Saluda Lexington

6065 Bush River Road, Columbia, SC 29212

Plant Summary Information

Saluda Lexington is ranked #8 out of 27 hydroelectric power plants in South Carolina in terms of total annual net electricity generation.

Saluda Lexington is comprised of 5 generators and generated 7.9 GWh during the 3-month period between September 2025 to December 2025.

Plant NameSaluda Lexington
Utility NameDominion Energy South Carolina, Inc
LocationLexington County, SC
Initial Operation DateAugust 1930
Last Update Dec 2025
Annual Generation 91.5 GWh
Annual Consumption 359.7 k MMBtu
Ranked #3,601 out of 13,081 Power Plants Nationwide
Ranked #345 out of 1,311 Water Power Plants Nationwide
Ranked #51 out of 202 South Carolina Power Plants
Ranked #8 out of 27 South Carolina Water Power Plants
Fuel Types Water
Previous Operator South Carolina Electric&Gas Company (2013 to 2017)
Dominion Energy South Carolina, Inc (2018 to 2025)

Map of Saluda Lexington

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Saluda Lexington.

Create Your Account Today

Monthly Net Generation for Saluda Lexington

Monthly Plant Fuel Consumption for Saluda Lexington

Saluda Lexington Details

Summary Information
Plant NameSaluda Lexington (3293)
Plant Address6065 Bush River Road, Columbia, SC 29212
UtilityDominion Energy South Carolina, Inc (17539)
Latitude, Longitude34.0533, -81.2172
Generation Dates on FileJan 2001 to Dec 2025
Initial Operation DateAugust 1930
Annual Generation 91.5 GWh
Fuel Types Water
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusRegulated
NERC RegionSERC
Balancing AuthorityDominion Energy South Carolina (SCEG)
NAICS CodeUtilities (22)
Sector Electric Utility (1)
Water SourceLake Murray
Ash Impoundment No
Transmission / Distribution OwnerDominion Energy South Carolina (17539) SC
Grid Voltage 115.00 kV
Energy StorageNo

Generator 1 Details Operating August 1930

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity32.5 MW
Nameplate Power Factor0.8
Summer Capacity32.5 MW
Winter Capacity32.5 MW
Minimum Load1.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 1930
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Planned Net Summer Capacity Uprate8 MW
Planned Net Winter Capacity Uprate8 MW
Planned UprateJune 2027
Multiple FuelsNo

Generator 2 Details Operating August 1930

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity32.5 MW
Nameplate Power Factor0.8
Summer Capacity32.5 MW
Winter Capacity32.5 MW
Minimum Load1.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 1930
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Planned Net Summer Capacity Uprate8 MW
Planned Net Winter Capacity Uprate8 MW
Planned UprateDecember 2029
Multiple FuelsNo

Generator 3 Details Operating August 1930

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity42.3 MW
Nameplate Power Factor0.9
Summer Capacity35 MW
Winter Capacity35 MW
Minimum Load2 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 1930
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Planned Net Summer Capacity Uprate8 MW
Planned Net Winter Capacity Uprate8 MW
Planned UprateDecember 2028
Multiple FuelsNo

Generator 4 Details Operating August 1930

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity32.5 MW
Nameplate Power Factor0.8
Summer Capacity32.5 MW
Winter Capacity32.5 MW
Minimum Load1.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 1930
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Planned Net Summer Capacity Uprate8 MW
Planned Net Winter Capacity Uprate8 MW
Planned UprateDecember 2030
Multiple FuelsNo

Generator 5 Details Operating July 1971

TechnologyConventional Hydroelectric
Prime MoverHydroelectric Turbine
OwnershipSingle Owner
Nameplate Capacity67.5 MW
Nameplate Power Factor0.9
Summer Capacity66 MW
Winter Capacity66 MW
Minimum Load4 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJuly 1971
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWater
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Planned Net Summer Capacity Uprate10 MW
Planned Net Winter Capacity Uprate10 MW
Planned UprateDecember 2031
Multiple FuelsNo

Saluda Lexington Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Water.

RankPlant NamePlant LocationAnnual Generation
#335Fort Patrick HenryKingsport, TN94.8 GWh
#336Beaver Dam (AR)Eureka Springs, AR94.6 GWh
#337TugaloTallulah Falls, GA93.9 GWh
#338Lake Lynn Hydro StationLake Lynn, PA93.9 GWh
#339Falls HydroBadin, NC93.6 GWh
#340ShepaugSouthbury, CT93.3 GWh
#341WinfieldWinfield, WV93.0 GWh
#342Horse MesaApache Junction, AZ92.6 GWh
#343Upper Salmon AHagerman, ID92.6 GWh
#344Shoshone (CO)Glenwood Springs, CO91.8 GWh
#346Bennetts BridgeAltmar, NY90.4 GWh
#347Stewarts BridgeCorinth, NY90.4 GWh
#348Mountain IslandMount Holly, NC90.0 GWh
#349Muck Valley HydroelectricNA, CA89.8 GWh
#350Union ValleyFresh Pond, CA89.1 GWh
#351Upper Salmon BHagerman, ID89.1 GWh
#352Laurel DamLondon, KY88.8 GWh
#353Navajo DamFarmington, NM88.3 GWh
#354Goat RockSmiths, AL88.1 GWh
#355Smith (NH)Berlin, NH87.5 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Saluda Lexington.

Plant NamePlant LocationAnnual GenerationDistance
Allora Solar, LLCGilbert, SC154.7 GWh14.9 mi
Beulah SolarBatesburg, SC149.0 GWh21.6 mi
Catalina Solar (SC)Batesburg, SC80.0 GWh24.3 mi
Champion SolarPelion, SC10.6 GWh18.1 mi
Coit GTColumbia, SC2.0 GWh11.3 mi
Columbia Energy Center (SC)Gaston, SC2.8 TWh17.1 mi
Diamond SolarPelion, SC5.2 GWh18.7 mi
Fairfield Pumped StorageJenkinsville, SC450.6 GWh18.6 mi
Gaston IISwansea, SC11.3 GWh20 mi
Gaston Solar I - SCGaston, SC16.5 GWh20.2 mi
Gunsight Solar, LLCSwansea, SC170.3 GWh22 mi
Hecate Energy West Newberry, LLCNewberry, SC6.2 GWh28.2 mi
McMeekinColumbia, SC385.7 GWh0.2 mi
Midway Green SolarUnion, SC20.5 GWh27.3 mi
Odyssey SolarPelion, SC13.3 GWh18.4 mi
Otarre Solar ParkCayce, SC2.8 GWh12.6 mi
Parr HydroJenkinsville, SC53.3 GWh15.8 mi
Richland County LandfillLugoff, SC5.1 GWh24.7 mi
Swamp Fox SolarPelion, SC21.0 GWh18.2 mi
V C SummerJenkinsville, SC6.9 TWh17.8 mi