Cellu Tissue
#2 Forbes Street, East Hartford, CT 6108Plant Summary Information
Cellu Tissue is ranked #40 out of 51 natural gas power plants in Connecticut in terms of total annual net electricity generation.
Cellu Tissue is comprised of 1 generator and generated 1.9 GWh during the 3-month period between May 2026 to August 2026.
| Plant Name | Cellu Tissue |
|---|---|
| Utility Name | Dunn Paper East Hartford, LLC |
| Location | Capitol Planning Region, CT |
| Initial Operation Date | May 2009 |
| Last Update | Aug 2026 |
| Annual Generation | 10.8 GWh |
| Annual Consumption | 129.7 k MMBtu |
| Ranked #6,175 out of 13,301 Power Plants Nationwide | |
| Ranked #1,552 out of 2,218 Natural Gas Power Plants Nationwide | |
| Ranked #65 out of 171 Connecticut Power Plants | |
| Ranked #40 out of 51 Connecticut Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
| Previous Operator |
Cellu Tissue LLC (2013 to 2015) Dunn Paper East Hartford, LLC (2016 to 2025) |
Map of Cellu Tissue
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cellu Tissue.
Monthly Net Generation for Cellu Tissue
Monthly Plant Fuel Consumption for Cellu Tissue
Cellu Tissue Details
| Summary Information | |
|---|---|
| Plant Name | Cellu Tissue (58116) |
| Plant Address | #2 Forbes Street, East Hartford, CT 6108 |
| Utility | Dunn Paper East Hartford, LLC (60642) |
| Latitude, Longitude | 41.77611, -72.60667 |
| Generation Dates on File | Jan 2012 to Aug 2026 |
| Initial Operation Date | May 2009 |
| Annual Generation | 10.8 GWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | ISO New England Inc. (ISNE) |
| NAICS Code | Paper Manufacturing (322) |
| Sector | Industrial Non-CHP (6) |
| Water Source | Municipality MDC |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Connecticut Light & Power Co (4176) CT |
| Grid Voltage | 13.80 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | CONNECTICUT NAT GAS CORP |
| Natural Gas Storage | No |
Generator GEN1 Details Operating May 2009
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | N/A |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
| Nameplate Capacity | 3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.5 MW |
| Winter Capacity | 2.5 MW |
| Minimum Load | 1.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 2009 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Industrial Non-CHP (6) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Cellu Tissue Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1542 | POET Biorefining - Jewell | Jewell, IA | 11.2 GWh |
| #1543 | Clay Boswell | Cohasset, MN | 5.5 TWh |
| #1544 | Red Hills Generating Facility | Ackerman, MS | 1.9 TWh |
| #1545 | Live Oak Limited | Bakersfield, CA | 11.1 GWh |
| #1546 | Trinity College Fuel Cell | Hartford, CT | 11.1 GWh |
| #1547 | Southside Water Reclamation Plant | Albuquerque, NM | 23.2 GWh |
| #1548 | POET Biorefining - Hudson | Hudson, SD | 10.9 GWh |
| #1549 | Kaiser Deer Valley Rd. Fuel Cell | Antioch, CA | 10.9 GWh |
| #1550 | Cutrale Citrus Juices USA I | Leesburg, FL | 10.9 GWh |
| #1551 | Covanta Fairfax Energy | Lorton, VA | 653.3 GWh |
| #1553 | Foxwoods CoGen | Mashantucket, CT | 10.8 GWh |
| #1554 | Lewis & Clark | Richland, MT | 10.7 GWh |
| #1555 | Plant No 2 Orange County | Huntington Beach, CA | 46.9 GWh |
| #1556 | SEMASS Resource Recovery | West Wareham, MA | 537.3 GWh |
| #1557 | East 12th Street | Winfield, KS | 10.5 GWh |
| #1558 | Virginia Tech Power Plant | Blacksburg, VA | 10.6 GWh |
| #1559 | Life Technologies - Fremont | Fremont, CA | 10.4 GWh |
| #1560 | Newman (PA) | Philadelphia, PA | 10.3 GWh |
| #1561 | Hank Nikkels Plant 1 | Anchorage, AK | 10.3 GWh |
| #1562 | Tinker | Oklahoma City, OK | 10.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cellu Tissue.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| ALDI DC 2 | South Windsor, CT | 1.3 GWh | 6.4 mi |
| East Windsor | East Windsor, CT | 869.0 MWh | 5.9 mi |
| East Windsor Solar One | East Windsor, CT | 6.5 GWh | 9.1 mi |
| East Windsor Solar Two | East Windsor, CT | 749.0 MWh | 9 mi |
| Glastonbury Solar One | Glastonbury, CT | 821.0 MWh | 3.4 mi |
| Gravel Pit Solar, LLC | East Windsor, CT | 198.1 GWh | 8.3 mi |
| Hartford Hospital Cogeneration | Hartford, CT | 49.1 GWh | 3.5 mi |
| Hartford Landfill Solar EGF | Hartford, CT | 1.2 GWh | 2.5 mi |
| HSCo CHP | Hartford, CT | 27.7 GWh | 3.3 mi |
| Manchester Community College East | Manchester, CT | 1.6 GWh | 2.7 mi |
| Manchester Community College North | Great Path, CT | 885.0 MWh | 2.4 mi |
| Niagara Bottling - Bloomfield | Bloomfield, CT | 4.0 GWh | 8.4 mi |
| Norcap North | East Windsor, CT | 3.3 GWh | 8 mi |
| Norcap South | East Windsor, CT | 3.6 GWh | 8 mi |
| Pepperidge Farm Bloomfield | Bloomfield, CT | 15.5 GWh | 8.6 mi |
| Pratt & Whitney | East Hartford, CT | 93.1 GWh | 2.5 mi |
| South Windsor Fuel Cell | South Windsor, CT | 37.4 GWh | 2.7 mi |
| Ticket Network South Windsor | South Windsor, CT | 1.6 GWh | 6 mi |
| Trinity College Fuel Cell | Hartford, CT | 11.1 GWh | 4.7 mi |
| UDR Glastonbury Fuel Cell | Glastonbury, CT | 15.8 GWh | 5.5 mi |