Uwharrie Mountain Renewable
561 Landfill Road, Mt. Gilead, NC 27306Plant Summary Information
Uwharrie Mountain Renewable is ranked #3 out of 17 landfill gas power plants in North Carolina in terms of total annual net electricity generation.
Uwharrie Mountain Renewable is comprised of 6 generators and generated 8.1 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Uwharrie Mountain Renewable |
---|---|
Utility Name | Uwharrie Mountain Renewable Energy, LLC |
Location | Montgomery County, NC |
Initial Operation Date | July 2014 |
Last Update | Dec 2024 |
Annual Generation | 32.1 GWh |
Annual Consumption | 384.3 k MMBtu |
Ranked #4,551 out of 12,288 Power Plants Nationwide | |
Ranked #76 out of 292 Landfill Gas Power Plants Nationwide | |
Ranked #123 out of 868 North Carolina Power Plants | |
Ranked #3 out of 17 North Carolina Landfill Gas Power Plants | |
Fuel Types | Landfill Gas |
Map of Uwharrie Mountain Renewable
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Uwharrie Mountain Renewable.
Monthly Net Generation for Uwharrie Mountain Renewable
Uwharrie Mountain Renewable Details
Summary Information | |
---|---|
Plant Name | Uwharrie Mountain Renewable (58526) |
Plant Address | 561 Landfill Road, Mt. Gilead, NC 27306 |
Utility | Uwharrie Mountain Renewable Energy, LLC (58502) |
Latitude, Longitude | 35.33297, -79.96494 |
Generation Dates on File | Jul 2014 to Dec 2024 |
Initial Operation Date | July 2014 |
Annual Generation | 32.1 GWh |
Fuel Types | Landfill Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 13-343-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Duke Energy Progress East (CPLE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | n/a |
Ash Impoundment | No |
Transmission / Distribution Owner | Duke Energy Progress - (NC) (3046) NC |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator 1 Details Operating July 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | n/a |
RTO ISO Location Designation For Reporting Wholesale Sales Data | n/a |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 1.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2014 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating July 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | n/a |
RTO ISO Location Designation For Reporting Wholesale Sales Data | n/a |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 1.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2014 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 3 Details Operating July 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | n/a |
RTO ISO Location Designation For Reporting Wholesale Sales Data | n/a |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 1.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2014 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 4 Details Operating July 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | n/a |
RTO ISO Location Designation For Reporting Wholesale Sales Data | n/a |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 1.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2014 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 5 Details Operating July 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | n/a |
RTO ISO Location Designation For Reporting Wholesale Sales Data | n/a |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 1.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2014 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 6 Details Operating July 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | n/a |
RTO ISO Location Designation For Reporting Wholesale Sales Data | n/a |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.6 MW |
Winter Capacity | 1.6 MW |
Minimum Load | 1.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2014 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Subcritical Technology | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Uwharrie Mountain Renewable Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Landfill Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#66 | Ridgeview | Whitelaw, WI | 35.6 GWh |
#67 | Springhill Gas Recovery Plant | Campbellton, FL | 35.3 GWh |
#68 | Zimmerman Energy | Argos, IN | 34.7 GWh |
#69 | Richmond Energy | Henrico, VA | 33.4 GWh |
#70 | Taylor | Mauk, GA | 33.4 GWh |
#71 | Hyland LFGTE Facility | Angelica, NY | 33.3 GWh |
#72 | Fitchburg Gas Recovery | Westminster, MA | 32.3 GWh |
#73 | Modern Innovative Energy LLC | Youngstown, NY | 32.3 GWh |
#74 | Ameresco Vasco Road | Livermore, CA | 32.3 GWh |
#75 | Austin Gas Recovery | Austin, TX | 32.2 GWh |
#77 | LRI LFGTE Facility | Graham, WA | 32.1 GWh |
#78 | Amelia | Jetersville, VA | 33.9 GWh |
#79 | Ameresco Forward | Manteca, CA | 31.8 GWh |
#80 | Chestnut Ridge Gas Recovery | Heiskell, TN | 31.1 GWh |
#81 | Stanton Energy Center | Orlando, FL | 4.1 TWh |
#82 | Ameresco San Joaquin | Linden, CA | 30.7 GWh |
#83 | Prairie View I & II LFGTE | Wyatt, IN | 30.5 GWh |
#84 | Pecan Row Landfill To Electric Facility | Valdosta, GA | 30.5 GWh |
#85 | Model City Energy Facility | Youngstown, NY | 30.1 GWh |
#86 | Georgia LFG Oak Grove Plant | Winder, GA | 38.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Uwharrie Mountain Renewable.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Achilles Solar | Troy, NC | 9.8 GWh | 3.5 mi |
Albemarle Hospital Unit | Albemarle, NC | 120.0 MWh | 13.1 mi |
Albemarle Prime Power Park | New London, NC | 90.0 MWh | 11.7 mi |
Biscoe Solar LLC | Biscoe, NC | 8.4 GWh | 11.5 mi |
Cabin Creek Solar, LLC | Biscoe, NC | 161.4 GWh | 12.6 mi |
Copperfield | Troy, NC | 3.4 GWh | 1.6 mi |
ESA Albemarle NC Solar | Albemarle, NC | 4.3 GWh | 9.9 mi |
Falls Hydro | Badin, NC | 126.5 GWh | 7.5 mi |
Fisher Solar Farm - NC | Oakboro, NC | 9.1 GWh | 7.5 mi |
Gilead | Gilead, NC | 5.8 GWh | 9.7 mi |
Haywood Farm Solar, LLC | Troy, NC | 9.1 GWh | 2.9 mi |
Hector Farm | Troy, NC | 9.4 GWh | 4.3 mi |
Kalish Farm Solar | Candor, NC | 9.1 GWh | 13.9 mi |
Montgomery Solar LLC | Biscoe, NC | 34.4 GWh | 11.1 mi |
Narrows (NC) | Badin, NC | 487.5 GWh | 9.3 mi |
Samarcand Solar Farm, LLC | Biscoe, NC | 7.6 GWh | 15.3 mi |
Spicewood Solar Farm LLC | Eagle Springs, NC | 9.0 GWh | 15 mi |
Stanly Solar, LLC | Albemarle, NC | 98.1 GWh | 15.5 mi |
Tillery | Mount Gilead, NC | 184.2 GWh | 10.4 mi |
Whiskey Solar | Cumberland, NC | 11.5 GWh | 13.5 mi |