WED NK Green
42 Thorton Way, North Kingstown, RI 2852Plant Summary Information
WED NK Green is ranked #17 out of 19 wind farms in Rhode Island in terms of total annual net electricity generation.
WED NK Green generated 802.0 MWh during the 3-month period between September 2025 to December 2025.
| Plant Name | WED NK Green |
|---|---|
| Utility Name | WED NK Green LLC |
| Location | Washington County, RI |
| Initial Operation Date | March 2012 |
| Last Update | Dec 2025 |
| Annual Generation | 2.7 GWh |
| Annual Consumption | 10.1 k MMBtu |
| Ranked #10,111 out of 13,081 Power Plants Nationwide | |
| Ranked #1,310 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #87 out of 106 Rhode Island Power Plants | |
| Ranked #17 out of 19 Rhode Island Wind Power Plants | |
| Fuel Types | Wind |
Map of WED NK Green
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for WED NK Green.
Monthly Net Generation for WED NK Green
Monthly Plant Fuel Consumption for WED NK Green
WED NK Green Details
| Summary Information | |
|---|---|
| Plant Name | WED NK Green (59295) |
| Plant Address | 42 Thorton Way, North Kingstown, RI 2852 |
| Utility | WED NK Green LLC (59097) |
| Latitude, Longitude | 41.58167, -71.48667 |
| Generation Dates on File | Jan 2013 to Dec 2025 |
| Initial Operation Date | March 2012 |
| Annual Generation | 2.7 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | ISO New England Inc. (ISNE) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | The Narragansett Electric Co (13214) RI |
| Grid Voltage | 12.47 kV |
| Energy Storage | No |
Generator NKG1 Details Operating March 2012
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 1.5 MW |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 0.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | March 2012 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 1 |
| Other Combustion Technology | No |
| Turbine Details | |
| Number Of Turbines | 1 |
|---|---|
| Predominant Turbine Manufacturer | Goldwind |
| Predominant Turbine Model Number | GW 82/1500 |
| Design Wind Speed | 12 MPH |
| Wind Quality Class | 3 - Low Wind |
| Turbine Hub Height Feet | 278.8 |
WED NK Green Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1300 | Bowling Green Wind | Bowling Green, OH | 3.3 GWh |
| #1301 | Helzel & Schwarzhoff 86 | Tehachapi, CA | 3.3 GWh |
| #1302 | Foundation AB | Fairfield, CA | 3.1 GWh |
| #1303 | Fairhaven Wind | Fairhaven, MA | 3.1 GWh |
| #1304 | Harpster Wind | Harpster, OH | 3.1 GWh |
| #1305 | Carstensen Wind | Pipestone, MN | 2.9 GWh |
| #1306 | Marshall Wind 6 LLC | Marshall, MN | 2.9 GWh |
| #1307 | Swauk Wind LLC | Thorp, WA | 2.9 GWh |
| #1308 | UMM Wind Turbine | Morris, MN | 2.9 GWh |
| #1309 | WED Coventry 1 | Coventry, RI | 2.8 GWh |
| #1311 | WED Coventry 4 | Coventry, RI | 2.7 GWh |
| #1312 | Welcome Wind Turbine | Welcome, MN | 2.6 GWh |
| #1313 | Scituate Wind | Scituate, MA | 2.5 GWh |
| #1314 | Sunset Breeze LLC | Rushmore, MN | 2.5 GWh |
| #1315 | Minnesota Breeze LLC | Rushmore, MN | 2.5 GWh |
| #1316 | G Flow Wind LLC | Rushmore, MN | 2.5 GWh |
| #1317 | Wolf Wind Enterprises LLC | Rushmore, MN | 2.5 GWh |
| #1318 | Green Acres Breeze LLC | Rushmore, MN | 2.5 GWh |
| #1319 | Mountain Lake | Mountain Lake, MN | 2.6 GWh |
| #1320 | St. Olaf Wind Turbine | Northfield, MN | 2.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding WED NK Green.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| 10 Briggs Solar NG, LLC (East) | East Greenwich, RI | 7.7 GWh | 3.6 mi |
| Dry Bridge Solar (Brown University) | North Kingstown, RI | 63.7 GWh | 2 mi |
| Exeter Mail CSG | Exeter, RI | 8.9 GWh | 5.1 mi |
| Exeter Renewables 1 | Exeter, RI | 16.2 GWh | 1.9 mi |
| Exeter Ten (CSG) | Exeter, RI | 4.8 GWh | 4.2 mi |
| GD West Greenwich Nooseneck I, LLC | West Greenwich, RI | 31.1 GWh | 8.5 mi |
| Hopkins Hill CSG | West Greenwich, RI | 9.6 GWh | 4.8 mi |
| Kearsarge SKSC1 LLC | South Kingstown, RI | 5.5 GWh | 7.6 mi |
| Kearsarge SKSC2 LLC | South Kingstown, RI | 5.6 GWh | 6.2 mi |
| Kilvert | Warwick, RI | 8.3 GWh | 10.3 mi |
| McAllister Landfill | Portsmouth, RI | 1.5 GWh | 10.2 mi |
| North Kingstown Solar LLC | North Kingstown, RI | 3.3 GWh | 3.3 mi |
| Robin Hollow Solar | West Greenwich, RI | 68.9 GWh | 8.4 mi |
| Tank Farm 4 | Portsmouth, RI | 13.1 GWh | 10.2 mi |
| Toray Plastic America's CHP Plant | North Kingstown, RI | 156.8 GWh | 3.2 mi |
| University Solar, LLC | West Greenwich, RI | 27.5 GWh | 9.2 mi |
| WED Kingstown Solar I - East Array | Washington, RI | 4.6 GWh | 9.2 mi |
| WED Kingstown Solar I, LLC - West | Richmond, RI | 2.1 GWh | 9.5 mi |
| West Davisville Solar | North Kingstown, RI | 2.9 GWh | 1.6 mi |
| White Brook Renewables PV | West Greenwich, RI | 6.9 GWh | 9.9 mi |