Carlyle
550 First St, Carlyle, IL 62231Plant Summary Information
Carlyle is ranked #8 out of 38 distillate fuel oil power plants in Illinois in terms of total annual net electricity generation.
Carlyle is comprised of 5 generators and generated 64.0 MWh during the 3-month period between September 2024 to December 2024.
Plant Name | Carlyle |
---|---|
Utility Name | City of Carlyle - (IL) |
Location | Clinton County, IL |
Initial Operation Date | August 1964 |
Last Update | Dec 2024 |
Annual Generation | 231.0 MWh |
Annual Consumption | 2.4 k MMBtu |
Ranked #11,681 out of 12,299 Power Plants Nationwide | |
Ranked #630 out of 1,230 Distillate Fuel Oil Power Plants Nationwide | |
Ranked #320 out of 348 Illinois Power Plants | |
Ranked #8 out of 38 Illinois Distillate Fuel Oil Power Plants | |
Fuel Types | Distillate Fuel Oil |
Map of Carlyle
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Carlyle.
Monthly Net Generation for Carlyle
Carlyle Details
Summary Information | |
---|---|
Plant Name | Carlyle (936) |
Plant Address | 550 First St, Carlyle, IL 62231 |
Utility | City of Carlyle - (IL) (3037) |
Latitude, Longitude | 38.6106, -89.3583 |
Generation Dates on File | Jan 2001 to Dec 2024 |
Initial Operation Date | August 1964 |
Annual Generation | 231.0 MWh |
Fuel Types | Distillate Fuel Oil |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Municipality |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Carlyle - (IL) (3037) IL |
Grid Voltage | 69.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | AMEREN ILLINOIS |
Pipeline Name | Ameren Illinois |
Natural Gas Storage | No |
Generator 7 Details Standby August 1964
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 2 MW |
Winter Capacity | 2 MW |
Minimum Load | 1 MW |
Uprate/Derate Completed | No |
Status | Standby |
Synchronized To Transmission Grid | Yes |
First Operation Date | August 1964 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil / Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | DFO / NG |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 2 MW |
Net Winter Capacity With Natural Gas | 2 MW |
Net Summer Capacity With Oil | 2 MW |
Net Winter Capacity With Oil | 2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 6H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Generator 8 Details Operating October 1998
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2.5 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1998 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Generator 9 Details Operating September 1999
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2.5 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 1999 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Generator 10 Details Operating October 2003
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2.5 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 2.5 MW |
Winter Capacity | 2.5 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 2003 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator 11 Details Operating February 2019
Technology | Petroleum Liquids |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 2.8 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 2.8 MW |
Winter Capacity | 2.8 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2019 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Carlyle Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#620 | ACM - Midtown Thermal | Atlantic City, NJ | 46.7 GWh |
#621 | Citrus City | Mission, TX | 245.0 MWh |
#622 | Napoleon Peaking | Napoleon, OH | 244.0 MWh |
#623 | Bucksport Generation LLC | Bucksport, ME | 13.9 GWh |
#624 | Merrimack | Bow, NH | 316.8 GWh |
#625 | Stonegate | Katy, TX | 234.0 MWh |
#626 | Blooming Prairie | Blooming Prairie, MN | 234.0 MWh |
#627 | E. Porte Ct. | Harlingen, TX | 233.0 MWh |
#628 | Savannah River Site Biomass Cogen | Aiken, SC | 89.9 GWh |
#629 | Coon Rapids II | Coon Rapids, IA | 232.0 MWh |
#631 | Carmi | Carmi, IL | 230.0 MWh |
#632 | Genoa Diesel Generating Station | Genoa, OH | 228.0 MWh |
#633 | Pella Peaking | Pella, IA | 227.0 MWh |
#634 | Thomas Fitzhugh | Ozark, AR | 484.4 GWh |
#635 | Hoffmann LaRoche | Nutley, NJ | 50.0 GWh |
#636 | Forest City Light Plant | Forest City, IA | 225.0 MWh |
#637 | Inver Hills | Inver Grove Heights, MN | 64.2 GWh |
#638 | Winnetka | Winnetka, IL | 2.7 GWh |
#639 | Bakke | Andrews, TX | 221.0 MWh |
#640 | Epic Verona | Verona, WI | 2.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Carlyle.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AES Belleville Solar LLC | Belleville, IL | 12.9 GWh | 36.4 mi |
Baldwin Energy Complex | Baldwin, IL | 6.8 TWh | 38.8 mi |
Baldwin Solar BESS | Baldwin, IL | 43.4 GWh | 38.9 mi |
Breese | Breese, IL | 263.0 MWh | 9 mi |
Clinton Solar 4 LLC CSG | Carlyle, IL | 3.5 GWh | 4.6 mi |
Coffeen Solar BESS | Coffeen, IL | 25.1 GWh | 31.7 mi |
Conagra Foods at St. Elmo | St. Elmo, IL | 3.2 GWh | 39.1 mi |
Edwardsville Solar II | Edwardsville, IL | 4.2 GWh | 37.2 mi |
Freeburg | Freeburg, IL | 122.0 MWh | 32.7 mi |
Highland | Highland, IL | 187.0 MWh | 19.8 mi |
Kinmundy | Patoka, IL | 3.2 GWh | 21.4 mi |
Marion Solar 4b LLC | Sandoval, IL | 970.0 MWh | 13.2 mi |
Marlow Solar, LLC CSG | Bluford, IL | 4.3 GWh | 38.4 mi |
Pinckneyville | Pinckneyville, IL | 79.8 GWh | 34.5 mi |
Prairie State Generating Station | Marissa, IL | 11.3 TWh | 28.3 mi |
Prairie State Solar Project | Swanwick Township, IL | 230.3 GWh | 30.3 mi |
Sandoval | Centralia, IL | 3.6 GWh | 11.4 mi |
St. Clair Solar 3 | Washington Park, IL | 158.0 MWh | 39.4 mi |
Trenton East | Trenton, IL | 1.7 GWh | 18.1 mi |
Trenton West | Trenton, IL | 2.2 GWh | 18.6 mi |