Gary Court 1 & 2

170 Gary Court, Groton, CT 6340

Plant Summary Information

Gary Court 1 & 2 is ranked #14 out of 21 distillate fuel oil power plants in Connecticut in terms of total annual net electricity generation.

Gary Court 1 & 2 is comprised of 2 generators and generated 117.8 MWh during the 3-month period between September 2024 to December 2024.

Plant NameGary Court 1 & 2
Utility NameConnecticut Mun Elec Engy Coop
LocationSoutheastern Connecticut Planning Region, CT
Initial Operation DateJuly 2010
Last Update Dec 2024
Annual Generation 422.0 MWh
Annual Consumption 4.6 k MMBtu
Ranked #11,498 out of 12,288 Power Plants Nationwide
Ranked #539 out of 1,233 Distillate Fuel Oil Power Plants Nationwide
Ranked #149 out of 158 Connecticut Power Plants
Ranked #14 out of 21 Connecticut Distillate Fuel Oil Power Plants
Fuel Types Distillate Fuel Oil

Map of Gary Court 1 & 2

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Gary Court 1 & 2.

Create Your Account Today

Monthly Net Generation for Gary Court 1 & 2

Gary Court 1 & 2 Details

Summary Information
Plant NameGary Court 1 & 2 (57601)
Plant Address170 Gary Court, Groton, CT 6340
UtilityConnecticut Mun Elec Engy Coop (4180)
Latitude, Longitude41.3367, -72.02
Generation Dates on FileJan 2011 to Dec 2024
Initial Operation DateJuly 2010
Annual Generation 422.0 MWh
Fuel Types Distillate Fuel Oil
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusRegulated
NERC RegionNPCC
Balancing AuthorityISO New England Inc. (ISNE)
NAICS CodeUtilities (22)
Sector Electric Utility (1)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerGroton Dept of Utilities - (CT) (7716) CT
Grid Voltage 13.80 kV
Energy StorageNo

Generator GC1 Details Operating July 2010

TechnologyPetroleum Liquids
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity2.6 MW
Nameplate Power Factor0.8
Summer Capacity2.5 MW
Winter Capacity2.5 MW
Minimum Load1.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 2010
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator GC2 Details Operating July 2010

TechnologyPetroleum Liquids
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity2.6 MW
Nameplate Power Factor0.8
Summer Capacity2.5 MW
Winter Capacity2.5 MW
Minimum Load1.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 2010
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceDistillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Gary Court 1 & 2 Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Distillate Fuel Oil.

RankPlant NamePlant LocationAnnual Generation
#529PetersburgPetersburg, AK13.0 GWh
#530PretlowFranklin, VA448.0 MWh
#531IndianolaIndianola, IA446.0 MWh
#532Colstrip Energy LPColstrip, MT287.5 GWh
#533Electric Avenue FacilityCulpeper, VA443.0 MWh
#534Indiana University of PennsylvaniaIndiana, PA12.6 GWh
#535MeridianMeridian, MS434.0 MWh
#536Long Creek Waste Water PlantDallas, NC432.0 MWh
#537Lost NationGroveton, NH428.0 MWh
#538Bridgewater Power LPBridgewater, NH93.0 GWh
#540Falls CityFalls City, NE456.0 MWh
#541Ames GTAmes, IA420.0 MWh
#542Dominion/Lo MarManassas, VA418.0 MWh
#543New HamptonNew Hampton, IA676.0 MWh
#544Godwin Drive PlantManassas, VA416.0 MWh
#545Sam RayburnNursery, TX194.0 GWh
#546Bluegrass Generating StationLaGrange, KY112.5 GWh
#547NY Times Daily Production FacilityFlushing, NY409.0 MWh
#548SEMASS Resource RecoveryWest Wareham, MA568.9 GWh
#549William F Wyman HybridYarmouth, ME50.5 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Gary Court 1 & 2.

Plant NamePlant LocationAnnual GenerationDistance
Antares-GRE 314 East Lyme LLCEast Lyme, CT3.7 GWh12.4 mi
Bridge Street 1 & 2Groton, CT458.0 MWh3.7 mi
CMEEC - Navy NE TridentGroton, CT1.3 GWh5.1 mi
CMEEC - Polaris Park Solar HybridGordon, CT4.9 GWh4.3 mi
Connecticut CollegeNew London, CT9.1 GWh5.3 mi
Covanta Southeastern Connecticut CompanyPreston, CT112.2 GWh9.9 mi
Fishers Island 1Fisher's Island, NY151.0 MWh4.7 mi
Fort Hill 1, 2, 3 & 4Uncasville, CT519.0 MWh10.2 mi
Foxwoods CoGenMashantucket, CT10.8 GWh9.9 mi
MillstoneWaterford, CT17.1 TWh7.9 mi
Montville StationUncasville, CT27.8 GWh7.6 mi
Naval Sub Base New London Fuel CellGroton, CT34.2 GWh5.5 mi
North Stonington Solar Center, LLCNorth Stonington, CT30.5 GWh11 mi
Pfizer Groton Fuel CellGroton, CT30.1 GWh2.7 mi
Pfizer Groton PlantGroton, CT80.2 GWh3.1 mi
Rand Whitney CHP PlantMontville, CT132.5 GWh10 mi
Subase Microgrid ProjectGroton, CT43.1 GWh5.6 mi
Water Treatment 1 & 2Groton, CT303.0 MWh1.3 mi
White Rock Road LLCWesterly, RI7.4 GWh10.4 mi
Yale New Haven - New LondonNew London, CT14.6 GWh4.4 mi