Independence II Solar Farm
2400 S Maywood Ave, Independence, MO 64052Plant Summary Information
Independence II Solar Farm is ranked #2 out of 24 solar farms in Missouri in terms of total annual net electricity generation.
Independence II Solar Farm generated 3.3 GWh during the 3-month period between November 2023 to February 2024.
Plant Name | Independence II Solar Farm |
---|---|
Utility Name | MC Power Companies Inc |
Location | Jackson County, MO |
Initial Operation Date | June 2018 |
Last Update | Feb 2024 |
Annual Generation | 16.2 GWh |
Annual Consumption | 55.4 k MMBtu |
Ranked #5,241 out of 11,455 Power Plants Nationwide | |
Ranked #1,155 out of 5,173 Solar Power Plants Nationwide | |
Ranked #58 out of 119 Missouri Power Plants | |
Ranked #2 out of 24 Missouri Solar Power Plants | |
Fuel Types | Solar |
Map of Independence II Solar Farm
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Independence II Solar Farm.
Monthly Net Generation for Independence II Solar Farm
Independence II Solar Farm Details
Summary Information | |
---|---|
Plant Name | Independence II Solar Farm (61588) |
Plant Address | 2400 S Maywood Ave Independence, MO 64052 |
Utility | MC Power Companies Inc (58822) |
Latitude, Longitude | 39.04, -94.27 |
Generation Dates on File | Jun 2018 to Feb 2024 |
Initial Operation Date | June 2018 |
Annual Generation | 16.2 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | QF18-1131-000,QF18-1202-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Independence - (MO) (9231) MO |
Grid Voltage | 13.20 kV |
Energy Storage | No |
Generator 1 Details Operating June 2018
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 4.1 MW |
Summer Capacity | 4.1 MW |
Winter Capacity | 4.1 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 25 |
DC Net Capacity | 4.9 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator 2 Details Operating June 2018
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 4.4 MW |
Summer Capacity | 4.4 MW |
Winter Capacity | 4.4 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | June 2018 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 25 |
DC Net Capacity | 5.8 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Independence II Solar Farm Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
Gardner Capital | 4803 S National Ste 300, Springfield, MO 65810 | Generator 1 | 100.00% |
Gardner Capital | 4803 S National Ste 300, Springfield, MO 65810 | Generator 2 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1145 | Covington Solar Farm | Covington, OK | 16.6 GWh |
#1146 | SR DeSoto III | DeSoto, GA | 16.6 GWh |
#1147 | Camp Ripley Solar | Little Falls, MN | 16.6 GWh |
#1148 | Cereal City Solar, LLC | Battle Creek, MI | 16.5 GWh |
#1149 | Lake Mabel Solar | Lake Wales, FL | 16.4 GWh |
#1150 | Beautyberry | Clewiston, FL | 16.4 GWh |
#1151 | Oxford PV - BD Solar Oxford LLC | Oxford, ME | 16.4 GWh |
#1152 | Arche Energy Project, LLC | Fulton, OH | 16.3 GWh |
#1153 | Crystal Hill Solar | Crystal Hill, VA | 16.3 GWh |
#1154 | Silver Palm | TBD, FL | 16.3 GWh |
#1156 | Los Lunas Solar Energy Center | Los Lunas, NM | 16.1 GWh |
#1157 | Big Bend | Apollo Beach, FL | 5.5 TWh |
#1158 | NJ Oak Solar Plant | Bridgetown, NJ | 16.1 GWh |
#1159 | Indy Solar I, LLC | Indianapolis, IN | 16.0 GWh |
#1160 | IBM Solar | Boulder, CO | 16.0 GWh |
#1161 | Indy Solar II, LLC | Indianapolis, IN | 16.0 GWh |
#1162 | Tracy Solar | Bailey, NC | 16.0 GWh |
#1163 | Space Coast Next Gen Solar Energy | Merritt Island, FL | 16.0 GWh |
#1164 | Wilson Solar Farm 6 | Wilson, NC | 15.9 GWh |
#1165 | Turnpike | Vero Beach, FL | 15.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Independence II Solar Farm.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
BPU Solar Farm | Kansas City, KS | 1.9 GWh | 24.5 mi |
Dogwood Energy Facility | Pleasant Hill, MO | 2.9 TWh | 17.1 mi |
Gardner Energy Center | Gardner, KS | 41.2 MWh | 36.3 mi |
Grand Ave Plant | Kansas City, MO | 44.0 GWh | 17.4 mi |
Greenwood (MO) | Greenwood, MO | 113.5 GWh | 12.4 mi |
Hawthorn | Kansas City, MO | 2.5 TWh | 12.8 mi |
Higginsville | Higginsville, MO | 12.5 GWh | 29.9 mi |
Higginsville Solar Farm | Higginsville, MO | 4.6 GWh | 29.3 mi |
Holden | Holden, MO | 195.9 GWh | 24.6 mi |
Iatan | Weston, MO | 5.1 TWh | 47.3 mi |
Independence Solar Farm | Independence, MO | 5.8 GWh | 5.4 mi |
Jackson Square | Independence, MO | 2.0 GWh | 8.5 mi |
Nearman Creek | Kansas, KS | 825.5 GWh | 24.6 mi |
Northeast (MO) | Kansas City, MO | 13.1 GWh | 16.6 mi |
Quindaro | Kansas, KS | 10.9 GWh | 21.1 mi |
Ralph Green | Pleasant Hill, MO | 24.9 GWh | 17.4 mi |
South Harper | Kansas City, MO | 216.6 GWh | 27.4 mi |
Station H | Independence, MO | 2.7 GWh | 7.5 mi |
Station I | Independence, MO | 3.1 GWh | 6.7 mi |
West Gardner | Johnson, KS | 181.6 GWh | 42.3 mi |