HEB00790
6001 Preston, Plano, TX 75093Plant Summary Information
HEB00790 is ranked #312 out of 312 natural gas power plants in Texas in terms of total annual net electricity generation.
HEB00790 is comprised of 3 generators and generated 980.0 kWh during the 3-month period between September 2024 to December 2024.
Plant Name | HEB00790 |
---|---|
Utility Name | Generate ER-NG, LLC |
Location | Collin County, TX |
Initial Operation Date | September 2022 |
Last Update | Dec 2024 |
Annual Generation | 980.0 kWh |
Annual Consumption | 11 MMBtu |
Ranked #12,299 out of 12,299 Power Plants Nationwide | |
Ranked #2,215 out of 2,221 Natural Gas Power Plants Nationwide | |
Ranked #792 out of 792 Texas Power Plants | |
Ranked #312 out of 312 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of HEB00790
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for HEB00790.
Monthly Net Generation for HEB00790
HEB00790 Details
Summary Information | |
---|---|
Plant Name | HEB00790 (67314) |
Plant Address | 6001 Preston, Plano, TX 75093 |
Utility | Generate ER-NG, LLC (64897) |
Latitude, Longitude | 33.05537, -96.79668 |
Generation Dates on File | Dec 2024 to Dec 2024 |
Initial Operation Date | September 2022 |
Annual Generation | 980.0 kWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | ATMOS ENERGY CORPORATION |
Natural Gas Storage | No |
Generator H7901 Details Operating September 2022
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2022 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator H7902 Details Operating September 2022
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2022 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator H7903 Details Operating September 2022
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 0.4 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 0.4 MW |
Winter Capacity | 0.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2022 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
HEB00790 Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#2201 | Robins | Robins AFB, GA | 4.4 GWh |
#2202 | Ubly | Ubly, MI | 11.8 MWh |
#2203 | ABC Coke | Tarrant, AL | 9.0 MWh |
#2204 | Payson | Payson, UT | 4.0 MWh |
#2205 | Anthony | Anthony, KS | 4.0 MWh |
#2206 | Regeneron Pharmaceuticals Inc. | Tarrytown, NY | 2.1 GWh |
#2207 | Osborne | Osborne, KS | 15.7 MWh |
#2208 | Algona | Algona, IA | 507.0 MWh |
#2209 | Good Samaritan Hospital | Suffern, NY | 46.0 MWh |
#2210 | Central Energy Facility | Clemson, SC | 2.0 MWh |
#2211 | Emerson | Emerson, NE | 3.0 MWh |
#2212 | Cadillac Renewable Energy | Cadillac, MI | 135.7 GWh |
#2213 | Water Reclamation Plant | Rochester, MN | 3.9 GWh |
#2214 | Pinellas County Resource Recovery | St. Petersburg, FL | 387.3 GWh |
#2216 | Covanta Marion Inc | Brooks, OR | 53.0 GWh |
#2217 | Stuart (NE) | Stuart, NE | 5.0 MWh |
#2218 | Janesville | Janesville, MN | 20.0 MWh |
#2219 | Glencoe | Glencoe, MN | 182.0 MWh |
#2220 | Cashton | Cashton, WI | 7.8 MWh |
#2221 | Richland Center Renewable Energy LLC | Richland Center, WI | 6.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding HEB00790.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
CoServ Community Solar Station | Aubrey, TX | 1.6 GWh | 18.2 mi |
Farmers Branch Renewable Energy Facility | Lewisville, TX | 23.7 GWh | 9.4 mi |
HEB00055 | Southlake, TX | 211.0 MWh | 21 mi |
HEB00789 | Frisco, TX | 212.0 MWh | 7.5 mi |
HEB00794 | McKinney, TX | 89.0 MWh | 9.2 mi |
HEB00796 | Allen, TX | 156.0 MWh | 9.3 mi |
OTHERBenEKDallas | Dallas, TX | 198.0 MWh | 16.7 mi |
Ray Olinger | Navada, TX | 117.4 GWh | 20 mi |
Spencer | Denton, TX | 10.8 GWh | 20.4 mi |
State Farm Insur Support Center Central | Irving, TX | 7.0 MWh | 14.6 mi |
Toyota HQ Plan | Plano, TX | 6.7 GWh | 3.3 mi |
WAL202 | Frisco, TX | 64.0 MWh | 3.1 mi |
WAL266 | Grapevine, TX | 247.0 MWh | 18.9 mi |
WAL2667 | Dallas, TX | 182.0 MWh | 19.1 mi |
WAL2883 | Plano, TX | 247.0 MWh | 2.9 mi |
WAL3224 | Garland, TX | 168.0 MWh | 18.7 mi |
WAL3406 | Dallas, TX | 175.0 MWh | 6.8 mi |
WAL3777 | Frisco, TX | 61.0 MWh | 10 mi |
WAL5211 | McKinney, TX | 99.0 MWh | 9.6 mi |
WAL5311 | Mckinney, TX | 85.0 MWh | 11.7 mi |