Green City Recovery, LLC
493 Double Culvert Road, Georgetown, KY 40324Plant Summary Information
Green City Recovery, LLC is ranked #8 out of 8 landfill gas power plants in Kentucky in terms of total annual net electricity generation.
Green City Recovery, LLC is comprised of 2 generators and generated 311.3 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Green City Recovery, LLC |
|---|---|
| Utility Name | Green City Recovery, LLC |
| Location | Scott County, KY |
| Initial Operation Date | January 2016 |
| Last Update | Dec 2024 |
| Annual Generation | 1.2 GWh |
| Annual Consumption | 21.3 k MMBtu |
| Ranked #11,846 out of 13,081 Power Plants Nationwide | |
| Ranked #263 out of 281 Landfill Gas Power Plants Nationwide | |
| Ranked #59 out of 61 Kentucky Power Plants | |
| Ranked #8 out of 8 Kentucky Landfill Gas Power Plants | |
| Fuel Types | Landfill Gas |
Map of Green City Recovery, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Green City Recovery, LLC.
Monthly Net Generation for Green City Recovery, LLC
Monthly Plant Fuel Consumption for Green City Recovery, LLC
Green City Recovery, LLC Details
| Summary Information | |
|---|---|
| Plant Name | Green City Recovery, LLC (60703) |
| Plant Address | 493 Double Culvert Road, Georgetown, KY 40324 |
| Utility | Green City Recovery, LLC (60428) |
| Latitude, Longitude | 38.34528, -84.54889 |
| Generation Dates on File | Jan 2016 to Dec 2024 |
| Initial Operation Date | January 2016 |
| Annual Generation | 1.2 GWh |
| Fuel Types | Landfill Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | SERC |
| Balancing Authority | Louisville Gas and Electric Company and Kentucky Utilities Company (LGEE) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Kentucky Utilities Co (10171) KY |
| Grid Voltage | 13.20 kV |
| Energy Storage | No |
Generator 1 Details Out of Service January 2016
| Technology | Landfill Gas |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 1 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1 MW |
| Winter Capacity | 1 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
| First Operation Date | January 2016 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Landfill Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 2 Details Out of Service July 2019
| Technology | Landfill Gas |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 1 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1 MW |
| Winter Capacity | 1 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
| First Operation Date | July 2019 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Landfill Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Green City Recovery, LLC Plant Owners
| Owner Name | Address | Generator | Ownership |
|---|---|---|---|
| Toyota Motor Manufacturing, Kentucky, Inc. | 1001 Cherry Blossom Way, Georgetown, KY 40324 | Generator 1 | 100.00% |
| Toyota Motor Manufacturing, Kentucky, Inc. | 1001 Cherry Blossom Way, Georgetown, KY 40324 | Generator 2 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Landfill Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #253 | Ameresco Janesville | Janesville, WI | 3.1 GWh |
| #254 | Hidden Hollow Energy | Boise, ID | 2.8 GWh |
| #255 | Sunnyvale City of WPCP | Sunnyvale, CA | 7.5 GWh |
| #256 | Adrian Energy Associates LLC | Adrian, MI | 2.1 GWh |
| #257 | Ameresco Chiquita Canyon | Castaic, CA | 2.1 GWh |
| #258 | SECCRA Community Landfill | West Grove, PA | 2.0 GWh |
| #259 | Archbald Power Station | Archbald, PA | 60.1 GWh |
| #260 | Sonoma Central Landfill Phase II | Petaluma, CA | 1.8 GWh |
| #261 | Granby LFG | Granby, MA | 1.7 GWh |
| #262 | Ameresco Stafford | Stafford, VA | 1.7 GWh |
| #264 | Woodbine Landfill Plant | Woodbine, NJ | 1.2 GWh |
| #265 | GRS Arbor Hills | Northville, MI | 1.2 GWh |
| #266 | Riverview Energy Systems | Riverview, MI | 1.1 GWh |
| #267 | POET Biorefining - Chancellor | Chancellor, SD | 27.6 GWh |
| #268 | Pennsauken Landfill | Pennsauken, NJ | 670.0 MWh |
| #269 | Port Charlotte Energy LLC | Punta Gorda, FL | 626.0 MWh |
| #270 | Sonoma Central Landfill Phase I | Petaluma, CA | 583.0 MWh |
| #271 | Alpha Ridge LFG | Marriottsville, MD | 250.0 MWh |
| #272 | Berkeley County Landfill | Moncks Corner, SC | 237.0 MWh |
| #273 | Pine Grove | Pine Grove, PA | 96.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Green City Recovery, LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bavarian LFGTE | Walton, KY | 30.9 GWh | 36.1 mi |
| Bluebird Solar LLC | Cynthiana, KY | 142.3 GWh | 9.5 mi |
| Bluegrass Generating Station | LaGrange, KY | 207.3 GWh | 46.9 mi |
| Cooperative Solar One | Winchester, KY | 13.1 GWh | 27.2 mi |
| Crittenden Solar Facility | Dry Ridge, KY | 3.5 GWh | 28.3 mi |
| Dix Dam | Harrodsburg, KY | 104.7 GWh | 39.5 mi |
| E W Brown | Harrodsburg, KY | 1.8 TWh | 39.5 mi |
| East Bend | Union, KY | 2.9 TWh | 41.9 mi |
| Ghent | Ghent, KY | 10.2 TWh | 38.4 mi |
| H L Spurlock | Maysville, KY | 8.8 TWh | 46.5 mi |
| Haefling | Lexington, KY | 76.0 MWh | 18.4 mi |
| J K Smith | Winchester, KY | 1.0 TWh | 40.1 mi |
| L'Oreal Solar - Florence | Florence, KY | 1.5 GWh | 44.5 mi |
| Markland | Florence, IN | 252.6 GWh | 37.5 mi |
| Meldahl Hydroelectric Project | Foster, KY | 470.5 GWh | 36.9 mi |
| Mother Ann Lee | Harrodsburg, KY | 6.4 GWh | 36.9 mi |
| Paris (KY) | Paris, KY | 370.4 MWh | 19.4 mi |
| Pendleton County LFGTE | Butler, KY | 24.0 GWh | 28 mi |
| Walton 1 Solar Facility | Walton, KY | 2.7 GWh | 35 mi |
| Walton 2 Solar Facility | Walton, KY | 2.6 GWh | 35 mi |