | Foote Creek Rim | McFadden, WY | 628.9 GWh |
| #245 | King Creek Wind Farm 2, LLC | Throckmorton, TX | 628.5 GWh |
| #246 | Sweetwater Wind 4 LLC | Roscoe, TX | 628.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Meadow Lake Wind Farm VI LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Benton County Wind Farm | Earl Park, IN | 357.6 GWh | 18.9 mi |
| BioTown Ag | Reynolds, IN | 33.3 GWh | 13.9 mi |
| Fowler Ridge IV Wind Farm LLC | Fowler, IN | 425.5 GWh | 14.1 mi |
| Fowler Ridge Wind Farm LLC | Fowler, IN | 1.5 TWh | 13.2 mi |
| Hoosier Wind Project LLC | Goodland, IN | 207.8 GWh | 7.3 mi |
| IMPA Rensselaer Solar Park | Rensselaer, IN | 985.0 MWh | 17.5 mi |
| Indiana Crossroads Solar Park | Reynolds, IN | 377.3 GWh | 14.6 mi |
| Indiana Crossroads Wind Farm II | Wolcott, IN | 591.3 GWh | 7.5 mi |
| Indiana Crossroads Wind Farm LLC | Chalmers, IN | 894.5 GWh | 13.6 mi |
| Meadow Lake Wind Farm II LLC | Lafayette, IN | 237.4 GWh | 6.4 mi |
| Meadow Lake Wind Farm III LLC | Lafayette, IN | 269.3 GWh | 8.6 mi |
| Meadow Lake Wind Farm IV | Lafayette, IN | 200.1 GWh | 5 mi |
| Meadow Lake Wind Farm LLC | Lafayette, IN | 442.8 GWh | 11 mi |
| Meadow Lake Wind Farm V LLC | Chalmers, IN | 328.9 GWh | 5.8 mi |
| Norway (IN) | Monticello, IN | 16.3 GWh | 20.1 mi |
| Oakdale | Monticello, IN | 17.4 GWh | 19.8 mi |
| Rensselaer Solar Site 2 | Rensselaer, IN | 7.7 GWh | 17.8 mi |
| Rosewater Wind Farm | Chalmers, IN | 308.0 GWh | 14.3 mi |
| Tippecanoe Solar Power Plant | West Lafayette, IN | 2.7 GWh | 21.2 mi |
| Twin Lakes Solar LLC | Monticello, IN | 325.4 GWh | 18.5 mi |