Hardscrabble Wind Power LLC
1408 State Route 170, Little Falls, NY 13365Plant Summary Information
Hardscrabble Wind Power LLC is ranked #20 out of 34 wind farms in New York in terms of total annual net electricity generation.
Hardscrabble Wind Power LLC generated 49.9 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Hardscrabble Wind Power LLC |
---|---|
Utility Name | Avangrid Power LLC |
Location | Herkimer County, NY |
Initial Operation Date | January 2011 |
Last Update | Dec 2024 |
Annual Generation | 163.8 GWh |
Annual Consumption | 616.9 k MMBtu |
Ranked #2,646 out of 12,299 Power Plants Nationwide | |
Ranked #793 out of 1,353 Wind Power Plants Nationwide | |
Ranked #68 out of 912 New York Power Plants | |
Ranked #20 out of 34 New York Wind Power Plants | |
Fuel Types | Wind |
Previous Operators |
Iberdrola Renewables Inc (2013 to 2014) Avangrid Renewables Inc (2015 to 2015) Avangrid Renewables LLC (2016 to 2023) Avangrid Power LLC (2024 to 2024) |
Map of Hardscrabble Wind Power LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hardscrabble Wind Power LLC.
Monthly Net Generation for Hardscrabble Wind Power LLC
Hardscrabble Wind Power LLC Details
Summary Information | |
---|---|
Plant Name | Hardscrabble Wind Power LLC (57287) |
Plant Address | 1408 State Route 170, Little Falls, NY 13365 |
Utility | Avangrid Power LLC (15399) |
Latitude, Longitude | 43.11222, -74.87889 |
Generation Dates on File | Jan 2011 to Dec 2024 |
Initial Operation Date | January 2011 |
Annual Generation | 163.8 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | EG10-63-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Niagara Mohawk Power Corp. (13573) NY |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator 1 Details Operating January 2011
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 74 MW |
Summer Capacity | 74 MW |
Winter Capacity | 74 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | January 2011 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 37 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 37 |
---|---|
Predominant Turbine Manufacturer | Gamesa |
Predominant Turbine Model Number | G90-2.0 |
Design Wind Speed | 16 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 328 |
Hardscrabble Wind Power LLC Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#783 | Spearville 3 LLC | Spearville, KS | 170.4 GWh |
#784 | Whitetail | Oilton, TX | 170.4 GWh |
#785 | Centennial Wind Farm | Fort Supply, OK | 170.2 GWh |
#786 | Kit Carson Windpower | Burlington, CO | 168.5 GWh |
#787 | Woodward Mountain II | Girvin, TX | 168.0 GWh |
#788 | Woodward Mountain I | Girvin, TX | 168.0 GWh |
#789 | Prairie Hill Wind Project | Mart, TX | 167.8 GWh |
#790 | Horse Butte Wind I, LLC | Iona, ID | 167.4 GWh |
#791 | Bison I Wind Energy Center | New Salem, ND | 165.9 GWh |
#792 | Scurry County Wind II | Snyder, TX | 164.9 GWh |
#794 | Eurus Combine Hills Turbine Ranch 2 | Milton Freewater, OR | 163.6 GWh |
#795 | Wolverine Creek | Idaho Falls, ID | 163.5 GWh |
#796 | Blue Canyon Windpower VI LLC | Carnegie, OK | 163.5 GWh |
#797 | Sweetwater Wind 5 | Roscoe, TX | 163.2 GWh |
#798 | TPW Petersburg | Petersburg, NE | 162.5 GWh |
#799 | Red Mesa Wind LLC | Seboyeta, NM | 162.1 GWh |
#800 | Busch Ranch II Wind Farm | Walsenburg, CO | 161.8 GWh |
#801 | Altona | Altona, NY | 157.9 GWh |
#802 | Michigan Wind 1 | Ubly, MI | 157.5 GWh |
#803 | Majestic II Wind | Panhandle, TX | 157.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hardscrabble Wind Power LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bantam Solar | Saint Johnsville, NY | 9.5 GWh | 8 mi |
Barneveld Solar | Barneveld, NY | 1.4 GWh | 17.8 mi |
Beardslee | Little Falls, NY | 51.1 GWh | 9.5 mi |
Burrstone Energy Center | New Hartford, NY | 17.1 GWh | 20.2 mi |
Dolgeville Hydro | Dolgeville, NY | 11.6 GWh | 5.8 mi |
Drinkwater Solar | Saint Johnsville, NY | 3.6 GWh | 11.9 mi |
Ephratah | Saint Johnsville, NY | 4.9 GWh | 18.7 mi |
GSPP 7024 Fox Rd, LLC | Marcy, NY | 7.6 GWh | 20.1 mi |
Inghams | Little Falls, NY | 27.0 GWh | 6.8 mi |
Jarvis (Hinckley) | Hinckley, NY | 22.8 GWh | 18 mi |
Kearsarge Oppenheim CSG | St. Johnsville, NY | 2.2 GWh | 8 mi |
Little Falls Hydro | Little Falls, NY | 51.0 GWh | 5.2 mi |
Little Falls Solar | Little Falls, NY | 3.5 GWh | 3.7 mi |
Little Falls Solar 1 | Little Falls, NY | 3.5 GWh | 4.2 mi |
Newport Hydro | Newport, NY | 6.3 GWh | 8.6 mi |
Ny Frankfort Bleecker St - Frankfort -NG | Frankfort, NY | 2.3 GWh | 15.1 mi |
Prospect | Prospect, NY | 69.1 GWh | 18.4 mi |
Source Power NY II - Whaling | Utica, NY | 824.0 MWh | 16.4 mi |
Trenton Falls | Barneveld, NY | 140.6 GWh | 18 mi |
Warrior Solar Partners | Frankfort, NY | 1.1 GWh | 12.8 mi |