Blackstone/Tupperware
2 Tupperware Drive, North Smithfield, RI 2917Plant Summary Information
Blackstone/Tupperware is ranked #2 out of 2 hydroelectric power plants in Rhode Island in terms of total annual net electricity generation.
Blackstone/Tupperware is comprised of 4 generators and generated 827.0 MWh during the 3-month period between February 2026 to May 2026.
| Plant Name | Blackstone/Tupperware |
|---|---|
| Utility Name | Blackstone Hydro Inc. |
| Location | Providence County, RI |
| Initial Operation Date | January 1981 |
| Last Update | May 2026 |
| Annual Generation | 1.8 GWh |
| Annual Consumption | 7.7 k MMBtu |
| Ranked #11,219 out of 13,081 Power Plants Nationwide | |
| Ranked #1,254 out of 1,311 Water Power Plants Nationwide | |
| Ranked #98 out of 106 Rhode Island Power Plants | |
| Ranked #2 out of 2 Rhode Island Water Power Plants | |
| Fuel Types | Water |
Map of Blackstone/Tupperware
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Blackstone/Tupperware.
Monthly Net Generation for Blackstone/Tupperware
Monthly Plant Fuel Consumption for Blackstone/Tupperware
Blackstone/Tupperware Details
| Summary Information | |
|---|---|
| Plant Name | Blackstone/Tupperware (50177) |
| Plant Address | 2 Tupperware Drive, North Smithfield, RI 2917 |
| Utility | Blackstone Hydro Inc. (56844) |
| Latitude, Longitude | 42.01447, -71.5444 |
| Generation Dates on File | Jan 2001 to May 2026 |
| Initial Operation Date | January 1981 |
| Annual Generation | 1.8 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | 88-104-001 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | ISO New England Inc. (ISNE) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Blackstone River |
| Ash Impoundment | No |
| Transmission / Distribution Owner | The Narragansett Electric Co (13214) RI |
| Grid Voltage | 13.80 kV |
| Energy Storage | No |
Generator GEN1 Details Operating January 1981
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.99 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1981 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
Generator GEN2 Details Operating January 1981
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.99 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1981 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
Generator GEN3 Details Operating January 1981
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.99 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1981 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
Generator GEN4 Details Operating January 1981
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.99 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1981 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
Blackstone/Tupperware Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1244 | Chasm Hydro Partnership | Chateaugay, NY | 1.9 GWh |
| #1245 | Great Falls (VT) | Lyndon, VT | 1.9 GWh |
| #1246 | Timothy Lake Powerhouse | Estacada, OR | 1.9 GWh |
| #1247 | Diamond Island Plant | Watertown, NY | 1.8 GWh |
| #1248 | Granite Falls | Granite Falls, MN | 1.8 GWh |
| #1249 | Kosterville | Lyonsdale, NY | 1.8 GWh |
| #1250 | Smith (VT) | Bradford, VT | 1.8 GWh |
| #1251 | Indian River Hydro | Russell, MA | 1.8 GWh |
| #1252 | Skookumchuck | Tenino, WA | 1.8 GWh |
| #1253 | Toadtown | Magalia, CA | 1.8 GWh |
| #1255 | Site 980 65 | Madera, CA | 1.8 GWh |
| #1256 | Ada Dam | Ada, MI | 1.7 GWh |
| #1257 | Deweys Mill | White River Jct., VT | 1.7 GWh |
| #1258 | Big Quinnesec 61 | Iron Mountain, MI | 1.7 GWh |
| #1259 | Salida | Salida, CO | 1.7 GWh |
| #1260 | Bartholomew | Springville, UT | 1.6 GWh |
| #1261 | Prairie River | Grand Rapids, MN | 1.6 GWh |
| #1262 | Pelican | Pelican, AK | 1.7 GWh |
| #1263 | Waterman Turnout Hydroelectric | San Bernardino, CA | 1.6 GWh |
| #1264 | C-Drop Hydro | Klamath Falls, OR | 1.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Blackstone/Tupperware.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| ANP Blackstone Energy Project | Blackstone, MA | 2.9 TWh | 3.5 mi |
| BJ's Wholesale Club, Inc- Uxbridge | Uxbridge, MA | 270.0 MWh | 3.1 mi |
| Brookside | North Smithfield, RI | 969.0 MWh | 2.8 mi |
| BWC Wading River One, Two, Three CSG | Mendon, MA | 1.6 GWh | 5 mi |
| Douglas Pike Solar, LLC | Burrillville, RI | 3.3 GWh | 4.4 mi |
| GDIM 1, LLC | North Smithfield, RI | 15.0 GWh | 3.4 mi |
| GDIM 2, LLC | North Smithfield, RI | 12.7 GWh | 3.5 mi |
| GDIM 3, LLC | North Smithfield, RI | 15.1 GWh | 3.8 mi |
| GDIM 4, LLC | North Smithfield, RI | 14.4 GWh | 3.8 mi |
| Hurteau Solar Project Hybrid | Uxbridge, MA | 2.8 GWh | 2.6 mi |
| Kearsarge William Way | Bellingham, MA | 7.3 GWh | 5.4 mi |
| MA Blackstone | Blackstone, MA | 6.6 GWh | 1.2 mi |
| Manville Hill Road Solar | Cumberland, RI | 6.7 GWh | 4.8 mi |
| North Smithfield Solar Power 1 | North Smithfield, RI | 2.1 GWh | 3.4 mi |
| Palombo B Solar, LLC CSG | Uxbridge, MA | 1.6 GWh | 2.8 mi |
| Palombo Solar, LLC CSG | Uxbridge, MA | 3.4 GWh | 2.9 mi |
| Pomham Islander (CSG) | North Smithfield, RI | 1.5 GWh | 4.3 mi |
| Thundermist Hydro | Providence, RI | 3.3 GWh | 1.8 mi |
| Town of Uxbridge MA at Commerce Dr | Uxbridge, MA | 2.4 GWh | 4.3 mi |
| TPE King Solar Holdings1, LLC (CSG) | North Smithfield, RI | 18.3 GWh | 3.1 mi |