Elder Branch
28800 State Road 62, Parrish, FL 34219Plant Summary Information
Elder Branch is ranked #51 out of 207 solar farms in Florida in terms of total annual net electricity generation.
Elder Branch generated 39.0 GWh during the 3-month period between July 2025 to October 2025.
| Plant Name | Elder Branch |
|---|---|
| Utility Name | Florida Power & Light Co |
| Location | Manatee County, FL |
| Initial Operation Date | January 2022 |
| Last Update | Oct 2025 |
| Annual Generation | 161.7 GWh |
| Annual Consumption | 581.8 k MMBtu |
| Ranked #2,777 out of 12,553 Power Plants Nationwide | |
| Ranked #535 out of 6,410 Solar Power Plants Nationwide | |
| Ranked #119 out of 313 Florida Power Plants | |
| Ranked #51 out of 207 Florida Solar Power Plants | |
| Fuel Types | Solar |
Map of Elder Branch
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Elder Branch.
Monthly Net Generation for Elder Branch
Elder Branch Details
| Summary Information | |
|---|---|
| Plant Name | Elder Branch (65041) |
| Plant Address | 28800 State Road 62, Parrish, FL 34219 |
| Utility | Florida Power & Light Co (6452) |
| Latitude, Longitude | 27.5966, -82.25272 |
| Generation Dates on File | Jan 2022 to Oct 2025 |
| Initial Operation Date | January 2022 |
| Annual Generation | 161.7 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | Florida Power & Light Company (FPL) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Florida Power & Light Co (6452) FL |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 1 Details Operating January 2022
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 74.5 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 74.5 MW |
| Winter Capacity | 74.5 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | January 2022 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| Tilt Angle | 52 |
| DC Net Capacity | 98.3 MW |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Elder Branch Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #525 | Hawthorne Creek | TBD, FL | 163.3 GWh |
| #526 | OETN1 | Obion, TN | 162.8 GWh |
| #527 | Big Juniper Solar | TBD, FL | 162.7 GWh |
| #528 | Ellis Solar LLC | Midlothian, TX | 162.6 GWh |
| #529 | High Springs Solar Power Plant | High Springs, FL | 162.6 GWh |
| #530 | Water Strider Solar | Nathalie, VA | 162.6 GWh |
| #531 | Assembly Solar III | Lennon, MI | 162.6 GWh |
| #532 | SR Cedar Springs, LLC | Blakely, GA | 162.3 GWh |
| #533 | Terrill Creek | Green Cove Springs, FL | 162.0 GWh |
| #534 | Cabin Creek Solar, LLC | Biscoe, NC | 161.9 GWh |
| #536 | Green Pasture | TBD, FL | 161.4 GWh |
| #537 | Lily Solar | Martin, SC | 160.7 GWh |
| #538 | Wilkinson Solar LLC | Pantego, NC | 160.7 GWh |
| #539 | Bay Trail Solar Power Plant | Crystal River, FL | 160.7 GWh |
| #540 | Moonshot | Picayune, MS | 160.4 GWh |
| #541 | Winfield Solar | Winfield, MO | 160.4 GWh |
| #542 | Fawn | TBD, FL | 160.1 GWh |
| #543 | Echo River Solar | Live Oak, FL | 158.1 GWh |
| #544 | Cove Mountain Solar | Beryl, UT | 159.5 GWh |
| #545 | G.S.E. One LLC | Bonham, TX | 159.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Elder Branch.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alafia Solar | Mulberry, FL | 114.5 GWh | 16.4 mi |
| Balm Solar | Wimauma, FL | 139.6 GWh | 11.5 mi |
| Big Bend Agrivoltaics | Apollo Beach, FL | 749.0 MWh | 15.7 mi |
| Big Bend Floating Solar I | Gibsonton, FL | 1.3 GWh | 15.9 mi |
| Big Bend II Solar | Apollo Beach, FL | 82.7 GWh | 15.3 mi |
| Bullfrog Creek Solar | Wimauma, FL | 142.5 GWh | 5.1 mi |
| Duette Solar Power Plant | Parrish, FL | 168.7 GWh | 11.7 mi |
| Grange Hall Solar | Wimauma, FL | 117.3 GWh | 8 mi |
| Lake Hancock Solar | Bartow, FL | 92.6 GWh | 15.8 mi |
| Lithia Solar | Lithia, FL | 141.2 GWh | 12.1 mi |
| Little Manatee River Solar | Ruskin, FL | 85.4 GWh | 11.7 mi |
| Long Creek | TBD, FL | 153.9 GWh | 15.7 mi |
| Manatee | Parrish, FL | 6.6 TWh | 5.7 mi |
| Manatee Solar Energy Center | Parrish, FL | 102.2 GWh | 6.3 mi |
| Riverside Solar | Ruskin, FL | 104.6 GWh | 14.7 mi |
| Sambucus | Myakka City, FL | 166.4 GWh | 15.5 mi |
| Southfork Solar | Parrish, FL | 134.8 GWh | 4.1 mi |
| Three Creeks | Parrish, FL | 172.5 GWh | 1.3 mi |
| Willow Solar Energy Center | Myakka City, FL | 154.3 GWh | 14.7 mi |
| Wimauma Solar and Battery Storage | Wimauma, FL | 96.2 GWh | 9.3 mi |