Montgomery County Resource Recovery

21204 Martinsburg Rd, Dickerson, MD 20842

Plant Summary Information

Montgomery County Resource Recovery is ranked #17 out of 57 non-biogenic municipal solid waste power plants nationwide in terms of total annual net electricity generation.

Montgomery County Resource Recovery is comprised of 1 generator and generated 61.0 GWh during the 3-month period between June 2025 to September 2025.

Plant NameMontgomery County Resource Recovery
Utility NameCovanta Montgomery, Inc.
LocationMontgomery County, MD
Initial Operation DateMay 1995
Last Update Sep 2025
Annual Generation 289.0 GWh
Annual Consumption 6.2 M MMBtu
Ranked #1,996 out of 12,539 Power Plants Nationwide
Ranked #17 out of 57 NON-Biogenic Municipal Solid Waste Power Plants Nationwide
Ranked #11 out of 200 Maryland Power Plants
Ranked #2 out of 2 Maryland NON-Biogenic Municipal Solid Waste Power Plants
Fuel Types Non-biogenic Municipal Solid Waste : 54.6% Biogenic Municipal Solid Waste : 44.6% Natural Gas : 0.8%

Map of Montgomery County Resource Recovery

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Montgomery County Resource Recovery.

Create Your Account Today

Monthly Net Generation for Montgomery County Resource Recovery

Montgomery County Resource Recovery Details

Summary Information
Plant NameMontgomery County Resource Recovery (50657)
Plant Address21204 Martinsburg Rd, Dickerson, MD 20842
UtilityCovanta Montgomery, Inc. (49760)
Latitude, Longitude39.2006, -77.4556
Generation Dates on FileJan 2001 to Sep 2025
Initial Operation DateMay 1995
Annual Generation 289.0 GWh
Fuel Types Non-biogenic Municipal Solid Waste : 54.6% Biogenic Municipal Solid Waste : 44.6% Natural Gas : 0.8%
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number90-185-001
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionRFC
Balancing AuthorityPJM Interconnection, LLC (PJM)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water SourcePotomac River
Ash Impoundment No
Transmission / Distribution OwnerPotomac Electric Power Co (15270) MD
Grid Voltage 69.00 kV
Energy StorageNo

Generator GEN1 Details Operating May 1995

TechnologyMunicipal Solid Waste
Prime MoverSteam Turbine
OwnershipWholly Owned by Other Entity
RTO ISO LMP Node Designation50825
RTO ISO Location Designation For Reporting Wholesale Sales Data50825
Nameplate Capacity67.8 MW
Nameplate Power Factor0.97
Summer Capacity54 MW
Winter Capacity56 MW
Minimum Load1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 1995
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceMunicipal Solid Waste
Startup SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load12H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Montgomery County Resource Recovery Plant Owners

Owner NameAddressOwnership
Northeast Maryland W D AuthSuite 210525 South Charles Street, Baltimore, MD 21201100.00%

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Non-biogenic Municipal Solid Waste.

RankPlant NamePlant LocationAnnual Generation
#7Wheelabrator BridgeportBridgeport, CT473.1 GWh
#8Wheelabrator South BrowardFt. Lauderdale, FL454.8 GWh
#9Wheelabrator WestchesterPeekskill, NY384.0 GWh
#10Pinellas County Resource RecoverySt. Petersburg, FL342.3 GWh
#11H PowerKapolei, HI340.8 GWh
#12Palm Beach Renewable Energy Facility 1West Palm Beach, FL335.4 GWh
#13Wheelabrator Millbury FacilityMillbury, MA317.5 GWh
#14Lee County Solid Waste EnergyFort Myers, FL300.7 GWh
#15Wheelabrator Baltimore RefuseBaltimore, MD295.2 GWh
#16Union County Resource RecoveryRahway, NJ288.3 GWh
#18Wheelabrator FallsMorrisville, PA266.9 GWh
#19Wheelabrator North AndoverNorth Andover, MA233.1 GWh
#20Wheelabrator SaugusSaugus, MA226.1 GWh
#21York County Resource RecoveryYork, PA222.2 GWh
#22Covanta HaverhillHaverhill, MA226.4 GWh
#23Onondaga County Resource RecoveryJamesville, NY206.3 GWh
#24Reworld Plymouth LLCConshohocken, PA205.0 GWh
#25Huntington Resource Recovery FacilityEast Northport, NY198.1 GWh
#26Hillsborough County Resource RecoveryTampa, FL188.6 GWh
#27Lancaster County Resource RecoveryBrainbridge, PA183.1 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Montgomery County Resource Recovery.

Plant NamePlant LocationAnnual GenerationDistance
Blake Solar PlantCharles Town, WV160.2 GWh20.7 mi
Boyd SoccerplexBoyds, MD354.0 MWh8.4 mi
Brookville Smart Bus Depot MicrogridSilver Spring, MD2.1 GWh25.5 mi
Cannonball Solar (CSG)Thurmont, MD1.5 GWh24 mi
Chaberton Solar CatherineCooksville, MD3.1 GWh25.4 mi
Dickerson PowerDickerson, MD173.7 GWh0.8 mi
Fort Detrick Solar PVFrederick, MD20.6 GWh16.5 mi
Francis Scott Key MallFrederick, MD1.3 GWh13 mi
Frederick County - LandfillFrederick, MD2.3 GWh13.2 mi
Millville Hydro StationMillville, WV8.6 GWh18.3 mi
MNCPPC Germantown SolarBoyds, MD1.6 GWh8.2 mi
MO33 CSGGaithersburg, MD3.3 GWh18 mi
Montgomery County Correctional FacilityBoyds, MD2.0 GWh9.1 mi
Montgomery County SolarGaithersburg, MD2.7 GWh13.2 mi
NIH Cogeneration FacilityBethesda, MD153.3 GWh23.8 mi
NIST SolarGaithersburg, MD5.6 GWh13.8 mi
Oaks Landfill - ANEMGaithersburg, MD2.7 GWh18 mi
Oaks Landfill CS 1Gaithersburg, MD2.6 GWh18 mi
Oaks Landfill CS 2Gaithersburg, MD2.7 GWh18 mi
Potomac Energy Center, LLCLeesburg, VA4.6 TWh11 mi