Gowanus Gas Turbines Generating
420 2nd Avenue, Brooklyn, NY 11232Plant Summary Information
Gowanus Gas Turbines Generating is ranked #57 out of 114 natural gas power plants in New York in terms of total annual net electricity generation.
Gowanus Gas Turbines Generating is comprised of 32 generators and generated 13.3 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Gowanus Gas Turbines Generating |
|---|---|
| Utility Name | Astoria Generating Company, L.P. |
| Location | Kings County, NY |
| Initial Operation Date | June 1971 |
| Last Update | Dec 2025 |
| Annual Generation | 61.0 GWh |
| Annual Consumption | 1.1 M MMBtu |
| Ranked #3,992 out of 13,094 Power Plants Nationwide | |
| Ranked #1,081 out of 2,208 Natural Gas Power Plants Nationwide | |
| Ranked #116 out of 1,045 New York Power Plants | |
| Ranked #57 out of 114 New York Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 86.8% Distillate Fuel Oil : 13.2% |
| Previous Operator |
U S Power Generating Company LLC (2013 to 2024) Astoria Generating Company, L.P. (2025 to 2025) |
Map of Gowanus Gas Turbines Generating
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Gowanus Gas Turbines Generating.
Monthly Net Generation for Gowanus Gas Turbines Generating
Monthly Plant Fuel Consumption for Gowanus Gas Turbines Generating
Gowanus Gas Turbines Generating Details
| Summary Information | |
|---|---|
| Plant Name | Gowanus Gas Turbines Generating (2494) |
| Plant Address | 420 2nd Avenue, Brooklyn, NY 11232 |
| Utility | Astoria Generating Company, L.P. (54863) |
| Latitude, Longitude | 40.6635, -74.0051 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | June 1971 |
| Annual Generation | 61.0 GWh |
| Fuel Types | Natural Gas : 86.8% Distillate Fuel Oil : 13.2% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 06-49-000 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | New York Independent System Operator (NYIS) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Municipality |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Consolidated Edison Co-NY Inc (4226) NY |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | KEYSPAN ENERGY DBA NATIOAL GRID NY |
| Natural Gas Storage | No |
Generator GT11 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19.1 MW |
| Winter Capacity | 24.9 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT12 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.1 MW |
| Winter Capacity | 22.3 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT13 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.2 MW |
| Winter Capacity | 22.5 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT14 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.1 MW |
| Winter Capacity | 22.3 MW |
| Minimum Load | 15.6 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT15 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 16.5 MW |
| Winter Capacity | 21.6 MW |
| Minimum Load | 15.9 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT16 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 18 MW |
| Winter Capacity | 23.5 MW |
| Minimum Load | 15.6 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT17 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.6 MW |
| Winter Capacity | 23 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT18 Details Out of Service June 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.9 MW |
| Winter Capacity | 23.4 MW |
| Minimum Load | 14.6 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT21 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.9 MW |
| Winter Capacity | 23.4 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 17 MW |
| Net Winter Capacity With Natural Gas | 21.6 MW |
| Net Summer Capacity With Oil | 17 MW |
| Net Winter Capacity With Oil | 21.6 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT22 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 18.8 MW |
| Winter Capacity | 24.6 MW |
| Minimum Load | 15.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 15.2 MW |
| Net Winter Capacity With Natural Gas | 21.5 MW |
| Net Summer Capacity With Oil | 15.2 MW |
| Net Winter Capacity With Oil | 21.5 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT23 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 20.6 MW |
| Winter Capacity | 26.9 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 19.1 MW |
| Net Winter Capacity With Natural Gas | 22.6 MW |
| Net Summer Capacity With Oil | 19.1 MW |
| Net Winter Capacity With Oil | 22.6 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT24 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19.3 MW |
| Winter Capacity | 25.2 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 17.3 MW |
| Net Winter Capacity With Natural Gas | 23.1 MW |
| Net Summer Capacity With Oil | 17.3 MW |
| Net Winter Capacity With Oil | 23.1 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT25 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 18.6 MW |
| Winter Capacity | 24.3 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 18 MW |
| Net Winter Capacity With Natural Gas | 23.4 MW |
| Net Summer Capacity With Oil | 18 MW |
| Net Winter Capacity With Oil | 23.4 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT26 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 20.3 MW |
| Winter Capacity | 26.5 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 19.5 MW |
| Net Winter Capacity With Natural Gas | 24.9 MW |
| Net Summer Capacity With Oil | 19.5 MW |
| Net Winter Capacity With Oil | 24.9 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT27 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19.6 MW |
| Winter Capacity | 25.6 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | June 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 19.1 MW |
| Net Winter Capacity With Natural Gas | 24.7 MW |
| Net Summer Capacity With Oil | 19.1 MW |
| Net Winter Capacity With Oil | 24.7 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT28 Details Operating June 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.7 MW |
| Winter Capacity | 23.1 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 17.7 MW |
| Net Winter Capacity With Natural Gas | 22.9 MW |
| Net Summer Capacity With Oil | 17.7 MW |
| Net Winter Capacity With Oil | 22.9 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT31 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.7 MW |
| Winter Capacity | 23.1 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 16.9 MW |
| Net Winter Capacity With Natural Gas | 21.9 MW |
| Net Summer Capacity With Oil | 16.9 MW |
| Net Winter Capacity With Oil | 21.9 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT32 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.7 MW |
| Winter Capacity | 23.1 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 17.1 MW |
| Net Winter Capacity With Natural Gas | 22.6 MW |
| Net Summer Capacity With Oil | 17.1 MW |
| Net Winter Capacity With Oil | 22.6 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT33 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19.8 MW |
| Winter Capacity | 25.9 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 18 MW |
| Net Winter Capacity With Natural Gas | 23.8 MW |
| Net Summer Capacity With Oil | 18 MW |
| Net Winter Capacity With Oil | 23.8 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT34 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.9 MW |
| Winter Capacity | 23.4 MW |
| Minimum Load | 15.9 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 16.2 MW |
| Net Winter Capacity With Natural Gas | 21.4 MW |
| Net Summer Capacity With Oil | 16.2 MW |
| Net Winter Capacity With Oil | 21.4 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT35 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19 MW |
| Winter Capacity | 24.8 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 17.3 MW |
| Net Winter Capacity With Natural Gas | 22.8 MW |
| Net Summer Capacity With Oil | 17.3 MW |
| Net Winter Capacity With Oil | 22.8 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT36 Details Out of Service July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.6 MW |
| Winter Capacity | 23 MW |
| Minimum Load | 15.2 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 15.5 MW |
| Net Winter Capacity With Natural Gas | 21 MW |
| Net Summer Capacity With Oil | 15.5 MW |
| Net Winter Capacity With Oil | 21 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT37 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 18.1 MW |
| Winter Capacity | 23.6 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 18.1 MW |
| Net Winter Capacity With Natural Gas | 23.9 MW |
| Net Summer Capacity With Oil | 18.1 MW |
| Net Winter Capacity With Oil | 23.9 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT38 Details Operating July 1971
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19 MW |
| Winter Capacity | 24.8 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1971 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Cofire Energy Source | NG / DFO |
|---|---|
| Switch When Operating | Yes |
| Net Summer Capacity With Natural Gas | 16.9 MW |
| Net Winter Capacity With Natural Gas | 23.9 MW |
| Net Summer Capacity With Oil | 16.9 MW |
| Net Winter Capacity With Oil | 23.9 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Air Permit Limits | Yes |
Generator GT41 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 16.8 MW |
| Winter Capacity | 21.9 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT42 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.3 MW |
| Winter Capacity | 22.6 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT43 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.6 MW |
| Winter Capacity | 23 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT44 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.1 MW |
| Winter Capacity | 22.3 MW |
| Minimum Load | 15.8 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT45 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 17.1 MW |
| Winter Capacity | 22.3 MW |
| Minimum Load | 15.7 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT46 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 18.6 MW |
| Winter Capacity | 24.3 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT47 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 16.6 MW |
| Winter Capacity | 21.7 MW |
| Minimum Load | 14 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator GT48 Details Out of Service July 1971
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 20 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 19 MW |
| Winter Capacity | 24.8 MW |
| Minimum Load | 16 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
|---|---|
| First Operation Date | July 1971 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Gowanus Gas Turbines Generating Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1071 | Waterbury Generation | Waterbury, CT | 55.0 GWh |
| #1072 | International Paper Georgetown Mill | Georgetown, SC | 484.7 GWh |
| #1073 | Cogeneration 1 | Tucson, AZ | 54.0 GWh |
| #1074 | New York Presbyterian Hospital- 68th Street | New York, NY | 54.1 GWh |
| #1075 | Tilton | Tilton, IL | 53.8 GWh |
| #1076 | AOC, Capitol Power Plant | Washington, DC | 54.4 GWh |
| #1077 | Osawatomie | Miami, KS | 53.6 GWh |
| #1078 | Warrick | Newburgh, IN | 3.0 TWh |
| #1079 | General Chemical | Green River, WY | 217.3 GWh |
| #1080 | Cymric 36W Cogen | McKittrick, CA | 53.4 GWh |
| #1082 | Burlington Generating Station | Burlington, NJ | 53.0 GWh |
| #1083 | W&T Onshore Treating Facility (OTF) | Theodore, AL | 52.3 GWh |
| #1084 | Franklin Heating Station | Rochester, MN | 63.1 GWh |
| #1085 | Imperial Savannah LP | Port Wentworth, GA | 52.8 GWh |
| #1086 | Silas Ray | Brownsville, TX | 51.9 GWh |
| #1087 | TNSG North Plant | Deadhorse, AK | 51.3 GWh |
| #1088 | Chamon | Houston, TX | 51.3 GWh |
| #1089 | Clearwater Paper APP CB | Arkansas City, AR | 123.3 GWh |
| #1090 | Marshall Energy Facility | Calvert City, KY | 51.2 GWh |
| #1091 | Ray Olinger | Navada, TX | 51.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Gowanus Gas Turbines Generating.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bayonne Energy Center | Bayonne, NJ | 1.1 TWh | 4.6 mi |
| Brooklyn Hospital Center | Brooklyn, NY | 5.0 MWh | 2.3 mi |
| Brooklyn Navy Yard Cogeneration | Brooklyn, NY | 2.1 TWh | 2.9 mi |
| East River | New York, NY | 2.8 TWh | 4.7 mi |
| Jersey City DWP | Jersey City, NJ | 1.2 GWh | 4.7 mi |
| Joseph J Seymour Power Project | Brooklyn, NY | 99.0 GWh | 0.3 mi |
| Kingsbrook Jewish Medical Center | Brooklyn, NY | 24.0 MWh | 3.8 mi |
| Maimonides Medical Center | Brooklyn, NY | 15.0 MWh | 1.7 mi |
| Narrows Gas Turbines Generating | Brooklyn, NY | 144.9 GWh | 1.3 mi |
| NewYork-Presbyterian Brooklyn Methodist | Brooklyn, NY | 29.0 MWh | 1.4 mi |
| NHH003 Clarkson Fuel Cell | Brooklyn, NY | 8.9 GWh | 3.3 mi |
| NHH004 Winthrop Fuel Cell | Brooklyn, NY | 7.9 GWh | 3.1 mi |
| North 1st | Brooklyn, NY | 92.8 GWh | 4.2 mi |
| NYP-Lower Manhattan Hospital | New York, NY | 20.0 MWh | 3.2 mi |
| NYU Langone Hospital- Brooklyn | New York City, NY | 486.0 MWh | 1.4 mi |
| Pouch | Staten Island, NY | 61.5 GWh | 4.6 mi |
| SDM000 Clarkson Fuel Cell | Brooklyn, NY | 14.2 GWh | 3.2 mi |
| The Bank of New York | New York, NY | 47.0 MWh | 3.8 mi |
| WEA Texas Bayonne | Bayonne, NJ | 2.0 GWh | 4.6 mi |
| Woodhull Hospital | Brooklyn, NY | 159.0 MWh | 4.4 mi |