Buffalo Ridge II LLC
21006 486th Avenue, Elkton, SD 57026Plant Summary Information
Buffalo Ridge II LLC is ranked #18 out of 49 power plants in South Dakota in terms of total annual net electricity generation.
Buffalo Ridge II LLC generated 167.9 GWh during the 3-month period between December 2024 to March 2025.
Plant Name | Buffalo Ridge II LLC |
---|---|
Utility Name | Avangrid Power LLC |
Location | Brookings County, SD |
Initial Operation Date | December 2010 |
Last Update | Mar 2025 |
Annual Generation | 410.3 GWh |
Annual Consumption | 1.5 M MMBtu |
Ranked #1,501 out of 12,288 Power Plants Nationwide | |
Ranked #433 out of 1,353 Wind Power Plants Nationwide | |
Ranked #18 out of 49 South Dakota Power Plants | |
Ranked #13 out of 25 South Dakota Wind Power Plants | |
Fuel Types | Wind |
Previous Operators |
Iberdrola Renewables Inc (2013 to 2014) Avangrid Renewables Inc (2015 to 2015) Avangrid Renewables LLC (2016 to 2023) Avangrid Power LLC (2024 to 2024) |
Map of Buffalo Ridge II LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Buffalo Ridge II LLC.
Monthly Net Generation for Buffalo Ridge II LLC
Buffalo Ridge II LLC Details
Summary Information | |
---|---|
Plant Name | Buffalo Ridge II LLC (57424) |
Plant Address | 21006 486th Avenue, Elkton, SD 57026 |
Utility | Avangrid Power LLC (15399) |
Latitude, Longitude | 44.5281, -96.6267 |
Generation Dates on File | Dec 2010 to Mar 2025 |
Initial Operation Date | December 2010 |
Annual Generation | 410.3 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | EG10-14-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Bonneville Power Administration (1738) OR |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator 1 Details Operating December 2010
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 210 MW |
Summer Capacity | 210 MW |
Winter Capacity | 210 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2010 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 105 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 105 |
---|---|
Predominant Turbine Manufacturer | Gamesa |
Predominant Turbine Model Number | G87-2.0 |
Design Wind Speed | 17.5 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 256 |
Buffalo Ridge II LLC Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#423 | Leaning Juniper Wind Power II | Arlington, OR | 416.6 GWh |
#424 | Osceola Windpower LLC | Harris, IA | 414.8 GWh |
#425 | Callahan Divide Wind Energy Center | Tusocola, TX | 414.3 GWh |
#426 | Smoky Hills Wind Project Phase II | Lincoln, KS | 414.3 GWh |
#427 | Senate Wind LLC | Bryson, TX | 413.7 GWh |
#428 | Morning Light Wind Farm | Adair, IA | 413.3 GWh |
#429 | Crossing Trails Wind Power Project LLC. | Seibert, CO | 412.5 GWh |
#430 | Lost Creek Wind Energy Facility | King City, MO | 412.5 GWh |
#431 | Keechi Wind | Jacksboro, TX | 411.9 GWh |
#432 | Skookumchuck Wind Facility | Rainier, WA | 410.3 GWh |
#434 | Rattlesnake Flat | Ritzville, WA | 408.9 GWh |
#435 | Clearwater Wind II | Miles City, MT | 408.7 GWh |
#436 | New Frontier Wind | Ruso, ND | 408.4 GWh |
#437 | Post Oak Wind LLC | Abilene, TX | 408.2 GWh |
#438 | Quilt Block Wind Farm LLC | Darlington, WI | 406.5 GWh |
#439 | Camp Grove Wind Farm | Wyoming, IL | 406.4 GWh |
#440 | Hopkins Ridge Wind | Dayton, WA | 405.8 GWh |
#441 | Wildhorse Mountain Wind Facility | Clayton, OK | 403.4 GWh |
#442 | Prairie Rose Wind Farm | Hardwick, MN | 402.5 GWh |
#443 | Panther Creek Wind Farm II | Big Spring, TX | 402.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Buffalo Ridge II LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Astoria Station | Astoria, SD | 325.1 GWh | 4.6 mi |
Autumn Hills LLC | Hendricks, MN | 3.7 GWh | 12.4 mi |
Blazing Star 2 Wind Farm | Hendricks, MN | 855.5 GWh | 14.7 mi |
Blazing Star Wind Farm 1 | Hendricks, MN | 853.8 GWh | 12.8 mi |
Buffalo Ridge I LLC | Elkton, SD | 89.0 GWh | 9.9 mi |
Buffalo Ridge Wind | Lake Benton, MN | 472.7 GWh | 17.8 mi |
Community Wind North LLC | Verdi Township, MN | 114.7 GWh | 22.3 mi |
Coyote Ridge | White, SD | 402.1 GWh | 6.6 mi |
Deer Creek Station | White, SD | 1.1 TWh | 10.2 mi |
Jack River LLC | Hendricks, MN | 3.7 GWh | 11.7 mi |
Jessica Mills LLC | Hendricks, MN | 3.7 GWh | 11.9 mi |
Julia Hills LLC | Hendricks, MN | 3.7 GWh | 11.5 mi |
Lake Benton I | Lake Benton, MN | 243.8 GWh | 20.5 mi |
Lakota Ridge LLC | Hendricks, MN | 16.7 GWh | 13.2 mi |
Lincoln Heights I | Lake Benton, MN | 10.0 GWh | 19.2 mi |
Lincoln Heights II | Lake Benton, MN | 6.6 GWh | 20.7 mi |
Shaokatan Hills LLC | Hendricks, MN | 12.1 GWh | 12 mi |
Sun River LLC | Hendricks, MN | 3.7 GWh | 11.6 mi |
Tatanka Ridge | Toronto, SD | 627.1 GWh | 5.1 mi |
Tsar Nicholas LLC | Hendricks, MN | 3.7 GWh | 12.1 mi |