Indiana Crossroads Wind Farm II
4143 N 800 W, Wolcott, IN 47995Plant Summary Information
Indiana Crossroads Wind Farm II is ranked #33 out of 211 power plants in Indiana in terms of total annual net electricity generation.
Indiana Crossroads Wind Farm II generated 198.9 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | Indiana Crossroads Wind Farm II |
|---|---|
| Utility Name | Indiana Crossroads Wind Farm II LLC |
| Location | White County, IN |
| Initial Operation Date | December 2024 |
| Last Update | Mar 2026 |
| Annual Generation | 580.8 GWh |
| Annual Consumption | 2.3 M MMBtu |
| Ranked #1,180 out of 12,332 Power Plants Nationwide | |
| Ranked #298 out of 1,358 Wind Power Plants Nationwide | |
| Ranked #33 out of 211 Indiana Power Plants | |
| Ranked #7 out of 19 Indiana Wind Power Plants | |
| Fuel Types | Wind |
Map of Indiana Crossroads Wind Farm II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Indiana Crossroads Wind Farm II.
Monthly Net Generation for Indiana Crossroads Wind Farm II
Monthly Plant Fuel Consumption for Indiana Crossroads Wind Farm II
Indiana Crossroads Wind Farm II Details
| Summary Information | |
|---|---|
| Plant Name | Indiana Crossroads Wind Farm II (66861) |
| Plant Address | 4143 N 800 W, Wolcott, IN 47995 |
| Utility | Indiana Crossroads Wind Farm II LLC (65794) |
| Latitude, Longitude | 40.77936, -87.04211 |
| Generation Dates on File | Jan 2024 to Mar 2026 |
| Initial Operation Date | December 2024 |
| Annual Generation | 580.8 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | RFC |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | NA |
| Ash Impoundment | |
| Transmission / Distribution Owner | Northern Indiana Pub Serv Co (13756) IN |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator GEN01 Details Operating December 2024
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 201.6 MW |
| Summer Capacity | 200 MW |
| Winter Capacity | 200 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2024 |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 42 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 42 |
|---|---|
| Predominant Turbine Manufacturer | Nordex |
| Predominant Turbine Model Number | N155/4.5 |
| Design Wind Speed | 19 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 345 |
Indiana Crossroads Wind Farm II Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #288 | Bishop Hill Energy LLC | Cambridge, IL | 591.6 GWh |
| #289 | Mountain Breeze Wind, LLC | Grover, CO | 590.9 GWh |
| #290 | Jumbo Hill Wind Project | Andrews, TX | 589.3 GWh |
| #291 | Goodwell Wind Project LLC | Goodwell, OK | 589.3 GWh |
| #292 | Rattlesnake Power, LLC | Brady, TX | 586.5 GWh |
| #293 | Prairie Wind Farm | Montezuma, IA | 586.4 GWh |
| #294 | South Hurlburt Wind LLC | Arlington, OR | 584.7 GWh |
| #295 | Walnut Wind Farm | Walnut, IA | 584.1 GWh |
| #296 | King Creek Wind Farm 1, LLC | Throckmorton, TX | 582.2 GWh |
| #297 | Limon Wind I | Limon, CO | 581.9 GWh |
| #299 | Foxtail Wind, LLC | Forbes, ND | 579.9 GWh |
| #300 | Langford Wind Power | Christoval, TX | 572.9 GWh |
| #301 | Logan Wind Energy | Peetz, CO | 572.8 GWh |
| #302 | Pattern Panhandle Wind LLC | Panhandle, TX | 572.6 GWh |
| #303 | Century | Blairsburg, IA | 572.0 GWh |
| #304 | Grant Wind, LLC | Medford, OK | 571.6 GWh |
| #305 | Boiling Springs Wind Farm | Woodward, OK | 570.7 GWh |
| #306 | Sherbino II | Ft. Stockton, TX | 570.6 GWh |
| #307 | Caney River Wind Project | Howard, KS | 569.9 GWh |
| #308 | Blue Cloud Wind Energy LLC | Sudan, TX | 569.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Indiana Crossroads Wind Farm II.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| BioTown Ag | Reynolds, IN | 33.3 GWh | 8.6 mi |
| Carpenter Wind Farm LLC | Remington, IN | 262.4 GWh | 5.9 mi |
| Cavalry Solar Hybrid | Monon, IN | 359.9 GWh | 14.5 mi |
| Fowler Ridge IV Wind Farm LLC | Fowler, IN | 425.4 GWh | 20.7 mi |
| Fowler Ridge Wind Farm LLC | Fowler, IN | 1.5 TWh | 20.4 mi |
| Hidden View Dairy, LLC | Rensselaer, IN | 4.3 GWh | 17.6 mi |
| IMPA Rensselaer Solar Park | Rensselaer, IN | 985.0 MWh | 12.5 mi |
| Indiana Crossroads Solar Park | Reynolds, IN | 380.1 GWh | 10.6 mi |
| Indiana Crossroads Wind Farm LLC | Chalmers, IN | 874.8 GWh | 12.1 mi |
| Meadow Lake Wind Farm II LLC | Lafayette, IN | 237.4 GWh | 9.5 mi |
| Meadow Lake Wind Farm III LLC | Lafayette, IN | 269.3 GWh | 12.5 mi |
| Meadow Lake Wind Farm IV | Lafayette, IN | 200.1 GWh | 7 mi |
| Meadow Lake Wind Farm LLC | Lafayette, IN | 442.8 GWh | 11.9 mi |
| Meadow Lake Wind Farm V LLC | Chalmers, IN | 332.9 GWh | 4.5 mi |
| Meadow Lake Wind Farm VI LLC | Remington, IN | 634.2 GWh | 7.5 mi |
| Norway (IN) | Monticello, IN | 16.3 GWh | 14.8 mi |
| Oakdale | Monticello, IN | 17.4 GWh | 17.4 mi |
| Rensselaer Solar Site 2 | Rensselaer, IN | 7.7 GWh | 13 mi |
| Rosewater Wind Farm | Chalmers, IN | 306.8 GWh | 8.8 mi |
| Twin Lakes Solar LLC | Monticello, IN | 328.3 GWh | 14.6 mi |