Empire Energy Center
2537 Fir Road, Sarcoxie, MO 64862Plant Summary Information
Empire Energy Center is ranked #42 out of 127 power plants in Missouri in terms of total annual net electricity generation.
Empire Energy Center is comprised of 4 generators and generated 30.4 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Empire Energy Center |
|---|---|
| Utility Name | Empire District Electric Co |
| Location | Jasper County, MO |
| Initial Operation Date | March 1978 |
| Last Update | Dec 2025 |
| Annual Generation | 143.8 GWh |
| Annual Consumption | 2.0 M MMBtu |
| Ranked #3,107 out of 13,301 Power Plants Nationwide | |
| Ranked #847 out of 2,218 Natural Gas Power Plants Nationwide | |
| Ranked #42 out of 127 Missouri Power Plants | |
| Ranked #10 out of 35 Missouri Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 93.5% Jet Fuel : 6.5% |
Map of Empire Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Empire Energy Center.
Monthly Net Generation for Empire Energy Center
Monthly Plant Fuel Consumption for Empire Energy Center
Empire Energy Center Details
| Summary Information | |
|---|---|
| Plant Name | Empire Energy Center (6223) |
| Plant Address | 2537 Fir Road, Sarcoxie, MO 64862 |
| Utility | Empire District Electric Co (5860) |
| Latitude, Longitude | 37.1385, -94.1041 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | March 1978 |
| Annual Generation | 143.8 GWh |
| Fuel Types | Natural Gas : 93.5% Jet Fuel : 6.5% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | MRO |
| Balancing Authority | Southwest Power Pool (SWPP) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Empire District Electric Co (5860) MO |
| Grid Voltage | 161.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | SOUTHERN STAR CENTRAL GAS PIPELINE |
| Natural Gas Storage | No |
Generator 1 Details Operating March 1978
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | EDELAR3821UN1_RA |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | EDELAR3821UN1_RA |
| Nameplate Capacity | 129 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 78 MW |
| Winter Capacity | 90 MW |
| Minimum Load | 30 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | March 1978 |
|---|---|
| Planned Retirement | December 2035 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Jet Fuel |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Switch When Operating | Yes |
|---|---|
| Net Summer Capacity With Natural Gas | 78 MW |
| Net Winter Capacity With Natural Gas | 90 MW |
| Net Summer Capacity With Oil | 80 MW |
| Net Winter Capacity With Oil | 95 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Storage Limits | Yes |
Generator 2 Details Operating June 1981
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | EDELAR3821UN2_RA |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | EDELAR3821UN2_RA |
| Nameplate Capacity | 129 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 77 MW |
| Winter Capacity | 95 MW |
| Minimum Load | 30 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1981 |
|---|---|
| Planned Retirement | December 2035 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Jet Fuel |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Switch When Operating | Yes |
|---|---|
| Net Summer Capacity With Natural Gas | 77 MW |
| Net Winter Capacity With Natural Gas | 92 MW |
| Net Summer Capacity With Oil | 82 MW |
| Net Winter Capacity With Oil | 83 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Storage Limits | Yes |
Generator 3 Details Operating April 2003
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | EDELAR3821UN3_RA |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | EDELAR3821UN3_RA |
| Nameplate Capacity | 60.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 48 MW |
| Winter Capacity | 58 MW |
| Minimum Load | 25 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Jet Fuel |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Switch When Operating | Yes |
|---|---|
| Net Summer Capacity With Natural Gas | 48 MW |
| Net Winter Capacity With Natural Gas | 58 MW |
| Net Summer Capacity With Oil | 41 MW |
| Net Winter Capacity With Oil | 58 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Storage Limits | Yes |
Generator 4 Details Operating April 2003
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | EDELAR3821UN4_RA |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | EDELAR3821UN4_RA |
| Nameplate Capacity | 60.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 41 MW |
| Winter Capacity | 58 MW |
| Minimum Load | 25 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Jet Fuel |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Switch When Operating | Yes |
|---|---|
| Net Summer Capacity With Natural Gas | 41 MW |
| Net Winter Capacity With Natural Gas | 58 MW |
| Net Summer Capacity With Oil | 41 MW |
| Net Winter Capacity With Oil | 58 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Storage Limits | Yes |
Empire Energy Center Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #837 | Cleveland Works | Cleveland, OH | 307.7 GWh |
| #838 | Sycamore Cogeneration | Bakersfield, CA | 140.8 GWh |
| #839 | Escanaba Mill | Escanaba, MI | 457.3 GWh |
| #840 | Georgia-Pacific Palatka Operations | Palatka, FL | 331.4 GWh |
| #841 | Calcasieu | Sulphur, LA | 138.8 GWh |
| #842 | Canal | Sandwich, MA | 447.0 GWh |
| #843 | Narrows Gas Turbines Generating | Brooklyn, NY | 144.9 GWh |
| #844 | Lederle Laboratories | Pearl River, NY | 139.0 GWh |
| #845 | Berry Cogen Tanne Hills 18 | Maricopa, CA | 137.6 GWh |
| #846 | Kalamazoo River Generating Station | Comstock, MI | 136.3 GWh |
| #848 | Harbor | Wilmington, CA | 134.1 GWh |
| #849 | LSU Cogen | Baton Rouge, LA | 133.7 GWh |
| #850 | Rand Whitney CHP Plant | Montville, CT | 132.0 GWh |
| #851 | Purdue University | West Lafayette, IN | 139.1 GWh |
| #852 | Algonquin Windsor Locks | Windsor Locks, CT | 143.1 GWh |
| #853 | Glenarm | Pasadena, CA | 129.8 GWh |
| #854 | Glenwood Landing | Glenwood Landing, NY | 137.0 GWh |
| #855 | Inver Hills | Inver Grove Heights, MN | 129.5 GWh |
| #856 | MPC Generating | Monroe, GA | 127.5 GWh |
| #857 | PE Berkeley | Berkeley, CA | 126.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Empire Energy Center.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Beaver Dam (AR) | Eureka Springs, AR | 184.1 GWh | 51.5 mi |
| Berryville School District Solar | Berryville, AR | 1.8 GWh | 60.1 mi |
| El Dorado Springs Solar Farm | El Dorado Springs, MO | 3.8 GWh | 50.1 mi |
| Girard | Girard, KS | 41.0 MWh | 47.8 mi |
| Greenbush-Heartland | Girard, KS | 1.9 GWh | 54.8 mi |
| James River Power Station | Springfield, MO | 79.9 GWh | 46.4 mi |
| John Twitty Energy Center | Springfield, MO | 1.9 TWh | 39.4 mi |
| Kings Point Wind Energy Center | Golden City, MO | 559.6 GWh | 9.5 mi |
| McCartney | Strafford, MO | 80.6 GWh | 51.9 mi |
| Nevada | Nevada, MO | 15.0 MWh | 50.9 mi |
| Nixa Solar, LLC | Nixa, MO | 14.1 GWh | 42.7 mi |
| North Fork Ridge Wind Energy Center | Mindenmines, MO | 561.7 GWh | 28.3 mi |
| Oak Grove Power Producers | Arcadia, KS | 10.9 GWh | 45 mi |
| Prosperity Solar Farm CSG | Joplin, MO | 3.7 GWh | 18.2 mi |
| Riverton | Riverton, KS | 1.3 TWh | 33.1 mi |
| Springfield Solar 1 LLC | Strafford, MO | 6.5 GWh | 52.1 mi |
| State Line Combined Cycle | Joplin, MO | 2.3 TWh | 28.5 mi |
| Stockton Hydro | Stockton, MO | 54.7 GWh | 42.5 mi |
| Table Rock | Branson, MO | 528.4 GWh | 57.7 mi |
| XNA (NW AR Natnl Airport) | Bentonville, AR | 1.3 GWh | 61.5 mi |