Holly Spring Meadows
5503 Marlboro Pike, District Heights, MD 20747Plant Summary Information
Holly Spring Meadows is ranked #147 out of 190 solar farms in Maryland in terms of total annual net electricity generation.
Holly Spring Meadows generated 323.0 MWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Holly Spring Meadows |
|---|---|
| Utility Name | Standard Solar |
| Location | Prince George's County, MD |
| Initial Operation Date | July 2023 |
| Last Update | Dec 2025 |
| Annual Generation | 2.0 GWh |
| Annual Consumption | 7.1 k MMBtu |
| Ranked #11,022 out of 13,301 Power Plants Nationwide | |
| Ranked #5,872 out of 7,209 Solar Power Plants Nationwide | |
| Ranked #186 out of 232 Maryland Power Plants | |
| Ranked #147 out of 190 Maryland Solar Power Plants | |
| Fuel Types | Solar |
Map of Holly Spring Meadows
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Holly Spring Meadows.
Monthly Net Generation for Holly Spring Meadows
Monthly Plant Fuel Consumption for Holly Spring Meadows
Holly Spring Meadows Details
| Summary Information | |
|---|---|
| Plant Name | Holly Spring Meadows (66819) |
| Plant Address | 5503 Marlboro Pike, District Heights, MD 20747 |
| Utility | Standard Solar (60531) |
| Latitude, Longitude | 38.86209, -76.91249 |
| Generation Dates on File | Aug 2023 to Dec 2025 |
| Initial Operation Date | July 2023 |
| Annual Generation | 2.0 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | RFC |
| Balancing Authority | PJM Interconnection, LLC (PJM) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | NA |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Potomac Electric Power Co (15270) MD |
| Grid Voltage | 12.07 kV |
| Energy Storage | No |
Generator HOLLY Details Operating July 2023
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 1.2 MW |
| Summer Capacity | 1.2 MW |
| Winter Capacity | 1.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 2023 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Fixed Tilt | No |
|---|---|
| East West Fixed Tilt | Yes |
| Tilt Angle | 13 |
| DC Net Capacity | 1.7 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | Yes |
| Net Metering DC Capacity | 1.2 MW |
| Virtual Net Metering Agreement | No |
Holly Spring Meadows Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #5862 | Olinda Trail Solar | Lindstrom, MN | 2.0 GWh |
| #5863 | Hayfield Solar III LLC CSG | Hayfield, MN | 2.0 GWh |
| #5864 | Blue Moon Farms | Tipton, CA | 2.0 GWh |
| #5865 | Bellflower Solar, LLC | Brooten, MN | 2.0 GWh |
| #5866 | Novel Milbradt Solar LLC | Belview, MN | 2.0 GWh |
| #5867 | FedEx Chicago Solar Facility | Bedford Park, IL | 2.0 GWh |
| #5868 | Lineage Logistics Solar | University Park, IL | 2.0 GWh |
| #5869 | LSE Pavo Solar | Walton, NY | 2.0 GWh |
| #5870 | Ace Solar | Piedmont, SC | 2.0 GWh |
| #5871 | Solar Star Palo Alto I, LLC | Palo Alto, CA | 2.0 GWh |
| #5873 | New Munich Solar | Melrose, MN | 2.0 GWh |
| #5874 | Freeze Solar | Dayton, NJ | 2.0 GWh |
| #5875 | Westar Cities Solar | Hutchinson, KS | 2.0 GWh |
| #5876 | BP-Kanza | Pratt, KS | 2.0 GWh |
| #5877 | Mashpee Landfill Solar | Mashpee, MA | 2.0 GWh |
| #5878 | Primrose Solar, LLC | Mankato, MN | 2.0 GWh |
| #5879 | Greene County Meter #1 | Cairo, NY | 2.0 GWh |
| #5880 | SolarClub 03 | Starbuck, MN | 2.0 GWh |
| #5881 | SAU Tech | Bearden, AR | 2.0 GWh |
| #5882 | Buffalo Lake CSG1, LLC | Buffalo Lake, MN | 2.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Holly Spring Meadows.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AOC, Capitol Power Plant | Washington, DC | 54.4 GWh | 5.3 mi |
| Beech Road (CSG) | Temple Hill, MD | 7.9 GWh | 3 mi |
| DC Water | Washington, DC | 257.0 MWh | 5.3 mi |
| First Baptist Church of Glenarden | Upper Marlboro, MD | 2.7 GWh | 3.7 mi |
| Gallaudet Uni Community Solar | Washington, DC | 1.7 GWh | 5.4 mi |
| JBAB - Washington DC | Washington, DC | 7.9 GWh | 5.2 mi |
| Kirby Road Solar, LLC | Clinton, MD | 2.4 GWh | 5.8 mi |
| Nationals | Washington, DC | 1.6 GWh | 5.1 mi |
| NCS FCPA LLC | Washington, DC | 1.2 GWh | 2.5 mi |
| NCS Paradise LLC | Washington, DC | 1.6 GWh | 3.7 mi |
| Oxon Run CREF | Washington, DC | 1.0 GWh | 5.6 mi |
| Ridgecrest | Washington, DC | 1.6 GWh | 3.6 mi |
| Sheriff Road | Hyattsville, MD | 1.8 GWh | 3.5 mi |
| Sol Phoenix | Capitol Heights, MD | 3.7 GWh | 2.2 mi |
| V Street Solar | Washington, DC | 803.0 MWh | 5.7 mi |
| WMATA - Anacostia CSG | Washington, DC | 1.7 GWh | 4.4 mi |
| WMATA - Cheverly Metro (CSG) | Cheverly, MD | 2.4 GWh | 3.7 mi |
| WMATA - Naylor Rd. Metro | Temple Hills, MD | 2.6 GWh | 2.5 mi |
| WMATA - S. Ave. Carport (East) (CSG) | Hillcrest Heights, MD | 2.5 GWh | 3.7 mi |
| WW-DC Solar 1, LLC | Washington, DC | 962.0 MWh | 5.4 mi |