Optimum Wind 5 LLC
Highway 30 & 590th Ave, Nevada, IA 50201Plant Summary Information
Optimum Wind 5 LLC is ranked #94 out of 123 wind farms in Iowa in terms of total annual net electricity generation.
Optimum Wind 5 LLC generated 2.8 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Optimum Wind 5 LLC |
|---|---|
| Utility Name | Optimum Wind 5 LLC |
| Location | Story County, IA |
| Initial Operation Date | March 2017 |
| Last Update | Dec 2024 |
| Annual Generation | 9.0 GWh |
| Annual Consumption | 32.4 k MMBtu |
| Ranked #6,425 out of 12,539 Power Plants Nationwide | |
| Ranked #1,154 out of 1,362 Wind Power Plants Nationwide | |
| Ranked #136 out of 279 Iowa Power Plants | |
| Ranked #94 out of 123 Iowa Wind Power Plants | |
| Fuel Types | Wind |
Map of Optimum Wind 5 LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Optimum Wind 5 LLC.
Monthly Net Generation for Optimum Wind 5 LLC
Optimum Wind 5 LLC Details
| Summary Information | |
|---|---|
| Plant Name | Optimum Wind 5 LLC (59223) |
| Plant Address | Highway 30 & 590th Ave, Nevada, IA 50201 |
| Utility | Optimum Wind 5 LLC (59017) |
| Latitude, Longitude | 42.014, -93.51806 |
| Generation Dates on File | Mar 2017 to Dec 2024 |
| Initial Operation Date | March 2017 |
| Annual Generation | 9.0 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | QF13-613-001 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Interstate Power and Light Co (9417) IA |
| Grid Voltage | 12.47 kV |
| Energy Storage | No |
Generator WT1 Details Operating March 2017
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 3 MW |
| Summer Capacity | 3 MW |
| Winter Capacity | 3 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2017 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 1 |
| Turbine Details | |
| Number Of Turbines | 1 |
|---|---|
| Predominant Turbine Manufacturer | Acciona |
| Predominant Turbine Model Number | AW125/3000 |
| Design Wind Speed | 22.8 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 287 |
Optimum Wind 5 LLC Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1144 | Leonardo Wind 1 LLC | Alden, IA | 10.0 GWh |
| #1145 | Redwood Falls Wind | Redwood Falls, MN | 9.7 GWh |
| #1146 | Anderson Wind I | Hagerman, NM | 9.7 GWh |
| #1147 | Springview | Springview, NE | 9.7 GWh |
| #1148 | WED Coventry 2 | Coventry, RI | 9.7 GWh |
| #1149 | MA Military Reservation Wind Project | Otis ANG Base Bourne, MA | 9.7 GWh |
| #1150 | Coram Energy LLC | Tehachapi, CA | 9.5 GWh |
| #1151 | Coram Energy LLC (4.5MW) | Tehachapi, CA | 9.5 GWh |
| #1152 | REG Juhl Glenville Wind, LLC | Albert Lea, MN | 9.4 GWh |
| #1153 | Cisco | Brewster, MN | 9.1 GWh |
| #1155 | Foundation RRM | Cabazon, CA | 8.9 GWh |
| #1156 | Worthington | Worthington, MN | 9.0 GWh |
| #1157 | Cuming County Renewables, LLC | Wisner, NE | 8.9 GWh |
| #1158 | UL Advanced Wind Turbine Test Facility | Canyon, TX | 8.8 GWh |
| #1159 | Porterhouse Wind (4) LLC | Gruver, TX | 8.7 GWh |
| #1160 | Optimum Wind 6 LLC | Nevada, IA | 8.7 GWh |
| #1161 | Michelangelo Wind 3 LLC | Huxley, IA | 8.6 GWh |
| #1162 | Uilk Wind LLC | Pipestone, MN | 8.6 GWh |
| #1163 | WED Coventry 6 | Coventry, RI | 8.5 GWh |
| #1164 | Carleton College | Northfield, MN | 8.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Optimum Wind 5 LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Ames Electric Services Power Plant | Ames, IA | 305.6 GWh | 4.7 mi |
| Ames GT | Ames, IA | 420.0 MWh | 3.4 mi |
| Fareway Customer Hosted 1 MW Solar | Boone, IA | 1.1 GWh | 17.7 mi |
| FPL Energy Story Wind LLC | Zearing, IA | 525.2 GWh | 14.1 mi |
| Garden Wind LLC | Zearing, IA | 345.4 GWh | 16.3 mi |
| IA - City of Ames - Airport Road | Ames, IA | 3.1 GWh | 5.1 mi |
| Iowa State University | Ames, IA | 80.9 GWh | 6.3 mi |
| ISU Customer Hosted 1MW Solar Project | Ames, IA | 1.6 GWh | 7.5 mi |
| Michelangelo Wind 1 LLC | Huxley, IA | 7.9 GWh | 10.7 mi |
| Michelangelo Wind 3 LLC | Huxley, IA | 8.6 GWh | 0.4 mi |
| Michelangelo Wind 4 LLC | Ames, IA | 10.4 GWh | 9.7 mi |
| NCAH Central Utility Plant | Ames, IA | 3.3 GWh | 3.9 mi |
| Optimum Wind 3 LLC | Nevada, IA | 10.4 GWh | 0.4 mi |
| Optimum Wind 4 LLC | Nevada, IA | 10.5 GWh | 0.2 mi |
| Optimum Wind 6 LLC | Nevada, IA | 8.7 GWh | 0.6 mi |
| Optimum Wind 7 LLC | Nevada, IA | 11.0 GWh | 4.6 mi |
| POET Biorefining - Jewell | Jewell, IA | 21.7 GWh | 22.9 mi |
| State Center | State Center, IA | 75.0 MWh | 18.2 mi |
| Story City | Story City, IA | 97.0 MWh | 12.6 mi |
| Story City Wind Project | Story City, IA | 5.1 GWh | 14 mi |