Spicer Meadow Project
477 Bret Hart Drive, Murphys, CA 95247Plant Summary Information
Spicer Meadow Project is ranked #122 out of 206 hydroelectric power plants in California in terms of total annual net electricity generation.
Spicer Meadow Project is comprised of 3 generators and generated 8.5 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Spicer Meadow Project |
---|---|
Utility Name | Northern California Power Agny |
Location | Tuolumne County, CA |
Initial Operation Date | November 1989 |
Last Update | Dec 2024 |
Annual Generation | 21.6 GWh |
Annual Consumption | 81.3 k MMBtu |
Ranked #5,101 out of 12,299 Power Plants Nationwide | |
Ranked #721 out of 1,323 Water Power Plants Nationwide | |
Ranked #683 out of 1,566 California Power Plants | |
Ranked #122 out of 206 California Water Power Plants | |
Fuel Types | Water |
Map of Spicer Meadow Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Spicer Meadow Project.
Monthly Net Generation for Spicer Meadow Project
Spicer Meadow Project Details
Summary Information | |
---|---|
Plant Name | Spicer Meadow Project (54554) |
Plant Address | 477 Bret Hart Drive, Murphys, CA 95247 |
Utility | Northern California Power Agny (40613) |
Latitude, Longitude | 38.3914, -120.0008 |
Generation Dates on File | Jan 2004 to Dec 2024 |
Initial Operation Date | November 1989 |
Annual Generation | 21.6 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Spicer Meadow Reservoir |
Ash Impoundment | No |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 21.00 kV |
Energy Storage | No |
Generator GEN1 Details Operating November 1989
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | SPICER_1_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SPICER_1_UNITS-APND |
Nameplate Capacity | 2.7 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 0.8 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | November 1989 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Generator GEN2 Details Operating November 1989
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | SPICER_1_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SPICER_1_UNITS-APND |
Nameplate Capacity | 2.7 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 0.8 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | November 1989 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Generator GEN3 Details Operating November 1989
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | SPICER_1_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | SPICER_1_UNITS-APND |
Nameplate Capacity | 0.5 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 0.5 MW |
Winter Capacity | 0.5 MW |
Minimum Load | 0.1 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | November 1989 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Spicer Meadow Project Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Calaveras County Water Dist | P O Box 846427 East St Charles Street, San Andreas, CA 95246 | Generator GEN1 | 100.00% |
Calaveras County Water Dist | P O Box 846427 East St Charles Street, San Andreas, CA 95246 | Generator GEN2 | 100.00% |
Calaveras County Water Dist | P O Box 846427 East St Charles Street, San Andreas, CA 95246 | Generator GEN3 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#711 | Hatchet Creek Project | Montgomery Creek, CA | 22.6 GWh |
#712 | South Edwards | Fine, NY | 22.5 GWh |
#713 | Tunnel 1 Power Project | Nyssa, OR | 22.4 GWh |
#714 | Granite Shoals | Marble Falls, TX | 22.4 GWh |
#715 | Taylorville | Croghan, NY | 22.3 GWh |
#716 | Varick | Oswego, NY | 22.2 GWh |
#717 | Ellsworth Hydro Station | Ellsworth, ME | 21.9 GWh |
#718 | Mechanicville Hydroelectric Station | Mechanicville, NY | 21.8 GWh |
#719 | A G Wishon | North Fork, CA | 21.6 GWh |
#720 | Kansas River Project | Lawrence, KS | 21.6 GWh |
#722 | Black Bear Lake | Craig, AK | 21.4 GWh |
#723 | Big Fork | Big Fork, MT | 21.3 GWh |
#724 | Orono B | Orono, ME | 21.3 GWh |
#725 | Rio | Glen Spey, NY | 21.2 GWh |
#726 | Mosinee Mill | Mosinee, WI | 125.8 GWh |
#727 | Etiwanda | Rancho Cucamonga, CA | 21.1 GWh |
#728 | Heart Mountain | Cody, WY | 21.0 GWh |
#729 | Wainiha Hydro | Hanalei, HI | 20.9 GWh |
#730 | Moyie Springs | Moyie Springs, ID | 20.9 GWh |
#731 | James W. Broderick Hydropower Plant | Pueblo, CO | 20.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Spicer Meadow Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Angels | Angels Camp, CA | 6.3 GWh | 36.6 mi |
Beardsley | None, CA | 55.7 GWh | 13.7 mi |
Camino | Camino, CA | 276.6 GWh | 41.9 mi |
Collierville Powerhouse | Murphys, CA | 465.2 GWh | 26.7 mi |
Dion R Holm | Groveland, CA | 492.3 GWh | 34.2 mi |
Donnells | None, CA | 219.2 GWh | 10.2 mi |
Electra | Jackson, CA | 244.8 GWh | 36.5 mi |
Jones Fork | Fresh Pond, CA | 8.6 GWh | 37.8 mi |
Murphys | Murphys, CA | 15.5 GWh | 29.5 mi |
Phoenix | Sonora, CA | 8.0 GWh | 30.5 mi |
R C Kirkwood | Groveland, CA | 412.1 GWh | 35.6 mi |
Robbs Peak | Fresh Pond, CA | 37.0 GWh | 40.4 mi |
Salt Springs | Pioneer, CA | 107.7 GWh | 13.9 mi |
Sand Bar Power Plant | Stanislaus Ntl. Fores, CA | 85.5 GWh | 16.3 mi |
Sierra Pacific Sonora | Standard, CA | 34.9 GWh | 34 mi |
Spring Gap | Long Barn, CA | 29.8 GWh | 15.4 mi |
Stanislaus | Vallecito, CA | 315.8 GWh | 26.6 mi |
Tiger Creek | Pioneer, CA | 225.1 GWh | 26.9 mi |
Union Valley | Fresh Pond, CA | 76.5 GWh | 40.5 mi |
West Point PH | Pioneer, CA | 88.9 GWh | 29.8 mi |