Westside Wastewater Treatment Plant Hybr
415 N Broyles Ave, Fayetteville, AR 72704Plant Summary Information
Westside Wastewater Treatment Plant Hybr is ranked #38 out of 71 solar farms in Arkansas in terms of total annual net electricity generation.
Westside Wastewater Treatment Plant Hybr generated 1.4 GWh during the 3-month period between February 2026 to May 2026.
| Plant Name | Westside Wastewater Treatment Plant Hybr |
|---|---|
| Utility Name | Today's Power, Inc. |
| Location | Washington County, AR |
| Initial Operation Date | July 2019 |
| Last Update | May 2026 |
| Annual Generation | 3.3 GWh |
| Annual Consumption | 11.6 k MMBtu |
| Ranked #9,557 out of 13,081 Power Plants Nationwide | |
| Ranked #4,518 out of 7,015 Solar Power Plants Nationwide | |
| Ranked #79 out of 115 Arkansas Power Plants | |
| Ranked #38 out of 71 Arkansas Solar Power Plants | |
| Fuel Types | Solar |
Map of Westside Wastewater Treatment Plant Hybr
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Westside Wastewater Treatment Plant Hybr.
Monthly Net Generation for Westside Wastewater Treatment Plant Hybr
Monthly Plant Fuel Consumption for Westside Wastewater Treatment Plant Hybr
Westside Wastewater Treatment Plant Hybr Details
| Summary Information | |
|---|---|
| Plant Name | Westside Wastewater Treatment Plant Hybr (62683) |
| Plant Address | 415 N Broyles Ave, Fayetteville, AR 72704 |
| Utility | Today's Power, Inc. (61204) |
| Latitude, Longitude | 36.04135, -94.14008 |
| Generation Dates on File | Aug 2019 to May 2026 |
| Initial Operation Date | July 2019 |
| Annual Generation | 3.3 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | QF19-1011; QF19-1012 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | MRO |
| Balancing Authority | Southwest Power Pool (SWPP) |
| NAICS Code | Sewage Treatment Facilities (22132) |
| Sector | Commercial Non-CHP (4) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Ozarks Electric Coop Corp - (AR) (14289) AR |
| Grid Voltage | 12.47 kV / 0.48 kV |
| Energy Storage | Yes |
Generator FAYW1 Details Operating July 2019
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 5 MW |
| Summer Capacity | 5 MW |
| Winter Capacity | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | July 2019 |
| Combined Heat & Power | No |
| Sector Name | Commercial Non-CHP (4) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 5.8 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | Yes |
| Net Metering DC Capacity | 5.8 MW |
| Virtual Net Metering Agreement | No |
Generator FAYWB Details Operating July 2019
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 6 MW |
| Summer Capacity | 6 MW |
| Winter Capacity | 6 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | July 2019 |
| Combined Heat & Power | No |
| Sector Name | Commercial Non-CHP (4) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 13.1 |
|---|---|
| Maximum Charge Rate | 6 MW |
| Maximum Discharge Rate | 6 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 6 |
| Storage Enclosure Type | BL |
| System Peak Shaving | Yes |
| Excess Wind And Solar Generation | Yes |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 62683 |
| Direct Support Gen Id | FAYW1 |
| Support T D Asset | No |
Westside Wastewater Treatment Plant Hybr Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #4508 | Antlia Community Solar | Edgerton, MN | 3.4 GWh |
| #4509 | Fogarty CSG | Middletown, NY | 3.4 GWh |
| #4510 | Ontario Sun | Sandy Creek, NY | 3.4 GWh |
| #4511 | Johnstown | Johnstown, NY | 3.4 GWh |
| #4512 | Valley Creek Solar | Salem, OR | 3.4 GWh |
| #4513 | Terrell Riles Stovall | Dawson, GA | 3.4 GWh |
| #4514 | Washburn Road Solar | Freetown, MA | 3.4 GWh |
| #4515 | Panda Solar NC 4, LLC | Clarkton, NC | 3.4 GWh |
| #4516 | Manalapan Village Solar | Manalapan, NJ | 3.4 GWh |
| #4517 | Middletown NY 1 | Middletown, NY | 3.4 GWh |
| #4519 | Venable Solar 2 | Blythe, CA | 3.4 GWh |
| #4520 | Trimbelle (Pierce Pepin) | Hager City, WI | 3.4 GWh |
| #4521 | NJ - CS Energy - Berkeley 1 | Bayville, NJ | 3.4 GWh |
| #4522 | Colton Solar | Molalla, OR | 3.4 GWh |
| #4523 | Minisink Community Solar 2 LLC | Minisink, NY | 3.4 GWh |
| #4524 | MF Mesa Lane LLC | Morrisville, PA | 3.4 GWh |
| #4525 | Donati Solar | Seneca Falls, NY | 3.4 GWh |
| #4526 | Lister Avenue Solar | Newark, NJ | 3.4 GWh |
| #4527 | Riley III - Site 6 Community Solar | Fort Riley, KS | 3.4 GWh |
| #4528 | Rising Paper | Great Barrington, MA | 3.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Westside Wastewater Treatment Plant Hybr.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Arkansas Valley | Ozark, AR | 2.1 GWh | 40.5 mi |
| Beaver Dam (AR) | Eureka Springs, AR | 94.6 GWh | 30.9 mi |
| Berryville School District Solar | Berryville, AR | 1.8 GWh | 38.5 mi |
| Branch Solar Farm | Branch, AR | 7.2 GWh | 52.2 mi |
| City of Clarksville | Clarksville, AR | 663.0 MWh | 52.9 mi |
| City of Green Forest (Carroll) | Berryville, AR | 2.2 GWh | 40.2 mi |
| Elkins Generating Center | Elkins, AR | 20.2 GWh | 9.1 mi |
| Ellis Hydro | Van Buren, AR | 133.9 GWh | 48.5 mi |
| Fayetteville Public Schools (Ozarks) | Elkins, AR | 2.2 GWh | 7.1 mi |
| Flint Creek | Gentry, AR | 2.8 TWh | 26.1 mi |
| Hindsville | Hindsville, AR | 127.0 MWh | 16 mi |
| Noland Wastewater Treatment Plant Hybrid | Fayetteville, AR | 3.8 GWh | 5 mi |
| Ozark | Ozark, AR | 314.7 GWh | 43.5 mi |
| Ozark Solar Park | Lincoln, AR | 4.1 GWh | 15.3 mi |
| Ozarks Natural Energy Community Solar | Springdale, AR | 2.1 GWh | 9.1 mi |
| Springdale School District | Springdale, AR | 4.6 GWh | 9.9 mi |
| Thomas Fitzhugh | Ozark, AR | 472.3 GWh | 44.2 mi |
| UA Central Utility Plant | Fayetteville, AR | 36.5 GWh | 2.5 mi |
| Waste Management Eco Vista LFGTE | Springdale, AR | 21.5 GWh | 9.6 mi |
| XNA (NW AR Natnl Airport) | Bentonville, AR | 1.3 GWh | 18 mi |