Kansas River Project

500 South Powerhouse Road, Lawrence, KS 66044

Plant Summary Information

Kansas River Project is ranked #1 out of 1 hydroelectric power plants in Kansas in terms of total annual net electricity generation.

Kansas River Project is comprised of 11 generators and generated 7.1 GWh during the 3-month period between May 2026 to August 2026.

Plant NameKansas River Project
Utility NameBowersock Mills & Power Co
LocationDouglas County, KS
Initial Operation DateJanuary 1920
Last Update Aug 2026
Annual Generation 26.1 GWh
Annual Consumption 97.0 k MMBtu
Ranked #5,107 out of 13,301 Power Plants Nationwide
Ranked #638 out of 1,316 Water Power Plants Nationwide
Ranked #74 out of 176 Kansas Power Plants
Ranked #1 out of 1 Kansas Water Power Plants
Fuel Types Water

Map of Kansas River Project

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Kansas River Project.

Create Your Account Today

Monthly Net Generation for Kansas River Project

Monthly Plant Fuel Consumption for Kansas River Project

Kansas River Project Details

Summary Information
Plant NameKansas River Project (10279)
Plant Address500 South Powerhouse Road, Lawrence, KS 66044
UtilityBowersock Mills & Power Co (2048)
Latitude, Longitude38.97402, -95.23508
Generation Dates on FileJun 2001 to Aug 2026
Initial Operation DateJanuary 1920
Annual Generation 26.1 GWh
Fuel Types Water
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number91-112-000
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionMRO
Balancing AuthoritySouthwest Power Pool (SWPP)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water SourceKansas River
Ash Impoundment No
Transmission / Distribution OwnerEvergy Kansas Central, Inc (22500) KS
Grid Voltage 12.47 kV
Energy StorageNo

Generator 1 Details Operating January 1920

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.4 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJanuary 1920
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M

Generator 2 Details Operating July 1922

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 1922
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 3 Details Operating July 1922

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 1922
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 4 Details Operating July 1922

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity0.3 MW
Nameplate Power Factor1
Summer Capacity0.3 MW
Winter Capacity0.3 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 1922
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 5 Details Operating July 1922

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity0.4 MW
Nameplate Power Factor1
Summer Capacity0.4 MW
Winter Capacity0.4 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 1922
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 6 Details Operating May 1925

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity0.4 MW
Nameplate Power Factor1
Summer Capacity0.4 MW
Winter Capacity0.4 MW
Minimum Load0.2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 1925
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 7 Details Operating May 1925

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales Data`KACYBOWERSOCK
Nameplate Capacity0.4 MW
Nameplate Power Factor1
Summer Capacity0.4 MW
Winter Capacity0.4 MW
Minimum Load0.2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 1925
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 10 Details Operating December 2012

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity1.3 MW
Nameplate Power Factor1
Summer Capacity1.3 MW
Winter Capacity1.3 MW
Minimum Load0.9 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2012
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 11 Details Operating December 2012

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity1 MW
Nameplate Power Factor1
Summer Capacity1 MW
Winter Capacity1 MW
Minimum Load0.8 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2012
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 8 Details Operating December 2012

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity1 MW
Nameplate Power Factor1
Summer Capacity1 MW
Winter Capacity1 MW
Minimum Load0.8 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2012
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Generator 9 Details Operating December 2012

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
RTO ISO LMP Node DesignationKACYBOWERSOCK
RTO ISO Location Designation For Reporting Wholesale Sales DataKACYBOWERSOCK
Nameplate Capacity1.3 MW
Nameplate Power Factor1
Summer Capacity1.3 MW
Winter Capacity1.3 MW
Minimum Load0.9 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2012
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWater
Solid Fuel Gasification No
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo

Kansas River Project Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Water.

RankPlant NamePlant LocationAnnual Generation
#628Lyons Falls HydroelectricLyons Falls, NY27.1 GWh
#629Little Falls (MN)Little Falls, MN27.0 GWh
#630Rio Bravo Hydro ProjectBakersfield, CA27.0 GWh
#631McSwainSnelling, CA26.9 GWh
#632Bulls BridgeNew Milford, CT26.9 GWh
#633Drop 2 (CA)Holtville, CA26.7 GWh
#634McClure DamMarquette, MI26.5 GWh
#635Deerfield 3Buckland, MA26.5 GWh
#636South Forks HydroHansen, ID26.3 GWh
#637PortalLakeshore, CA26.2 GWh
#639Stevens PointStevens Point, WI25.9 GWh
#640PHP 2Sandy, OR25.8 GWh
#641KingsfordKingsford, MI25.7 GWh
#642Falls VillageFalls Village, CT25.7 GWh
#643InghamsLittle Falls, NY25.6 GWh
#644AlconaGlennie, MI25.5 GWh
#645Chili BarPlacerville, CA25.2 GWh
#646PetersonMilton, VT25.1 GWh
#647High Falls - Croghan NYCroghan, NY25.0 GWh
#648Pyrites PlantPyrites, NY24.9 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Kansas River Project.

Plant NamePlant LocationAnnual GenerationDistance
Baldwin City Plant No 1Baldwin City, KS13.0 MWh14 mi
Baldwin City Plant No 2Baldwin City, KS122.0 MWh14.6 mi
BPU Solar FarmKansas City, KS1.7 GWh31.8 mi
BurlingameBurlingame, KS9.0 MWh35.7 mi
FreeState Crooked Post Solar ITopeka, KS3.4 GWh31.2 mi
FreeState Kiro Solar ISilver Lake, KS2.2 GWh31 mi
FreeState Stull Solar ILeCompton, KS2.9 GWh10.4 mi
Gardner Energy CenterGardner, KS504.0 MWh21 mi
Grand Ave PlantKansas City, MO42.5 GWh36.4 mi
IatanWeston, MO5.6 TWh35.4 mi
Lawrence Energy CenterLawrence, KS1.7 TWh2.9 mi
Nearman CreekKansas, KS1.2 TWh31.8 mi
OsawatomieMiami, KS53.6 GWh35.4 mi
Osawatomie Power Plant North SubOsawatomie, KS3.0 MWh35.9 mi
Osawatomie Power Plant South SubOsawatomie, KS3.0 MWh36.4 mi
Osawatomie SolarOsawatomie, KS10.8 GWh35.1 mi
OskaloosaOskaloosa, KS2.1 GWh13 mi
QuindaroKansas, KS7.8 GWh34.2 mi
Waste Management Rolling Meadows LFGTETopeka, KS48.1 GWh30 mi
West GardnerJohnson, KS239.2 GWh18.6 mi