Findlay Wind Farm
12367 Township Road 215, Findlay, OH 45840Plant Summary Information
Findlay Wind Farm is ranked #15 out of 22 wind farms in Ohio in terms of total annual net electricity generation.
Findlay Wind Farm generated 2.8 GWh during the 3-month period between September 2022 to December 2022.
Plant Name | Findlay Wind Farm |
---|---|
Utility Name | Findlay Wind Farm |
Location | Hancock County, OH |
Initial Operation Date | December 2015 |
Last Update | Dec 2022 |
Annual Generation | 9.2 GWh |
Annual Consumption | 35.8 k MMBtu |
Ranked #6,254 out of 11,455 Power Plants Nationwide | |
Ranked #1,135 out of 1,337 Wind Power Plants Nationwide | |
Ranked #91 out of 178 Ohio Power Plants | |
Ranked #15 out of 22 Ohio Wind Power Plants | |
Fuel Types | Wind |
Map of Findlay Wind Farm
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Findlay Wind Farm.
Monthly Net Generation for Findlay Wind Farm
Findlay Wind Farm Details
Summary Information | |
---|---|
Plant Name | Findlay Wind Farm (60015) |
Plant Address | 12367 Township Road 215 Findlay, OH 45840 |
Utility | Findlay Wind Farm (59760) |
Latitude, Longitude | 41.10122, -83.64439 |
Generation Dates on File | Jan 2016 to Dec 2022 |
Initial Operation Date | December 2015 |
Annual Generation | 9.2 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | PJM Interconnection, LLC (PJM) |
NAICS Code | Plastics and Rubber Products Manufacturing (326) |
Sector | Industrial Non-CHP (6) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Ohio Power Co (14006) OH |
Grid Voltage | 12.47 kV |
Energy Storage | No |
Generator WNDW1 Details Operating December 2015
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Jointly Owned |
Nameplate Capacity | 3 MW |
Summer Capacity | 3 MW |
Winter Capacity | 3 MW |
Minimum Load | 3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2015 |
Combined Heat & Power | No |
Sector Name | Industrial Non-CHP (6) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Turbines/Hydrokinetic Buoys | 2 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 2 |
---|---|
Predominant Turbine Manufacturer | Goldwind |
Predominant Turbine Model Number | GW 87/1500 |
Design Wind Speed | 13.1 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 262 |
Findlay Wind Farm Plant Owners
Owner Name | Address | Ownership |
---|---|---|
One Energy Capital LLC | 12385 Township Road 215, Findlay, OH 48540 | 5.00% |
Todd A.Stoller Living Trust | 100 W. Main Street, Haviland, OH 45851 | 95.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1125 | Searsburg Wind Turbine | Searsburg, VT | 10.7 GWh |
#1126 | Worthington | Worthington, MN | 10.8 GWh |
#1127 | Cuming County Renewables, LLC | Wisner, NE | 10.7 GWh |
#1128 | Anchor Wind, LLC | Mechanicsville, IA | 10.5 GWh |
#1129 | Wind Colebrook South | Colebrook, CT | 10.3 GWh |
#1130 | Ocotillo Windpower | Forsan, TX | 10.3 GWh |
#1131 | MA Military Reservation Wind Project | Otis ANG Base Bourne, MA | 10.2 GWh |
#1132 | Lincoln Heights II | Lake Benton, MN | 10.2 GWh |
#1133 | Lake Region Community Hybrid, LLC | Rothsay, MN | 10.0 GWh |
#1134 | Com Adam 1WF-1 | Sublette, IL | 9.5 GWh |
#1136 | Swauk Wind LLC | Thorp, WA | 9.1 GWh |
#1137 | CCC Hastings Wind Turbine | Hastings, NE | 8.9 GWh |
#1138 | Roseman | Anita, IA | 8.9 GWh |
#1139 | Seward Wind Farm | Seward, NE | 8.8 GWh |
#1140 | Valfilm Wind Project | Findlay, OH | 8.8 GWh |
#1141 | August Wind Farm | Clearfield, IA | 8.8 GWh |
#1142 | Fox Island Wind LLC | Vinalhaven, ME | 8.7 GWh |
#1143 | UL Advanced Wind Turbine Test Facility | Canyon, TX | 8.5 GWh |
#1144 | Foundation RRM | Cabazon, CA | 8.4 GWh |
#1145 | SPPW1, LLC | Upland, NE | 8.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Findlay Wind Farm.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AMP Napoleon Solar Facility | Napoleon, OH | 4.8 GWh | 32.1 mi |
Bowling Green Generating Station | Bowling Green, OH | 1.7 GWh | 20.5 mi |
Bowling Green Peaking | Bowling Green, OH | 1.0 GWh | 19.8 mi |
Bowling Green Wind | Bowling Green, OH | 5.9 GWh | 19.8 mi |
DG AMP Solar Bowling Green | Bowling Green, OH | 41.8 GWh | 20.6 mi |
Fremont Energy Center | Fremont, OH | 3.8 TWh | 31.5 mi |
Genoa Diesel Generating Station | Genoa, OH | 146.3 MWh | 31.8 mi |
Hardin Solar Energy LLC | Alger, OH | 303.7 GWh | 31.8 mi |
Hog Creek Wind Project | Ada, OH | 216.6 GWh | 21.7 mi |
Napoleon Solar I | Napoleon, OH | 9.4 GWh | 30.7 mi |
Ohio Northern University Solar Site | Ada, OH | 4.5 GWh | 25.7 mi |
POET Biorefining - Fostoria | Fostoria, OH | 20.2 GWh | 14.7 mi |
POET Biorefining - Leipsic, LLC | Leipsic, OH | 13.2 GWh | 17 mi |
Troy Energy LLC | Luckey, OH | 1.1 TWh | 27.7 mi |
Valfilm Wind Project | Findlay, OH | 8.8 GWh | 1.2 mi |
Whirlpool Corporation - Ottawa Wind Farm | Ottawa, OH | 4.9 GWh | 21.4 mi |
Woodville RTO BTM | Woodville, OH | 29.0 MWh | 28.5 mi |
Wyandot Solar Farm | Upper Sandusky, OH | 11.0 GWh | 22.9 mi |
Zephyr Wind | Findlay, OH | 13.2 GWh | 0.4 mi |
Zephyr Wind Project - 2.0 | Findlay, OH | 13.3 GWh | 0.7 mi |