Bronx Zoo
2300 Southern Blvd, New York, NY 10460Plant Summary Information
Bronx Zoo is ranked #70 out of 115 natural gas power plants in New York in terms of total annual net electricity generation.
Bronx Zoo is comprised of 4 generators and generated 5.1 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Bronx Zoo |
|---|---|
| Utility Name | New York Zoological Society |
| Location | Bronx County, NY |
| Initial Operation Date | January 1991 |
| Last Update | Dec 2024 |
| Annual Generation | 21.6 GWh |
| Annual Consumption | 314.4 k MMBtu |
| Ranked #5,160 out of 12,539 Power Plants Nationwide | |
| Ranked #1,354 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #215 out of 944 New York Power Plants | |
| Ranked #70 out of 115 New York Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of Bronx Zoo
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Bronx Zoo.
Monthly Net Generation for Bronx Zoo
Bronx Zoo Details
| Summary Information | |
|---|---|
| Plant Name | Bronx Zoo (50427) |
| Plant Address | 2300 Southern Blvd, New York, NY 10460 |
| Utility | New York Zoological Society (13487) |
| Latitude, Longitude | 40.84411, -73.87689 |
| Generation Dates on File | Jan 2001 to Dec 2024 |
| Initial Operation Date | January 1991 |
| Annual Generation | 21.6 GWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | New York Independent System Operator (NYIS) |
| NAICS Code | Museums, Historical Sites, and Similar Institutions (712) |
| Sector | Commercial CHP (5) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Consolidated Edison Co-NY Inc (4226) NY |
| Grid Voltage | 4.16 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | CONSOLIDATED EDISON NEW YORK INC |
| Natural Gas Storage | No |
Generator GEN1 Details Standby January 1991
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.5 MW |
| Winter Capacity | 0.5 MW |
| Minimum Load | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
| First Operation Date | January 1991 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Commercial CHP (5) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN2 Details Standby January 1991
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.5 MW |
| Winter Capacity | 0.5 MW |
| Minimum Load | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Standby |
| Synchronized To Transmission Grid | Yes |
| First Operation Date | January 1991 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Commercial CHP (5) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN3 Details Operating January 1991
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.1 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.1 MW |
| Winter Capacity | 1.1 MW |
| Minimum Load | 0.8 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1991 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Commercial CHP (5) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN4 Details Operating April 1995
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | April 1995 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Commercial CHP (5) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Bronx Zoo Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1344 | Yankee Street | Centerville, OH | 23.2 GWh |
| #1345 | West Groton CHP | Groton, MA | 22.0 GWh |
| #1346 | Tesoro Mandan Cogeneration Plant | Mandan, ND | 55.6 GWh |
| #1347 | Potter Station 2 | Braintree, MA | 23.3 GWh |
| #1348 | Pleasant Hill | Pleasant Hill, IA | 21.9 GWh |
| #1349 | Riverview Energy Center | Antioch, CA | 21.9 GWh |
| #1350 | Brandon Station | Lubbock, TX | 21.7 GWh |
| #1351 | POET Biorefining - Jewell | Jewell, IA | 21.7 GWh |
| #1352 | Archer Daniels Midland Mankato | Mankato, MN | 21.6 GWh |
| #1353 | Gaylord Rockies CHP | Aurora, CO | 21.6 GWh |
| #1355 | Hibbing | Hibbing, MN | 35.9 GWh |
| #1356 | Waste Management Eco Vista LFGTE | Springdale, AR | 21.5 GWh |
| #1357 | American Gypsum Cogeneration | Gypsum, CO | 21.5 GWh |
| #1358 | Kaweah Delta District Hospital | Visalia, CA | 21.4 GWh |
| #1359 | WestRock Demopolis Mill | Demopolis, AL | 313.0 GWh |
| #1360 | Anheuser Busch - Fairfield | Fairfield, CA | 21.3 GWh |
| #1361 | Robert A Reid | Robards, KY | 21.2 GWh |
| #1362 | Tracy 210 | Tracy, CA | 21.2 GWh |
| #1363 | Live Oak Limited | Bakersfield, CA | 21.1 GWh |
| #1364 | Ben French | Rapid City, SD | 20.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Bronx Zoo.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Albert Einstein College of Medicine | Bronx, NY | 11.0 MWh | 1.6 mi |
| Astoria Energy | New York, NY | 4.1 TWh | 4.4 mi |
| Astoria Energy II | Astoria, NY | 2.6 TWh | 4.5 mi |
| Astoria Generating Station | Astoria, NY | 870.9 GWh | 4.3 mi |
| Fordham University | Bronx, NY | 6.0 MWh | 1.3 mi |
| Fuel Cell 3245 Yates Avenue | Bronx, NY | 40.2 GWh | 2.3 mi |
| Harlem River Yard | Bronx, NY | 109.7 GWh | 3.7 mi |
| Hell Gate | Bronx, NY | 105.5 GWh | 3.6 mi |
| Montefieor Medical Center Moses Division | Bronx, NY | 31.9 GWh | 2.6 mi |
| Montefiore - Westchester Square | Bronx, NY | 9.0 MWh | 1.5 mi |
| Montefiore Mount Vernon Hospital | Mount Vernon, NY | 12.0 MWh | 4.1 mi |
| Mt. Sinai- Morningside | New York, NY | 17.0 MWh | 6 mi |
| New York Presbyterian Hospital-168th St | New York, NY | 60.0 MWh | 3.4 mi |
| New York University Central Plant | New York, NY | 74.3 GWh | 4.5 mi |
| NY - PANYNJ - LaGuardia - Rooftop | Queens, NY | 999.0 MWh | 4.9 mi |
| NY Times Daily Production Facility | Flushing, NY | 409.0 MWh | 5.3 mi |
| Riverbay | New York, NY | 130.1 GWh | 3.3 mi |
| The Allen Hospital | New York, NY | 12.0 MWh | 2.8 mi |
| The Mount Sinai Hospital | New York, NY | 184.0 MWh | 5.5 mi |
| Zeltmann | Astoria, NY | 3.2 TWh | 4.1 mi |