995 Mile 46 Road, Hooker, OK 73945Plant Summary Information
Tri County - TenK is ranked #15 out of 15 solar farms in Oklahoma in terms of total annual net electricity generation.
Tri County - TenK generated 588.0 MWh during the 3-month period between March 2024 to June 2024.
Plant Name | Tri County - TenK |
---|---|
Utility Name | Today's Power, Inc. |
Location | Texas County, OK |
Initial Operation Date | April 2016 |
Last Update | Jun 2024 |
Annual Generation | 954.0 MWh |
Annual Consumption | 3.3 k MMBtu |
Ranked #11,247 out of 12,299 Power Plants Nationwide | |
Ranked #5,931 out of 6,182 Solar Power Plants Nationwide | |
Ranked #128 out of 132 Oklahoma Power Plants | |
Ranked #15 out of 15 Oklahoma Solar Power Plants | |
Fuel Types | Solar |
Map of Tri County - TenK
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Tri County - TenK.
Monthly Net Generation for Tri County - TenK
Tri County - TenK Details
Summary Information | |
---|---|
Plant Name | Tri County - TenK (68725) |
Plant Address | 995 Mile 46 Road, Hooker, OK 73945 |
Utility | Today's Power, Inc. (61204) |
Latitude, Longitude | 36.86354, -101.19399 |
Generation Dates on File | Jan 2024 to Jun 2024 |
Initial Operation Date | April 2016 |
Annual Generation | 954.0 MWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Tri-County Electric Coop, Inc (OK) (19160) OK |
Grid Voltage | 12.47 kV / 0.48 kV |
Energy Storage | No |
Generator TRICO Details Operating April 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 1 MW |
Summer Capacity | 1 MW |
Winter Capacity | 1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | April 2016 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 1.6 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Tri County - TenK Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#5921 | IMPA Rensselaer Solar Park | Rensselaer, IN | 985.0 MWh |
#5922 | Crown Cooling Facility | Brawley, CA | 982.0 MWh |
#5923 | Novel Kanewischer Solar CSG | Waseca, MN | 982.0 MWh |
#5924 | NEDC Solar Site | Whitinsville, MA | 979.0 MWh |
#5925 | CBS Television City | Los Angeles, CA | 977.0 MWh |
#5926 | Marion Solar 4b LLC | Sandoval, IL | 970.0 MWh |
#5927 | FECC Solar Benton | Benton, AR | 967.0 MWh |
#5928 | Caldwell Wastewater Treatment Plant Hybr | West Caldwell, NJ | 967.0 MWh |
#5929 | Delano Land 1 | Delano, CA | 963.0 MWh |
#5930 | Sacramento Fairbain Water Treatment Plan | Sacramento, CA | 961.0 MWh |
#5932 | Kohls San Bernardino Solar Facility | San Bernardino, CA | 944.0 MWh |
#5933 | Severson Garden | Waseca, MN | 943.0 MWh |
#5934 | Alexander Road Solar | Batavia, NY | 943.0 MWh |
#5935 | UMASS | Amherst, MA | 941.0 MWh |
#5936 | Northline Solar CSG | Schaghticoke, NY | 936.0 MWh |
#5937 | Ozarks Natural Energy Community Solar | Springdale, AR | 935.0 MWh |
#5938 | IKEA Memphis 508 | Cordova, TN | 934.0 MWh |
#5939 | Dakota Solar 1, LLC | Dakota, IL | 933.0 MWh |
#5940 | IKEA Tejon 345 | Lebec, CA | 929.0 MWh |
#5941 | Stafford Hill Solar Hybrid | Rutland, VT | 923.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Tri County - TenK.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arkalon Ethanol LLC | Liberal, KS | 12.5 GWh | 27.5 mi |
Balko Wind LLC | Balko, OK | 934.2 GWh | 30.6 mi |
Bluestem | Beaver, OK | 799.3 GWh | 39.9 mi |
Buffalo Dunes Wind Project | Satanta, KS | 880.2 GWh | 52.7 mi |
Cimarron River | Liberal, KS | 57.7 GWh | 31.5 mi |
Filet Wind (5) LLC | Stratford, TX | 3.3 GWh | 47.6 mi |
Goodwell Wind Project LLC | Goodwell, OK | 712.6 GWh | 30.3 mi |
Gray County Wind Energy | Montezuma, KS | 264.1 GWh | 68.5 mi |
Great Plains Windpark LLC | Spearman, TX | 107.1 GWh | 27.6 mi |
Great Prairie Wind | Gruver, TX | 4.1 TWh | 42.8 mi |
Hugoton 2 | Hugoton, KS | 13.7 MWh | 22.3 mi |
Johnson | Johnson, KS | 31.0 MWh | 57.5 mi |
Johnson Corner Solar 1 | Johnson City, KS | 39.2 GWh | 57.8 mi |
Meade | Meade, KS | 85.0 MWh | 55.7 mi |
Palo Duro Wind | Perryton, TX | 769.8 GWh | 44.1 mi |
Ponderosa Wind Energy Center | Beaver, OK | 947.8 GWh | 36 mi |
Ponderosa Wind II | Balko, OK | 192.3 GWh | 28.7 mi |
Porterhouse Wind (4) LLC | Gruver, TX | 8.7 GWh | 32.8 mi |
Rubart | Ulysses, KS | 40.9 GWh | 48.3 mi |
Tenderloin Wind (6) LLC | Texhoma, TX | 4.4 GWh | 44.3 mi |