Clifton Dam 3 Power Station
Highway 29, Converse, SC 29329Plant Summary Information
Clifton Dam 3 Power Station is ranked #24 out of 27 hydroelectric power plants in South Carolina in terms of total annual net electricity generation.
Clifton Dam 3 Power Station is comprised of 2 generators and generated 905.0 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Clifton Dam 3 Power Station |
|---|---|
| Utility Name | Converse Energy Inc |
| Location | Spartanburg County, SC |
| Initial Operation Date | August 1985 |
| Last Update | Dec 2024 |
| Annual Generation | 3.7 GWh |
| Annual Consumption | 13.5 k MMBtu |
| Ranked #9,188 out of 13,081 Power Plants Nationwide | |
| Ranked #1,154 out of 1,311 Water Power Plants Nationwide | |
| Ranked #154 out of 202 South Carolina Power Plants | |
| Ranked #24 out of 27 South Carolina Water Power Plants | |
| Fuel Types | Water |
Map of Clifton Dam 3 Power Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Clifton Dam 3 Power Station.
Monthly Net Generation for Clifton Dam 3 Power Station
Monthly Plant Fuel Consumption for Clifton Dam 3 Power Station
Clifton Dam 3 Power Station Details
| Summary Information | |
|---|---|
| Plant Name | Clifton Dam 3 Power Station (52049) |
| Plant Address | Highway 29, Converse, SC 29329 |
| Utility | Converse Energy Inc (4277) |
| Latitude, Longitude | 34.9953, -81.8344 |
| Generation Dates on File | Jan 2005 to Dec 2024 |
| Initial Operation Date | August 1985 |
| Annual Generation | 3.7 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | 81-85-000 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | SERC |
| Balancing Authority | Duke Energy Carolinas (DUK) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Pacolet River |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Duke Energy Carolinas, LLC (5416) SC |
| Grid Voltage | 13.00 kV |
| Energy Storage | No |
Generator 2V Details Operating August 1985
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.5 MW |
| Winter Capacity | 0.5 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | August 1985 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Water |
| Time From Cold Shutdown To Full Load | 1H |
Generator 1H Details Operating April 1987
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.7 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.7 MW |
| Winter Capacity | 0.7 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | April 1987 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Water |
| Time From Cold Shutdown To Full Load | 1H |
Clifton Dam 3 Power Station Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1144 | Scott Flat | Nevada City, CA | 3.8 GWh |
| #1145 | Messalonskee 3 | Oakland, ME | 3.8 GWh |
| #1146 | Newfound Hydroelectric | Bristol, NH | 3.8 GWh |
| #1147 | Snake Creek | Midway, UT | 3.8 GWh |
| #1148 | Fargo Drop | Wilder, ID | 3.8 GWh |
| #1149 | Lower No 2 | Idaho Falls, ID | 3.8 GWh |
| #1150 | King Mill | Augusta, GA | 3.7 GWh |
| #1151 | Combie South | Auburn, CA | 3.7 GWh |
| #1152 | Dunlap TP 1 | New Brannfels, TX | 3.7 GWh |
| #1153 | Blind Canyon Hydro | Wendell, ID | 3.7 GWh |
| #1155 | Merrill | Merrill, WI | 3.7 GWh |
| #1156 | Volta 2 | Manton, CA | 3.6 GWh |
| #1157 | Hickman | Hickman, CA | 3.6 GWh |
| #1158 | Stevens Mills Dam | Franklin, NH | 3.6 GWh |
| #1159 | Hoot Lake | Fergus Falls, MN | 3.6 GWh |
| #1160 | Haw River Hydro | Saxapahaw, NC | 3.5 GWh |
| #1161 | Marsh Valley Development | McCammon, ID | 3.5 GWh |
| #1162 | Messalonskee 5 | Waterville, ME | 3.5 GWh |
| #1163 | Last Chance | Grace, ID | 3.5 GWh |
| #1164 | Indian Orchard | Indian Orchard, MA | 3.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Clifton Dam 3 Power Station.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AGA TAG Solar III LLC | Spartanburg, SC | 1.6 GWh | 11.8 mi |
| Atood II | Cowpens, SC | 3.5 GWh | 2.8 mi |
| ATOOD Solar III LLC | Spartanburg, SC | 2.2 GWh | 11.8 mi |
| Ballenger Road Solar A | Inman, SC | 4.0 GWh | 16.1 mi |
| Beetle Solar | Mooresboro, NC | 5.7 GWh | 15.9 mi |
| Broad River Energy Center | Gaffney, SC | 1.2 TWh | 15.8 mi |
| Broad River Solar, LLC | Mooresboro, NC | 107.3 GWh | 14.1 mi |
| Bryant Road Solar | Spartanburg, SC | 1.7 GWh | 5.5 mi |
| Charlotte Solar | Forest City, NC | 8.0 GWh | 18.4 mi |
| Cherokee County Cogen | Gaffney, SC | 644.3 GWh | 13.6 mi |
| Gaston Shoals | Blacksburg, SC | 5.0 GWh | 16.6 mi |
| James E. Rogers Energy Complex | Cliffside, NC | 5.6 TWh | 16.1 mi |
| Limelight Solar I, LLC | Spartanburg, SC | 3.2 GWh | 9.3 mi |
| Limelight Solar II LLC | Spartanburg, SC | 1.4 GWh | 2.5 mi |
| Limelight Solar III, LLC | Spartanburg, SC | 1.8 GWh | 8.7 mi |
| Mohea Solar Energy Center, LLC | Gaffney, SC | 8.5 GWh | 13.5 mi |
| Rutherford Farm | Forest City, NC | 136.2 GWh | 18.1 mi |
| Spartanburg Water System | Chesnee, SC | 620.0 MWh | 10.9 mi |
| Upper Pacolet Hydro | Pacolet, SC | 4.8 GWh | 7.2 mi |
| Wellford Renewable Energy Plant | Spartanburg, SC | 59.0 MWh | 16.8 mi |