Solar BESS Hybrid
1000 EMC PKWY, Marietta, GA 30060Plant Summary Information
Solar BESS Hybrid is ranked #132 out of 150 solar farms in Georgia in terms of total annual net electricity generation.
Solar BESS Hybrid generated 437.7 MWh during the 3-month period between September 2024 to December 2024.
Plant Name | Solar BESS Hybrid |
---|---|
Utility Name | Cobb Electric Membership Corporation |
Location | Cobb County, GA |
Initial Operation Date | October 2020 |
Last Update | Dec 2024 |
Annual Generation | 2.3 GWh |
Annual Consumption | 9.5 k MMBtu |
Ranked #9,963 out of 12,288 Power Plants Nationwide | |
Ranked #4,817 out of 6,174 Solar Power Plants Nationwide | |
Ranked #219 out of 246 Georgia Power Plants | |
Ranked #132 out of 150 Georgia Solar Power Plants | |
Fuel Types | Solar : 94.6% Natural Gas : 5.4% |
Map of Solar BESS Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Solar BESS Hybrid.
Monthly Net Generation for Solar BESS Hybrid
Solar BESS Hybrid Details
Summary Information | |
---|---|
Plant Name | Solar BESS Hybrid (63535) |
Plant Address | 1000 EMC PKWY, Marietta, GA 30060 |
Utility | Cobb Electric Membership Corporation (63260) |
Latitude, Longitude | 33.97935, -84.55613 |
Generation Dates on File | Oct 2020 to Dec 2024 |
Initial Operation Date | October 2020 |
Annual Generation | 2.3 GWh |
Fuel Types | Solar : 94.6% Natural Gas : 5.4% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Georgia Transmission Corp (7197) |
Grid Voltage | 480.00 kV / 240.00 kV |
Energy Storage | Yes |
Natural Gas Information | |
Local Distribution Company (LDC) | Other - See pipeline notes. |
Natural Gas Storage | No |
Generator SOLAR Details Operating October 2020
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 1.5 MW |
Summer Capacity | 1.4 MW |
Winter Capacity | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Solar Details | |
Dual Axis Tracking | Yes |
---|---|
Fixed Tilt | No |
East West Fixed Tilt | Yes |
DC Net Capacity | 1.8 MW |
Crystalline Silicon | Yes |
Virtual Net Metering Agreement | No |
Generator TEST Details Operating October 2020
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 1 MW |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 1H |
Cofire Fuels | No |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 4 |
---|---|
Maximum Charge Rate | 1 MW |
Maximum Discharge Rate | 1 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 1 |
Storage Enclosure Type | BL |
Arbitrage | Yes |
System Peak Shaving | P |
Backup Power | Yes |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Independent | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 63535 |
Direct Support Gen Id | SOLAR |
Support T D Asset | No |
Generator NG Details Operating September 2022
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
Nameplate Capacity | 1 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Minimum Load | 0.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Solar BESS Hybrid Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Gas South | 3625 Cumberland Blvd SE, Atlanta, GA 30339 | Generator SOLAR | 100.00% |
Gas South | 3625 Cumberland Blvd SE, Atlanta, GA 30339 | Generator TEST | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#4807 | Broadway 2 - UC Riverside | Riverside, CA | 2.3 GWh |
#4808 | USS Cosmo Solar LLC (CSG) | Danube, MN | 2.2 GWh |
#4809 | McCormick & Co. Inc. at Belcamp | Belcamp, MD | 2.2 GWh |
#4810 | Case Vander Eyk, Jr Dairy Solar | Pixley, CA | 2.2 GWh |
#4811 | 601 Doremus CDG | Newark, NJ | 2.2 GWh |
#4812 | USS Rosebud Solar LLC | Morgan, MN | 2.2 GWh |
#4813 | Petit Jean | Clinton, AR | 2.2 GWh |
#4814 | Emerald Marshfields, LLC | Marshfield, MA | 2.2 GWh |
#4815 | Ledgeview | Fond du Lac, WI | 2.2 GWh |
#4816 | Coventry Photovoltaic, LLC | Coventry, VT | 2.2 GWh |
#4818 | IMPA Knightstown Solar Park | Knightstown, IN | 2.2 GWh |
#4819 | West Boylston Community Shared Solar | West Boylston, MA | 2.2 GWh |
#4820 | Sabert Solar | Sayreville, NJ | 2.2 GWh |
#4821 | DIA 9 | Denver, CO | 2.2 GWh |
#4822 | Tom Sifers Solar | Fraser, CO | 2.2 GWh |
#4823 | Curry Solar | Reidsville, GA | 2.2 GWh |
#4824 | Main Street Solar Project | Rutland, VT | 2.2 GWh |
#4825 | Lakeland Electric Co. (FL) - Airport II | Lakeland, FL | 2.2 GWh |
#4826 | Skidmore College | Saratoga Springs, NY | 2.2 GWh |
#4827 | Novel Martens Solar LLC(CSG) | Lafayette, MN | 2.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Solar BESS Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Allatoona | Cartersville, GA | 122.5 GWh | 16.1 mi |
Atlanta Falcons Solar | Atlanta, GA | 1.1 GWh | 17.9 mi |
Bartow Davidson | Cartersville, GA | 6.0 GWh | 24.8 mi |
Bowen | Cartersville, GA | 11.1 TWh | 23.3 mi |
Buford | Buford, GA | 147.1 GWh | 30.2 mi |
CNN Center | Atlanta, GA | 77.0 MWh | 17.8 mi |
Georgia LFG Richland Creek Plant | Buford, GA | 54.1 GWh | 31.6 mi |
Gordon Pine Hall | Fairmount, GA | 4.5 GWh | 33 mi |
Gordon Thompson | Fairmount, GA | 4.3 GWh | 33.1 mi |
Jack McDonough | Smyrna, GA | 17.6 TWh | 11.7 mi |
MAS ASB Cogen Plant | Atlanta, GA | 37.8 GWh | 24.3 mi |
Morgan Falls | Dunwoody, GA | 31.6 GWh | 9.9 mi |
Polk Cedartown 2 | Cedartown, GA | 3.8 GWh | 37.8 mi |
Polk County GA S1, LLC | Cedartown, GA | 6.5 GWh | 37.9 mi |
Rockmart | Rockmart, GA | 5.4 GWh | 26.8 mi |
Sewell Creek Energy | Cedartown, GA | 522.9 GWh | 41.4 mi |
Sun Trust Plaza | Atlanta, GA | 22.0 MWh | 17.8 mi |
Tech Square Microgrid | Atlanta, GA | 1.4 GWh | 17 mi |
Turnipseed Solar, LLC | Douglasville, GA | 5.3 GWh | 20.6 mi |
Yates | Newnan, GA | 2.2 TWh | 40.8 mi |